Fee schedule, building permits:
Building Permits
Fee
Statutory or Code Reference
Application (minimum fee)
§ 90-5
Owner-occupied single-family dwelling
$25
All other applicants
$75
Zoning determination
$75
§ 90-5
Building
The greater of:
§ 90-5
$0.25 per square foot; or
$8 per $1,000 of work
Demolition
$10 per $1,000 of work
§ 90-5
Sign
$25 plus $1 per square foot
§ 90-5
Curb cut
$100
§ 280-14.5
Parking lot/paving
$100
§ 90-5
Certificate of occupancy
§ 90-5
Business occupancy
$150 per unit
Residential occupancy
$50 per unit
Permit obtained after work has commenced
2 times the fee
§ 90-5
Fee schedule, electrical permits:
Electrical Permits
Fee
Statutory or Code Reference
Application (minimum fee)
$75
§ 116-4
Amp service:
§ 116-4
Up to 199 amps
$50
200 to 599 amps
$75
600 amps and up
$85
Temporary service
$50
Subpanel
$25
Generator and transfer switch
$25
Solar/wind, hydro/fuel cell system
$85
Wiring/outlets:
§ 116-4
Each outlet (light switch, receptacle)
$0.50 each (no fee for up to 5 outlet replacements)
Smoke detector
$5 each
Ground-fault, arc-fault breakers and devices
$5 each
Appliances:
§ 116-4
Electric range, countertop range, oven, electric dryer
$10 each
Dishwasher, disposal, clothes washer
$7.50 each
Mechanical:
§ 116-4
HVAC and gas/oil-fired boiler wiring
$25
Electric/gas/oil water heater
$25 each
Electric heater per thermostat
$5 each
Miscellaneous:
§ 116-4
Mobile and modular homes (prewired at factory) inspection at interconnection of sections
$15
Swimming pool/hot tub/Jacuzzi
$75 each
Each air conditioner, condenser, mini split heat pump
$25 each
Electrical motors:
§ 116-4
Motor up to 9 horsepower
$5 each
Motor greater than 9 horsepower
$10 each
Alarm system (except fire alarm and pull stations)
$35
§ 116-4
Sign
$45
§ 116-4
Hazardous or classified wiring systems
$85
§ 116-4
Reinspection fee for failed inspection after 2 failed inspections
$50
§ 116-4
Permit obtained after work has commenced (belated fee)
$100 plus fee
§ 116-4
Fee schedule, plumbing permits:
Plumbing Permits
Fee
Statutory or Code Reference
Application (minimum fee)
$40
§ 90-5
Each additional fixture
$10
§ 90-5
Hook-up to public sewer
$10
§ 90-5
Hook-up to existing subsurface system
$10
§ 90-5
Piping relocation with no new fixtures
$10
§ 90-5
Permit transfer
$10
§ 90-5
Surcharge fee
$15
§ 90-5
A. 
Fee schedule, disposal system permits:
Disposal System Permits
Fee
Statutory or Code Reference
Complete disposal system and variances:
§ 90-5
Engineered system
$200
Nonengineered system
$250
Primitive system
$100
Separate grey waste disposal field
$35
Seasonal conversion permit
$50
First time system variance
$20
Permits for separate parts of disposal system:
§ 90-5
Alternative toilet (only)
$50
Disposal field only (engineered system)
$150
Disposal field only (nonengineered system)
$150
Treatment tank only (nonengineered system)
$150
Treatment tank (engineered system)
$80
Holding tank
$100
Other components (complete pump station, piping, other)
$30
B. 
Late permit fee. A person who starts construction without first obtaining a subsurface wastewater disposal permit shall pay double the permit fee indicated in Subsection A listed above.
Fee schedule, fire safety:
Fire Safety
Fee
Statutory or Code Reference
State of Maine construction permit
$0.05 per square foot
Fire alarm/sprinkler system
$25 minimum
Commercial
$8 per $1,000 of work
One- and two-family
$8 per $1,000 of work
Fixed fire suppression system
General plan review
$75 plus puff test
Gas station plan review
$200 plus puff test
Retest
$75 per test
Special event permit
$75 per event
Fireworks permit
$75 per event
Blasting permit
$75 per job
Fee schedule, enforcement:
Enforcement
Fee
Statutory or Code Reference
Stop-work order removal
§ 90-8
No work completed during stop-work order
$150
Work completed in violation of stop-work order
$300
Reinspection fee for failed inspection after 2 failed inspections:
§ 90-4
First
$50
Second
$100
Third and subsequent
$200
Securing building
$500
§ 90-31