Exciting enhancements are coming soon to eCode360! Learn more 🡪
Village of Port Jefferson, NY
Suffolk County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
A. 
Right-of-way widths.
(1) 
Collector streets as classified by the Planning Board shall be not less than 60 feet in width.
(2) 
Minor streets shall be not less than 50 feet in width.
(3) 
Alleys, pedestrian ways, utility easements, access strips, rights-of-way, etc., shall be at least 20 feet wide. Deviation from the twenty-foot rights-of-way may be permitted in accordance with Chapter 250, Zoning, § 250-27.
B. 
Paved widths of streets.
(1) 
Collector streets shall be Paved to a width of 36 feet or as directed by the Planning Board.
(2) 
Minor streets shall be Paved to a width of 30 feet.
(3) 
Alleys, pedestrian ways, utility easements, access strips, rights-of-way, etc., shall be paved to a width as determined by the Planning Board.
(4) 
Driveways to recharge basins shall be paved to a width of 12 feet.
C. 
Culs-de-sac. Where lots have direct access onto a cul-de-sac, the radius of the turnaround (right-of-way) at the end of the cul-de-sac shall be 50 feet; the radius of the paved area of the turnaround at the end of the cul-de-sac shall be 34 feet
[Amended 1-7-1981 by L.L No. 1-1981]
A. 
Construction starting date.
(1) 
Construction may not be commended until after a public hearing has been duly held on the particular subdivision map and the final map has been approved and filed with the County Clerk.
(2) 
The developer must consult or notify the Planning Board's authorized representative not less than 24 hours before beginning any construction work that requires inspection in accordance with the site bond.
(3) 
No road or drainage work may commence until drawings pertaining to such work have been approved by the Village and the Planning Board. Approval signatures with dates shall be affixed to drawings in spaces provided.
B. 
Building permits. Building permits shall not be issued by the Building Inspector before final action by the Planning Board and plat filed with the County Clerk, with the exception of those pertaining to model houses.
C. 
Model houses. After a public hearing and before final action by the Planning Board, the developer may secure building permits for model houses, subject to requirements and conditions as imposed by the Planning Board. In no event will a certificate of occupancy be issued until all improvements have been made, with the exception of landscape items. Separate performance bonds for all site improvements incidental to the site of each model house, including a proportionate share of off-site but related other improvements, shall be filed by the developer before any permit shall be issued for a model house.
D. 
Schedule of operations. The developer shall indicate, in writing, a schedule of operations prior to the start of construction to ensure the orderly procedure of the work.
E. 
Neatness. The developer, during the entire period of construction work, shall keep the site in a neat and orderly condition and shall immediately comply with any reasonable directives of the Building Inspector or Planning Board as and when issued.
F. 
Sanitary facilities. The developer shall provide sufficient and suitable conveniences, well secluded, constructed and maintained in conformance with the local, county and state sanitary laws, for use of all workmen employed on the site. On or before the completion of the work, the developer shall remove all of the temporary buildings and structures used for this purpose.
G. 
Traffic maintenance. The flow of traffic or the safety thereof on any public street or highway within the Village will not be restricted or endangered in any way by construction operations, equipment, vehicles or materials connected with the construction or sales' operations of a subdivision. The developer must provide off-street parking space for all vehicles used in construction or sales' operations. Equipment or materials may not be stored within the right-of-way lines of any public street or highway but shall be stored in an area protected by solid-type fence structure not to exceed eight feet in height.
H. 
Temporary roads. All roads within a development which are used by the contractors or others and which have not been surfaced must be suitably treated and maintained to minimize dust.
I. 
Temporary drainage. Rainfall runoff from developments during construction operations must be confined to the site unless an adequate stormwater drainage system exists. Methods of providing for temporary drainage and erosion control shall be approved by the Planning Board. Stormwater runoff disposal during construction onto existing roads, streets or private property is prohibited. All work shall conform to the soil erosion, sediment control and water retention policy of the Village.
J. 
Protection of new drainage facilities. All drainage facilities during construction operations shall be cleared of lumber, debris, dirt and other objectionable materials after completion and shall be maintained in a clean condition until time for use.
K. 
Condition of construction equipment. Equipment used for site improvement work shall be of modern type and in sound operating condition and adequate for the purpose for which it is to be used and must conform to those laws, rules and regulations of the New York State Department of Motor Vehicles.
L. 
