A. 
Application requirements. The applicant shall submit the following:
(1) 
All items as specified and required by Article VI of this chapter.
(2) 
Revised amenities or performance financial security, where revisions to previous approvals warrant an increase in said financial security, as determined by the Township Engineer.
(3) 
All plans and plats otherwise required shall be limited to those specific plans and locations proposed for revision, where amendments to previously approved final land developments and subdivisions are proposed.
B. 
Application acceptance, review, and procedural actions.
(1) 
The Zoning Officer shall review the submitted application within 10 business or working days of submittal. Where an application is found to be deficient by virtue of the submission of an incomplete application or where the application proposes activities which violate any other Township ordinance, the Zoning Officer shall return all submitted materials to the applicant, citing the basis for said deficiencies.
(2) 
The Zoning Officer shall, within five business or working days of submission, forward said plans along with a recommendation to the Chairman of the Planning Commission and Chairman of the Board. In the event that either party presents a reasonable written disagreement, within five days of receipt, with Zoning Officer's recommendation, the plan shall be reviewed at the next regular meeting of the Planning Commission to be processed in the same manner as a minor plan.
(3) 
The Zoning Officer shall submit a copy of the application to the Allegheny County Office of Economic Development for review and shall not act upon the plan until comments are received or 30 days have lapsed since the submittal of the plan to the county planning agency. Additionally, where any similar review is required by an adjoining municipality, as required by any intergovernmental cooperative or implementation agreement entered into by the Township, said municipality shall be afforded the same review period required for the county.
(4) 
In the event of a denial by the Zoning Officer, the Zoning Officer shall, within 15 days of the denial, present a written letter to the applicant informing him of said denial along with express deficiencies found and related ordinance citations, within 90 days of application submittal, unless waived by the applicant in writing. Failure to act within the timeline specified shall result in a deemed approval.
(5) 
In the event of approval or an approval with conditions, the Zoning Officer shall direct the signatures of the Municipal Engineer, Chairman of the Planning Commission, and Chairman of the Board, in addition to his own signature to the plat. The date on which all signatures have been received shall constitute the approval date. Said approval shall occur within 90 days of application submittal, unless waived by the applicant in writing. The Zoning Officer shall provide the applicant written notice of the approval within 15 days of said approval and may attach reasonable conditions as cited in his previous correspondence to the Chairs.
(6) 
Administrative approvals are subject to all post-approval requirements as cited in Article VIII.
(7) 
Any alteration to a recorded developer's agreement or subdivision plat shall be recorded at the Allegheny County Recorder of Deeds within 90 days of approval or shall lose its effect of approval.
A. 
Application requirements. The applicant shall submit the following:
(1) 
All items as specified and required by Article VI of this chapter.
(2) 
Revised amenities or performance bonds, where revisions to previous approvals warrant an increase in said bonds, as determined by the Township Engineer.
(3) 
All plans and plats otherwise required shall be limited to those specific plans and locations proposed for revision, where amendments to previously approved final land developments and are proposed.
B. 
Application acceptance, review, and procedural actions.
(1) 
The Zoning Officer shall review the submitted application within 10 business or working days of submittal. Where an application is found to be deficient by virtue of the submission of an incomplete application or where the application proposes activities which violate any other Township ordinance, the Zoning Officer shall return all submitted materials to the applicant, citing the basis for said deficiencies.
(2) 
The Zoning Officer shall, within five business or working days of submission, forward said plans along with a recommendation to the Chairman of the Planning Commission. In the event that the Chairman provides a reasonable written disagreement, within five days of receipt, with Zoning Officer's recommendation, the plan shall be reviewed at the next regular meeting of the Planning Commission to be processed in the same manner as a minor plan. Otherwise the plan shall be reviewed and approved by the Board of Commissioners.
