Exciting enhancements are coming soon to eCode360! Learn more 🡪
Township of Upper Burrell, PA
Westmoreland County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
A. 
The developer shall notify the Inspector at least 72 hours prior to beginning any installation of public improvements in an approved plan. While work is in progress, the developer shall notify the Inspector at least 72 hours prior to the time that the following required progress inspections are desired:
(1) 
Inspection of subgrade of streets prior to laying of base;
(2) 
Inspection of base prior to final paving of streets;
(3) 
Inspection on installation of water lines, sanitary sewer lines, storm sewers and drainage facilities before they are covered.
B. 
At the Township Engineer's discretion, an inspector may be required to be present at the site on a continual basis while work is in progress. The cost of providing a full-time or part-time inspector shall be charged to the developer in accordance with § 292-80C of this chapter.
C. 
The Inspector shall maintain a daily report of all inspections. The daily reports shall be turned over to the Township Engineer upon completion of the project.
When the developer has completed the required public improvements in a plan, the developer shall notify the Township Secretary or his/her authorized designee, in writing, by certified or registered mail and shall send a copy thereof to the Township Engineer. Within 10 days of the receipt of such notification, the Board of Supervisors shall authorize the Township Engineer to conduct a final inspection of the public improvements in the plan to determine compliance with the design standards specified in Article VII of this chapter and the Township Construction Standards.
Upon completion of the public improvements in a plan, as-built plans, profiles and calculations for the public improvements, as constructed, shall be filed with the Township by the developer within 10 days of the mailing of the notice of completion. Paper prints and an electronic copy in CAD format acceptable to the Township of each as-built drawing shall be submitted. As-built plans and profiles shall be marked "as-built" and shall contain the final grade of all sanitary and storm sewers and appurtenances. Horizontal angles between sanitary sewer manholes shall be shown.
A. 
Township Engineer's report. Upon authorization by the Board of Supervisors, the Township Engineer shall perform a final inspection of the public improvements in the plan. Within 30 days of receiving the authorization by the Board of Supervisors, the Township Engineer shall file a report, in writing, with the Board of Supervisors indicating approval or rejection of the improvements, either in whole or in part, and in the case of rejection, shall provide a statement of the reasons for such rejection. The Township Engineer shall promptly mail a copy of said report to the developer by certified or registered mail.
B. 
Notification of developer by the Board of Supervisors. The Board of Supervisors shall notify the developer, in writing, by certified mail, within 15 days of receipt of the Township Engineer's report, of the action of the Board of Supervisors with relation to approval or rejection of the public improvements.
C. 
Failure of Township to comply. If the Board of Supervisors or the Township Engineer fails to comply with the time limitation provisions contained in this article, all public improvements will be deemed to have been approved and the developer shall be released from all liability pursuant to the performance guarantee posted with the Township.
D. 
Completion of rejected public improvements. If any portion of the public improvements shall not be approved or shall be rejected by the Board of Supervisors, the developer shall proceed to make the required corrections or additions and, upon completion, the same procedure of notification, inspection and approval, as outlined in this article, shall be followed.
E. 
Developer's rights. Nothing in this article, however, shall be construed to limit the developer's right to contest or question, by legal proceedings or otherwise, any determination of the Board of Supervisors or the Township Engineer.
F. 
Release of performance guarantee.
(1) 
Upon approval of all of the public improvements in the plan, the developer shall be released from any liability pursuant to the performance guarantee posted to guarantee the proper installation of those improvements.
(2) 
From time to time, during the installation of the public improvements, the developer may request partial release of the performance guarantee in an amount necessary for payment of contractors performing the work. Any such request shall be in writing and shall be addressed to the Board of Supervisors. The Board of Supervisors shall have 45 days from the receipt of such request to allow the Township Engineer to certify, in writing, that such portion of the installation of public improvements has been completed in accordance with the requirements of this chapter and the approved final plat.
(3) 
Upon such certification by the Township Engineer, the Board of Supervisors shall authorize release of an amount as estimated by the Township Engineer which fairly represents the value of the improvements completed. The Board of Supervisors shall require retention of 10% of the estimated cost of such improvements until such time as all improvements have been installed and the performance guarantee is released in its entirety.
A. 
Upon completion of the final inspection and approval of the public improvements, the developer shall submit a request to the Board of Supervisors, in writing, to accept the dedication of the public improvements. The request for acceptance shall be submitted at least 10 days prior to the regular meeting of the Board of Supervisors and shall be accompanied by deeds of dedication and legal descriptions for all easements and rights-of-way. At the regular meeting, the Board of Supervisors shall enact an ordinance accepting the public improvements as part of the Township's public facilities, subject to the posting of the maintenance bond required by § 292-31 of this chapter.
B. 
In addition, if construction is not substantially completed on 90% of the lots in the plan at the time that the public improvements are accepted, the developer shall post a bond in an amount determined by the Township Engineer to guarantee installation of the final wearing course on the public streets in the plan.
C. 
No property or public improvements shown on a final plat shall be considered to have been finally accepted by the Township until the dedication thereof has been officially accepted by adoption of an ordinance of the Township, duly enacted and advertised in accordance with law.
A. 
When the Board of Supervisors accepts the dedication of all or some of the required public improvements in a plan, following their completion, the Board of Supervisors shall require the posting of a maintenance bond, as defined by this chapter, to insure the structural integrity of the improvements in accordance with the design standards of Article VII, the Township Construction Standards and the specifications of the final plat.
B. 
The term of the maintenance bond shall be for a period of 18 months from the date of the acceptance of the public improvements by the Board of Supervisors. The amount of the maintenance bond shall be 15% of the actual cost of installation of the public improvements.
In the event that the public improvements required to be installed by the provisions of this chapter are not installed in accordance with the requirements of this chapter or the approved final plat prior to the expiration of the performance guarantee, the Board of Supervisors shall have the power to enforce the performance guarantee by appropriate legal and equitable remedies provided by the laws of the Commonwealth of Pennsylvania. If proceeds from the performance guarantee are insufficient to pay the cost of installing or making repairs or corrections to all the improvements guaranteed by such performance guarantee, the Board of Supervisors may, at its option, install part of such improvements in all or in part of the subdivision or land development and may institute appropriate legal or equitable action to recover the moneys necessary to complete the remainder of the improvements. All of the proceeds, whether resulting from the performance guarantee or from any legal or equitable action brought against the developer, or both, shall be used solely for the installation of the improvements guaranteed by such performance guarantee and not for any other municipal purpose.
The developer shall notify the Code Enforcement Officer at least 72 hours prior to initiating the installation of any of the private improvements. Upon completion of the private improvements, the developer shall request a final inspection by the Inspector. If deficiencies are found, the Code Enforcement Officer shall notify the developer in writing. If the installation of private improvements has been satisfactorily completed in accordance with this chapter and the approved plan, the Code Enforcement Officer shall issue a certificate of completion of site improvements which shall be prerequisite to release of the amenities bond and issuance of a certificate of occupancy under Chapter 350, Zoning.
Upon issuance of a certificate of completion of site improvements by the Code Enforcement Officer, the Township shall release the amenities bond. Approval by the Code Enforcement Officer of private improvements for which an amenities bond has been posted and final release of that amenities bond shall only indicate compliance with the specifications shown on the approved subdivision or land development plan. Such approval and release of the amenities bond shall not imply approval by the Township of the method of construction or the structural integrity of the private improvements, nor shall there be any liability associated with or responsibility for maintenance of those private improvements by the Township. A maintenance bond shall not be required to be posted for private improvements as a condition of release of the amenities bond.