Developer's responsibility. The developer is responsible for keeping all roads, streets and private property free of debris and damage caused by construction operations or by stormwater runoff from the development site. Any damage so caused shall be immediately repaired by the developer at his own expense. If after due notice by the Village Clerk or Building Inspector or Planning Board, the developer does not proceed within 72 hours to make the necessary repairs or to remove the debris caused by his operations, the Village is empowered to take necessary corrective measures and the costs shall be paid by the developer. The developer shall comply with the New York State Manual of Uniform Traffic Control Devices (Maintenance of Traffic) and New York State Code 23 (Safety - Excavations).
M. 
Construction emergencies. In any emergency arising during the construction period of a development where the developer or his representative is not immediately available to take responsible charge, the Village Clerk or Village Board shall take such measures and render such decisions as may be necessary to control the situation. Any resultant costs shall be borne by the developer at no expense to the Village.
N. 
Decision of Village final. It shall be mandatory upon the developer that the work proceed in accordance with proper construction practice and that all necessary measures be taken for the protection of the public health, safety and welfare. The decision of the Village or its representative shall be final and binding in these matters.
O. 
Bonds for new or undedicated roads.
[Added 1-22-1990 by L.L. No. 1-1990]
(1) 
Undedicated roads remain the property and responsibility of the developer. However, upon issuance of the first certificate of occupancy in the development involving new or undedicated roads, the developer shall post a cash bond to cover estimated cost of snow plowing and sanding to be performed by the Village in the event that the developer shall fail to plow and sand the roads.
(2) 
The purpose of this provision is to insure the public safety by maintaining access to residents in newly developed areas.
(3) 
Any unused funds will be returned to the developer upon dedication of the roads. Prior to dedication, the developer shall replace used funds by November 1 of the following year
(4) 
The bond formula shall be as follows: length of road in feet times $0.10 per foot times three services per storm times five storms per year.
A. 
Portland cement concrete.
(1) 
Proportioning. All concrete shall be generally a one-two-to-four mix consisting of one part portland cement, two parts of clean, washed sand and four parts of three-fourths-inch broken stone. Measurements shall be by absolute volume, with some deviation in aggregate volume as may be required to achieve a denser or more plastic mix.
(2) 
Strength. All concrete, when tested at 28 days after pour by an approved laboratory, shall show a minimum strength of 3,000 pounds per square inch. Concrete not meeting this requirement shall be rejected, removed from the site of the work by the developer and replaced with proper materials.
(3) 
Mixing. All concrete shall be mixed in an approved mixer and shall be deposited within 30 minutes of the time that the mixing operation was started.
(4) 
Placing. No more than 30 minutes shall elapse between placement of successive batches to prevent the formation of "cold joints." Concrete shall be deposited with a designed slump of three inches to four inches, and no additional water shall be added. Any batch not acceptable to the Planning Board's authorized representative shall be rejected and immediately removed from the job.
(5) 
Temperature. Temperature, when pouring concrete, shall be 40º F. and rising.
(6) 
Curing. Provisions shall be made for maintaining concrete in a moist condition for at least five days after the placement of the concrete. The method of curing shall be accomplished in an approved manner and shall be the responsibility of the developer/builder.
(7) 
Delivery tickets. Copies of concrete delivery tickets shall be furnished to the Planning Board or Planning Board's authorized representative upon demand.
B. 
Piping.
(1) 
Reinforced concrete pipe. Unless otherwise specified, all drainage conductors shall be reinforced concrete pipe as specified by ASTM C-75, Table 1, for culvert pipe. The piping shall meet the requirements of the New York State Department of Transportation Item 706.02, Class III or IV, as required by the design engineer.
(2) 
Corrugated steel pipe (circular). Under certain conditions and only after written approval by the Planning Board, corrugated steel pipe, in lieu of concrete pipe, may be used for drainage purposes. Pipe shall be fully coated with acceptable bituminous material and have bituminous-paved inverts. It shall be installed according to manufacturer's recommendations. Design considerations shall be approved by the Planning Board's authorized representative prior to installation.
C. 
Reinforcing steel. All bar reinforcement for concrete shall be of open-hearth steel and shall consist of deformed bars. The bars shall be rolled from new billets. Reinforcement must be securely placed in the exact position shown on the approved plans or detail drawing and shall be held securely by wiring and blocking during the pouring of concrete.
D. 