(3) 
The Zoning Officer shall submit copies of the application to the Allegheny County Office of Economic Development for review and shall not act upon the plan until comments are received or 30 days have lapsed since the submittal of the plan to the county planning agency. Additionally, where any similar review is required by an adjoining municipality, as required by any intergovernmental cooperative or implementation agreement entered into by the Township, said municipality shall be afforded the same review period required for the county.
(4) 
In the event of a denial by the Board, the Zoning Officer shall, within 15 days of the denial, present a written letter to the applicant informing him of said denial along with express deficiencies found and related ordinance citations, within 90 days of application submittal, unless waived by the applicant in writing. Failure to act within the timeline specified shall result in a deemed approval.
(5) 
In the event of approval by the Board, the Zoning Officer shall direct the signatures of the Municipal Engineer, Chairman of the Planning Commission, and Chairman of the Board, in addition to his own signature to the plat. The date on which all signatures have been received shall constitute the approval date. Said approval shall occur within 90 days of application submittal, unless waived by the applicant in writing. In approving a plan, the Board may attach reasonable conditions. The Zoning Officer shall provide the applicant written notice of the approval within 15 days of said approval and may attach reasonable conditions as cited in his previous correspondence to the Chairs.
(6) 
Revised land development plan approvals are subject to all post-approval requirements as cited in Article VIII.
(7) 
Any alteration to a recorded developer's agreement shall be recorded at the Allegheny County Recorder of Deeds within 90 days of approval or shall lose its effect of approval.
A. 
Application requirements. The applicant shall submit the following:
(1) 
All items as specified and required by Article VI of this chapter.
(2) 
The Municipal Engineer, Zoning Officer, or Planning Commission may require the submittal of additional items cited in § 265-606 for major subdivision and land development plans, where said item or items are required to determine conformity with the standards of this and other Township ordinances.
B. 
Application acceptance, review, and procedural actions.
(1) 
The Zoning Officer shall review the submitted application within 10 business or working days of submittal. Where an application is found to be deficient by virtue of the submission of an incomplete application or where the application proposes activities which violate any other Township ordinance, the Zoning Officer shall return all submitted materials to the applicant, citing the basis for said deficiencies. Otherwise, the Zoning Officer shall inform the applicant of application acceptance within 10 days of submittal. Said notification shall constitute of official date of filing. The Zoning Officer shall forward the plan to the Allegheny County Office of Economic Development for review and comment.
(2) 
The Zoning Officer shall present the application to the Planning Commission at their next regular meeting held within 15 days of application filing. The Planning Commission shall recommend denial of the plan, approval, or approval with conditions to the Board of Commissioners.
(3) 
The Board shall not act on the plan until a recommendation from the Planning Commission is received or until 60 days lapse from the first regular meeting of the Commission at which the plan was initially reviewed.
(4) 
The Board shall not act on the plan until recommendations are received from the Allegheny County Office of Economic Development or until 30 days have lapsed since the plan's submittal to the county. Additionally, where any similar review is required by an adjoining municipality, as required by any intergovernmental cooperative or implementation agreement entered into by the Township, said municipality shall be afforded the same review period required for the county.
(5) 
The Board, within 90 days of the official date of filing or within 120 days of the date on which the application was submitted, in the event that a regular meeting of the Planning Commission does not occur within 30 days of submittal, shall act to deny, approve, or approve with conditions. The Board may require the execution of a developer's agreement in accordance with § 265-803 of this chapter where the Board finds that such an agreement is warranted in relation to other conditions placed and the scale or impact of the improvements proposed. Failure to act within the stated timelines shall result in a deemed approval.
(6) 
Minor plan approvals are subject to all post-approval requirements as cited in Article VIII.
The applications cited within this article shall be afforded the protections granted by Section 508 of the Municipalities Planning Code[1] and in § 265-800 of this chapter, wherein approval of the above applications constitutes both a preliminary and final approval. Where an applicant fails to record an agreement or plan as required by this chapter and the effect of final approval is lost accordingly, the effect of preliminary approval, granted on the approval date, shall remain.
[1]
Editor's Note: See 53 P.S. § 10508.