[Ord. 3-2016, 10/13/2016]
1. The Canton Township Engineer or his designee shall inspect all phases
of development of the site, including, but not limited to:
A. Completion of preliminary site preparation, including stripping of
vegetation, stockpiling of topsoil and construction of temporary stormwater
management and erosion control facilities.
B. Completion of rough grading, but prior to placing topsoil, permanent
drainage or other site development improvements and ground covers.
C. During construction of the permanent stormwater facilities at such
times as specified by the Canton Township Engineer.
D. Upon completion of permanent stormwater management facilities, including
established ground covers and plantings.
E. Upon completion of any final grading, vegetative control measures
or other site restoration work done in accordance with the approved
plan and permit.
2. No work shall begin on a subsequent stage until the preceding stage
has been inspected and approved by the Canton Township Engineer.
3. It is the responsibility of the permittee to notify the Canton Township
Engineer 48 hours in advance of the completion of each identified
phase of development.
4. Any portion of the work which does not comply with the approved plan
must be corrected by the permittee within 48 hours. No work may proceed
on any subsequent phase of the stormwater management plan, the subdivision
or land development or building construction until the required corrections
have been made.
5. If at any stage of the work the Canton Township Engineer determines that the soil or other conditions are not as stated or shown in the approved application, he may refuse to approve further work and Canton Township may revoke existing permits until a revised plan is submitted and approved as required by §
17-406 of this chapter.
6. Subsequent/Periodic Inspections. SWM BMPs should be inspected by
the landowner/developer (including the Township for dedicated facilities)
according to the following list of frequencies:
A. Annually for the first five years.
B. Once every three years thereafter.
C. During or immediately after the cessation of a ten-year or greater
storm.
[Ord. 3-2016, 10/13/2016]
Land disturbance permit fees covering costs to Canton Township
for plan reviews, permit issuance and inspections shall be established
pursuant to resolution of the Canton Township Board of Supervisors.
No permit to begin any work on the project shall be issued until the
requisite fees have been paid.
[Ord. 3-2016, 10/13/2016]
If it is determined that a modification to the existing stormwater management plan is required under §
17-406 of this chapter, a new land disturbance permit shall not be issued until the additional fees have been paid by the applicant.
[Ord. 3-2016, 10/13/2016]
1. The fees payable by an applicant shall, at a minimum, cover:
A. The review of the stormwater management plan.
C. The inspection of required controls and improvements during construction.
D. The final inspection upon completion of the controls and improvements
required in the plan.
E. Any additional work required to enforce the permit provisions, correct
violations and assure the completion of stipulated remedial actions.
[Ord. 3-2016, 10/13/2016]
1. It shall be unlawful for a person to undertake any regulated activity
except as provided in an approved SWM site plan.
2. It shall be unlawful to alter or remove any control structure required
by the SWM site plan.
3. Inspections regarding compliance with the SWM site plan are a responsibility
of the municipality.