Catch basin or manhole steps. These shall be of open-hearth steel and shall be hot-bent before galvanizing. They shall be 3/4 inch in diameter and shall be bent to form a step 16 inches wide. The anchorage ends shall be 11 inches long with an additional two inches at the ends of each leg bent up at right angles. (See detail drawing included at end of chapter.[1]) Steps shall be built into catch basins and manholes during construction. Wherever possible, steps shall be placed on a blank wall of the structure.
[1]
Editor's Note: The detailed drawing is on file and available for inspection in the Village Clerk's office.
E. 
Iron castings. Castings for catch basins and manholes shall be true to pattern in form and dimension and free from pouring faults, sponginess, cracks, blowholes and other defects. All frames and covers shall be placed nine inches from the inside of the wall on which the steps are mounted. All cast-iron inlets shall be backed up with well-trimmed asbestos shingles before the concrete slab is poured.
F. 
Crushed stone. Crushed stone in various sizes shall be used for road materials as elsewhere specified. The stone shall consist of angular particles of clean, hard, tough, durable rock, free from adherent coatings. An excess of flat or elongated fragments shall be cause for rejection.
G. 
Asphaltic concrete. Asphaltic concrete shall be in accordance with the requirements of the latest edition of the New York State Department of Transportation Specifications.
H. 
Street signs shall be four-way criss-cross type with the complete bracket assembly on pipe post, as manufactured by Lyle Sign Inc. or equal. Street signs shall be 24 inches by 6 inches, having black letters on white enamel background. Letters shall be 3 1/2 inches high on eighteen-gauge steel plate with heavy zinc coating applied by hot-dip process bonderized after fabrication. The letters and border shall be heavily embossed to a depth of 0.125 inch. Only perfect dies are to be used in the embrossing process. Nameplates shall be finished with three coats of white baking enamel applied to the background of the plates by the spray method. In addition, letters and borders shall have two black enamel coats applied by power rubber rollers, with each of these coats baked separately. Even temperatures of 350º F. are to be maintained for all baking. The finish is to be free of blemishes, blisters and cracks. The style of letters is to conform to existing street signs. The bracket assembly is to consist of post cap made from semisteel; the tie rod shall be galvanized after fabrication; four center clips shall be made from sixteen-gauge steel and galvanized after fabrication. The finish of the bracket assembly is the same and applied in the same manner as the background for the street nameplate. All of the assembly is to be aluminum or other rust-resisting material. Signs are to be mounted on two-inch diameter by three-eighths-inch-thick, butt-welded, standard galvanized pipe. The bottom of signs is to be seven feet zero inches above ground and set in three-thousand-pound concrete forming a base 42 inches deep and eight inches in diameter.
I. 
Monuments.
(1) 
Monuments shall be of concrete mix: one part Portland cement or equal, two parts clean, washed sand and three parts three-eighths-inch to 3/4 inch gravel. Measurements shall be by absolute volume with enough water added to produce a workable mix. The monument shall be 30 inches minimum length, four inches square on the top and six inches square at the bottom. One three-eighths-inch reinforcing rod 28 inches long remaining the length of the monument shall be cast in each corner with a minimum of one inch of cover from each face. When stripped, the concrete shall be smooth and dense with no "honeycombing," and all markers shall be suitably cured before installation.
(2) 
A metal tablet shall be cast of a copper-bearing alloy similar to manganese bronze. The bronze tablet with legs spread shall be cast in the concrete as shown in the elevation, with care being taken to keep it free of all mortar. The inscription shall be cast as depressed letters, and an area designated for a number shall be blank and slightly raised. The entire top surface of the casting shall be polished, and the tablet shall be clean, with all lettering legible and five from detects.
(3) 
The inscription in the metal tablet shall be as shown in the plan and elevation.
J. 
Fencing: recharge basins.
(1) 
The chain-link fabric shall be two-inch mesh. No. 6 gauge wire, six feet zero inches high, hot-dipped galvanized after fabrication. Finish is to be standard, and the wire shall be twisted and barbed on top and bottom. All necessary pipe shall be galvanized, with sizes and weights as follows:
Type
Outside Diameter
(Inches)
Pounds Per Linear Foot
Line post
2
2.72
Corner and posts
2 1/2
3.65
Gate posts (allow for 16 foot opening)
4
9.10
(2) 
Fence to include a 1 5/8 inch outside diameter top rail securely joined with necessary expansion sleeves. A concrete curb eight inches by 18 inches shall be provided around the entire length of fence and depth shall be increased to 36 inches at all posts. The top of curb shall be true to line so that the fence is centered on the curb. An eighteen-inch wooden form shall be provided for both sides of the curb. The top of both forms shall conform to line and grade. Concrete shall be in accordance with Subsection A.
