A. 
Prospective subdividers shall arrange a preapplication conference with the Township Planning Commission to determine the practical and legal feasibility of the proposed project prior to the development of normal preliminary plan preparation.
B. 
Subdividers shall present all information and data, as required by this chapter, for review and discussion with the Planning Commission. The Planning Commission shall indicate the general suitability of the proposed plan for refinement into preliminary plans.
C. 
In assessing the suitability of the plan, the Planning Commission shall consider the Township's future land use projections, thoroughfare plan, community facilities plan and any other appropriate plans, including, but not limited to, proposed streets, recreation areas, drainage reservations, shopping centers, housing programs and school sites.
D. 
Consideration shall also be given to possible hazards to health, safety and welfare. Land shall not be approved for subdivision until such hazards are properly addressed. Land subject to flooding, slides due to soil type or slope or excavation, excessive erosion, improper drainage, mine subsidence problems or land unsuited for on-site sewage disposal shall be deemed hazardous to an extent which requires a specific demonstration of measures to remove the identified hazard-producing condition.
Submission of the following information at the preapplication conference is recommended:
A. 
General information. A general description of existing covenants, land characteristics, the availability of community facilities and utilities. Also, information relating to the proposed subdivision, such as the number of lots, typical lot width and depth, commercial areas, playgrounds, park areas, other public areas, proposed protective covenants, proposed utilities and street improvements.
B. 
Topographic map. Existing USGS Quadrangle Sheet or other acceptable map in sufficient detail to show topographic features of the site.
C. 
Sketch plan. A simple sketch of the tract boundaries, proposed layout of streets, lots, significant topographic modifications contemplated and other features in relation to existing conditions.
D. 
Timing. A projected timetable for development of the project, including the anticipated schedule of project phasing.