Exciting enhancements are coming soon to eCode360! Learn more 🡪
Town of East Fishkill, NY
Dutchess County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
Any additional drainage facilities not shown on the approved plan and which may be ordered by the Highway Superintendent or the Town Engineer shall be constructed by the developer at his expense and in accordance with this chapter.
A. 
The width of the trench in which the pipe is placed shall be equal to, as a minimum, the outside diameter of the pipe plus an additional two feet. The trench excavation shall conform to Figure VI-1.
B. 
Where soft, spongy or other unstable soil is encountered at the grade established, all such unstable soil up two feet under the pipe and for the total width of the trench shall be removed and replaced with run of bank gravel or other acceptable material.
C. 
Where rock (see § A197-32D) or boulders are encountered, all such rock, and boulders larger than six inches diameter, shall be excavated at least eight inches clear of the pipe. The excavation shall be backfilled with run-of-bank gravel or other acceptable material and properly compacted.
D. 
In all cases the bed and the fill on both sides of the pipe shall be thoroughly compacted and shall provide a firm support for the pipe.
E. 
In general, material removed from the trench during excavation is suitable for final backfill; provided, however, that such material is free of sod, roots, spongy material, pieces of pavement, frozen clumps, lumps or clods of soil, mush, clay, cinders, slag, ashes, rubbish, rocks or pieces of rock measuring more than six inches of diameter.
F. 
Regardless of the type or kind of backfill used, specifications relating to lifts and compaction in § A197-32B shall be observed.
A. 
Pipe shall be laid to a true line and grade on the prepared bed of the trench. Pipe laying shall begin at the downstream end and progress upstream.
B. 
Reinforced concrete pipe shall be sealed with flexible, watertight, elastomeric gaskets, approved bituminous sealers or plastic sealers applied at the time the pipe is being laid to line and grade. Such sealants shall be installed in accordance with the sealant manufacturer's instruction so that the joint is completely filled with the sealant. Mortar joint pipe shall not be used.
C. 
Corrugated pipe and pipe arch field connections shall be constructed so that the corrugated band laps equally on each culvert section.
D. 
Smooth interior corrugated polyethylene pipe shall be installed on a minimum of six inches of suitable bedding material with one inch of suitable run-of-bank gravel placed on both sides and on the top of the pipe. Proper compaction must be achieved. The remainder of the trench shall be backfilled with suitable material having no stone exceeding six inches in diameter.
E. 
When a drainage pipe ends in an open ditch, the ditch shall be excavated as shown on the plan and the excavated area shall be entirely filled with rip-rap.
F. 
The underdrains should be placed as shown on the plan or as ordered by the Highway Superintendent or the Town Engineer. Underdrains shall be placed in trenches and surrounded by material which is both pervious to water and capable of protecting the pipe from infiltration by the surrounding soil (See Figure VI-2). Underdrains shall outlet in a ditch or shall be connected to a basin or manhole.
A. 
Holes for catch basins shall be excavated to a depth of at least 29 inches below the plan elevation of the invert of the outlet pipe. Excavation for the catch basin shall be made at least two feet in the clear around the structure. Crushed stone or run-of-bank gravel shall be placed in the hole to a uniform depth of nine inches and shall be leveled and compacted over the entire area under the base.
B. 
Excavation for the manhole and the manhole foundation shall be made at least two feet in the clear around the structure. Crushed stone or run-of-bank gravel shall be placed in the hole to a uniform depth of nine inches and shall be leveled and compacted over the entire area under the base.
C. 
In areas of high groundwater, minimum four-inch diameter underdains shall be placed to drain into the basin or manhole, in order to relieve hydrostatic pressure. The backfill around the basin or manhole shall be coarse granular material for at least one-foot thickness around the perimeter.
D. 
Assembly of sections.
(1) 
The interior and exterior of catch basins shall be parged at all seams and joints, unless sealed with flexible, watertight, elastomeric gaskets, approved bituminous sealers or plastic sealers. Bituminous or plastic sealants shall be applied at the time the basin is set. Such sealants shall be installed in accordance with the sealant manufacturer's instruction so that the joint is completely filled with sealant. Brick or block shall be mortared in place and parged both inside and outside the basin.
(2) 
Bituminous or plastic joint sealants shall be applied at the time a manhole is set. Such sealants shall be installed in accordance is with the sealant manufacturer's instruction so that the joint is completely filled with the sealant. Rubber gaskets shall be installed per the manufacturer's instructions, especially relating to location, lubrication and setting of manhole sections.
(3) 
All steps in each section shall be aligned to form a continuous ladder with steps being spaced vertically in the assembled basin or manhole at twelve-inch intervals.
E. 
Installation of pipes.
(1) 
The openings around all pipes entering or leaving catch basins (or manholes) shall fit the contours of the pipes as closely as possible. Remaining interstices shall be solidly filled with mortar for the full thickness of the wall. All pipes shall be mortared inside and outside of each basin or manhole.
(2) 
The ends of all pipes shall be flush with the inside surfaces of the catch basin or manhole walls and shall project outside a sufficient distance to allow for the proper connection with an adjoining pipe section. No piping shall extend into the catch basin or manhole.
(3) 
When the diameter of the effluent pipe is greater than that of an influent pipe, the elevation of the crown of the influent pipe shall be no lower than the elevation of the crown of the effluent pipe.
(4) 
When the diameter of the effluent pipe is the same as or smaller than that of an influent pipe, the elevation of the invert of the influent pipe shall be 0.1 foot higher than the elevation of the invert of the effluent pipe.
(5) 
There shall be a minimum 0.1 foot difference in elevation between inlet invert and the outlet invert at each basin or manhole.
F. 
Setting frames and grates or covers.
(1) 
Frames shall be set in a full bed of mortar.
(2) 
The frame shall be set to match the pavement cross slope and to match the roadway profile. Special care shall be taken at intersections to assure that no ponding will occur.
(3) 
The grate or cover shall rest evenly in the frame. If necessary, the parts shall be filed or ground to assure even bearing.
(4) 
Where the curb inlet shape does not match the asphalt curb shape, the gutter lines shall match and the asphalt curb shall be blended/shaped to make a transition between three feet and five feet long.
G. 
Backfill around catch basins and manholes shall comply with the provisions of § A197-32B.
A. 
The general construction requirements of Article III shall apply.
B. 
In addition, all open ditches shall be cleared of all trees, shrubs, rock, boulders and excess material to ensure proper flow of water and ease of maintenance.
C. 
The ditches shall be finished as shown on the plan and in accordance with § A197-46.
A. 
Rip-rap should be sized per § A197-43C and as shown on the plans.
B. 
The largest stones shall be placed first and smaller pieces shall be fitted to chink the voids. The stones shall be placed on a slope not steeper than two to one and so laid that the weight of the larger stones is carried by the soil and not by the adjacent stones.
C. 
It is intended to have a rough surface, but a generally uniform shape conforming to the swale cross section.