(3) 
Fencing requirements may be modified or waived by the Planning Board after special consideration to the topography, size, slopes, vegetation and of the proposed recharge basin. Particular consideration must be given to the safety factor that must surround a recharge basin. Three and 5/16 inch galvanized rods 12 inches long shall be placed 2 1/2 inches apart in each ten-foot panel. There shall be a one-inch-long right-angle hook formed on one end of rod. The hook end shall be placed five inches below top surface of concrete curb. After fabric has been placed, the top six inches of rod shall be bent toward the inside of the recharge basin to make a tight hook around the mesh wire. All terminal posts are to be furnished with horizontal braces and turnbuckle attachments with 3/8 inch rod. Braces are to be 1 5/8 inch outside diameter pipe 2.27 pounds per linear foot.
(4) 
Fittings shall be of galvanized malleable iron or pressed steel. All ties are to be of aluminum No. 9 wire. For line posts, one tie for every foot of fabric height shall be installed. For rail and braces, the ties must be approximately 24 inches apart.
(5) 
Three strands of aluminum barbed wire running the entire length of the fence above the fabric and gates and supported on the line posts by means of barb arms sloping away from the basin area at an angle of 45º shall be installed. Double gates for a 16 foot-wide opening shall be constructed in accordance with the manufacturer's specifications, but the frame shall be welded at the four corners. The gauges shall be reinforced with a 1 5/8 inch outside diameter pipe welded to frame and a 3/8 inch rod attached at corners with a turnbuckle. All welds shall be painted. Fabric shall be two-inch mesh, No. 6 wire galvanized. Gates shall be equipped with a drop-bar locking device and lock. A Northland hinge OH-35 or equal; Northland drop-bar locking device G-10 or equal; and Wickwire center stop No. 8725 or equal shall be used on all entrance. All materials are to be heavily galvanized by the hot-dip process.
(6) 
A reinforced concrete curb of three-thousand-pound concrete, 18 inches wide and 24 inches deep, shall be constructed under the gate opening and extending six inches beyond the gate posts. The top of the curb shall be 1 1/2 inches below the bottom rail of the gates. The locking device for gates shall extend into an approved center stop set in the concrete curb. One lock and key for each gate opening shall be furnished and delivered to the Planning Board. Locks shall be bronze body and cylinder as manufactured by Yale and Towne, No. 851, keyed alike to key change No. 18970.
K. 
Leaching basins, standard.
(1) 
Standard leaching basins shall be constructed of 8 by 16 inch concrete leaching-block (Hawkins) type to within two feet of finished grade. The final two feet of wall on the road side shall be of concrete with curb inlet set in place and poured with the top slab. The continuation of the other side walls to the underside of the concrete top slab may be poured concrete or concrete building blocks laid with the cells vertical. All blocks shall be laid in one-to-two cement-sand mortar. The top slab shall be of eight-inch reinforced concrete, wood-float finished, with all exposed edges tooled. Footings shall be of 3,500 pound concrete formed as shown on the detail drawing. In cases where unsuitable material is encountered at normal subgrade depth, the excavation shall continue down to good leaching material and to a depth of six feet into this stratum. The excavation shall then be backfilled with clean sand and gravel to normal subgrade depth, after which the construction of the basin shall proceed. Material so backfilled shall be tamped or otherwise properly consolidated before proceeding with the basin construction. All such excavation shall be subject to inspection by the Planning Board's authorized representative before backfill is placed. Clean sand and gravel to a depth of two feet shall be placed inside of the basin at the bottom as shown. All backfill must be clean, acceptable material placed under the direction of the Planning Board's authorized representative. A gravel collar three feet wide shall be provided from the bottom surface of the dome to the bottom of the basin. The gravel range size shall be one-inch minimum to three-inch maximum gradation.
(2) 
All specifications pertaining to inlets, frame and cover, and steps are to be as shown on detail drawings and as outlined elsewhere in these specifications.
L. 
