At such time as preliminary plans are submitted to the Borough of Moosic, a developer shall also submit three copies of said plans to the Borough along with a request for reserved capacity in the system and the required plan review fee, if so requested by the Borough, is paid in full at the rate established in the Schedule of Tariffs.
After the Borough has determined that the requested flow can be allowed to enter the system from a development, the developer shall submit six copies of preliminary sewer extension plans to the Borough showing the location of sewer mains, sewer main rights-of-way, size of sewer mains, direction of flow, distance of sewer mains from any structure, location of existing mains and manholes to which connection is to be made.
Upon approval of the preliminary sewer extension plans by the Borough and the approval of the preliminary plans by the Planning Commission and payment of any applicable fees by the developer, the developer shall submit to the Borough six copies of the final sewer extension plans with specifications which shall include all rights-of-way at least 30 feet wide, which the developer intends to grant to the Borough, where lines will be outside of public streets, depth of all lines, profile drawings, locations of all manholes, distance of lines from any above or below ground structures, the location of any specialized equipment or pumps. When final sewer extension plans and specifications are submitted the developer shall also file a completed application for a sewer extension permit from the applicable modules, federal agency in the same name of the Borough, and all applicable modules, supporting documents and supplementary reports as required. The final plan review fee must be submitted before any final plan review can be started.
Upon receipt of the permit as issued by the applicable state and/or federal agency, the developer must record the same in the Recorder of Deeds' office located in Lackawanna County Courthouse in Scranton, Pennsylvania, and file proof of same with the Borough.
Prior to starting construction of the new facilities the developer must provide coverage satisfactory to the Borough in both limits and coverage, as may be specified in Article X herein.
Prior to starting construction the developer must deliver to the Borough proof of right-of-way over any lands not owned by the developer but necessary for the sewer extension, including but not limited to the state, county and local highways or trafficways.
The developer shall submit a schedule of construction upon completion of all requirements in this article which will be used to estimate the construction inspection fees. This fee shall be submitted prior to any construction started by the developer.
Construction of new facilities shall be completed within 18 months starting upon acceptance by the Borough of the final sewer extension plans. A time extension may be granted by the Borough and, if time extensions are granted, the developer must submit any necessary fees required by the Borough and such fees shall be used to offset the additional costs of inspection or plan review, and these fees shall be submitted within 10 days of the Borough's request for such fees.