Precast leaching basins. When authorized by the Planning Board, precast leaching basins will be permitted as an alternate to standard leaching basins. See detail drawing for method of installation. All concrete is to test 4,000 pounds prior to installation and shall be subject to inspection by the Planning Board Engineer. All materials shall conform in every respect to these specifications. Design drawings shall be submitted by manufacturers and approved by the Planning Board's authorized representative prior to installation of basins. A bankrun collar one foot wide shall be provided from the bottom surface of the dome to the bottom of the basin. The gravel range size shall be one-inch minimum to three-inch maximum gradation. A four-by-seven-foot wick shall penetrate five feet through impervious soil beneath leaching basins.
M. 
Precast overflow leaching pool. A precast overflow leaching pool can be used in conjunction with a standard leaching basin or precast leaching basin in place of additional standard basins. The dome of the precast pool shall be cast with a large enough hole to accommodate pipe leading from the basin. No cutting or chopping shall be allowed. A cast-iron ring with bottom flange and cover shall be required. See detail drawing for dimensions. A gravel collar three feet wide shall be provided from the bottom surface of the dome to the bottom of the basin. The gravel range size shall be one-inch minimum to three-inch maximum gradation.
N. 
Catch basin, Type A. This basin is used in connection with underground piping and is constructed as shown on detail drawing. Wall sections below 12 feet shall be increased to 12 inches in thickness. The bottom of the basin or top of footing shall be three feet below the invert of the outfall pipe. The length of the curb inlet opening is a variable depending upon the hydraulic conditions. All other dimensions shall be as shown on the detail drawing. All materials shall conform in every respect to these specifications.
O. 
Manholes. Manholes shall be constructed of concrete, brick or acceptable precast concrete in accordance with dimensions shown on the detail drawing. If precast manholes are used prior approval of plans shall be secured from the Planning Board's authorized representative. Manholes shall have a minimum inside dimension of four feet by four feet if square or be four feet in diameter if round. Inside dimensions may be greater if required by pipe sizes. All manholes shall include galvanized steps as shown on the detail drawing. All materials shall conform in every respect to these specifications.
P. 
Headwalls. Whenever a recharge basin is constructed, the drainage pipe shall be introduced to the basin by means of a headwall constructed of three-thousand-pound concrete in accordance with the detail drawing. All materials shall conform in every respect to these specifications.
Q. 
Streetlights. Streetlights shall be required for all new streets and shall conform to the following requirements:
[Added 6-10-1976 by L.L. No. 6-1976]
(1) 
Spacing.
(a) 
There shall be one light at each intersection.
(b) 
There shall be one light centrally located at each cul-de-sac.
(c) 
Maximum spacing shall be 200 feet between lights.
(d) 
Lights shall be located two feet six inches behind the face of the curb.
(2) 
Light fixture.
(a) 
The fixture shall have a 175 watt mercury vapor lamp.
(b) 
The frame shall be of cast aluminum, black acrylic baked finish, with a hinged cast-aluminum top.
(c) 
The fixture shall be equipped with a photoelectric control.
(d) 
The fixture shall be by Pemco, Adams Heritage Luminaire, Catalog No. H-0602; or General Electric TC-100 Luminaire, Catalog No. C-721 G007; or an approved equal.
(3) 
Pole.
(a) 
The pole shall be four-by-three-inch tapered aluminum with black acrylic baked finish or four-by-four-inch redwood pole, as approved by the Planning Board.
(b) 
The aluminum pole shall be 12 feet long with the fixture set 10 feet above ground level, and the pole shall be set two feet into the ground and imbedded in concrete.
(c) 
The redwood pole shall be 13 feet long with the fixture set 10 feet above ground level, and the pole shall be set three feet into the ground. The corners of the pole shall be chambered and the pole shall be fitted with a three-inch O.D. terminal top. The finish shall be rough sawed.
(d) 
The aluminum pole shall be by Pemeo, Catalog No. AE 10; or General Electric, Catalog No. 35-112197-47; or an approved equal.
(4) 
Wiring.
(a) 
Wiring shall be underground, with the size of the wire and method of connection to the utility lines to be approved by the Long Island Lighting Company.
(b) 
Wiring shall be installed by a licensed electrician.
(5) 
Location plan.
(a) 
A plan shall be prepared by the developer at a scale of one inch equals 100 feet or larger and submitted to the Planning Board indicating the proposed location of the streetlights.
(b) 
The plan shall be approved by the Planning Board before commencing with the installation.
(6) 
Maintenance. The developer shall maintain the lights in an operating condition until they are approved and accepted by the Village.
A. 
Clearing.
(1) 
Scope of work. All trees, roots, stumps, bushes, timber and decaying or growing organic matter above and below the surface of the ground and large rocks shall be removed from the bed of the proposed street to a width two feet greater than the proposed back to back of curb dimension.
(2) 
Disposal of wood. All wood shall be disposed of in a legal fashion. No burning or burying is permitted.
(3) 
Fire permits. Fire permits shall be obtained in accordance with the provisions of Chapter 40, Fire Prevention Code, Article XVII, § 40-141, of the Village of Port Jefferson Code[1] and the requirements of other jurisdictions.
[1]
Editor's Note: See now Ch. 139, Fire Prevention.
(4) 
Excess width of clearing. Clearings wider than those specified in § 220-33B and Subsection A(l) above may be permitted in certain cases to provide for proper slopes where substantial cuts and fills are necessary, with Planning Board approval.
(5) 
Trees to be retained. All sound trees larger than four inches diameter which are existing in the roadway right-of-way outside of the paved area shall be retained unless grading requires their removal.
(6) 
Additional landscaping information is contained in the Chapter 250, Zoning, §§ 250-51.1 and 250-52.
B. 
Grading.
(1) 
Topsoil. All topsoil shall be removed from the cleared area and stockpiled for use in final grading.
(2) 
Excess topsoil: permission to remove. No topsoil shall be removed from the area within the boundaries of the map except when an excess exists and the final plat has been filed with the County Clerk. Such proof, upon demand, in writing, will take the form of a written affidavit submitted by a licensed surveyor or professional engineer after an initial estimate and verification by the Planning Board's authorized representative. No excess shall be deemed to exist until at least eight inches of topsoil is provided for all disturbed portions of the development area, with the exception of those areas set aside for paved streets, driveways, walks and recharge basins. This permission shall be valid for a three-month period only.
(3) 
Developments where no excess topsoil exists. In such developments, the available topsoil shall be evenly distributed over all plots, except that in no case shall the minimum depth be less than six inches at the time of placement. If required, the developer shall bring in topsoil to comply with his requisite except in areas where natural vegetation has not been disturbed. The developer shall also meet requirements elsewhere set forth in this chapter and its specifications.
(4) 
Graded sections. Typical graded sections shall be as shown in the detail at the end of this chapter.[2]
[2]
Editor's Note: Said diagram is on file in the Village offices.
(5) 
Driveway entrances. Driveway entrances, in cut or fill, shall be properly engineered and shall be as shown in the detail at the end of this chapter.[3]
[3]
Editor's Note: Said diagram is on file in the Village offices.
(6) 
Roadway grading. Roadways shall be acurately graded to the approved profiles. Before grading is started, the engineer for the developer shall furnish adequate line and grade stakes to ensure accurate vertical and horizontal alignment of all roads in the development in accordance with approved plans. The developer shall be held responsible for correct grading operations, including sidewalk areas and correct bank slopes in cut or fill areas.
(7) 
Subsurface utilities. All subsurface utilities, substructures and service connections in street areas shall be completed and installed prior to the final grading of the subgrade. All backfill shall be properly consolidated in six-inch layers by mechanical tamping or other approved means before paving operations are commenced.
(8) 
Excavation below grade. No excavation shall be permitted below the approved subgrade elevations unless the base is unsatisfactory to the Planning Board's authorized representative. In such cases, all unsatisfactory material shall be removed and replaced with suitable material properly compacted, as directed by the Planning Board representative.
(9) 
Topsoil included in performance bond. In determining the amount of the performance bond, the Planning Board shall consult with the Village Engineer regarding the topsoil in each particular subdivision. They shall then determine the amount of moneys to be included in the performance bond to provide for six inches of topsoil per lot for the lot areas disturbed.
[Added 9-27-1978 by L.L. No. 13-1978]
C. 
Concrete sidewalks.
(1) 
Concrete sidewalks shall be required when specified by the Planning Board. They shall be four feet wide and placed as indicated on the final plat plan or site plan.
(2) 
Sidewalks shall be constructed of three-thousand-pound concrete four inches thick laid on a six-inch base of selected, clean sand and gravel. Slabs shall be tooled from four-foot one-half-inch square panels. Bituminous expansion joints of one-half-inch material shall be provided at every fourth panel or 16 feet apart.
(3) 
Expansion joints shall be properly braced during construction to ensure accurate finished alignment
(4) 
Surface finish shall be provided by wood-float method.
(5) 
Curing will be accomplished as specified in § 220-35A(6).
D. 
Concrete aprons.
(1) 
A concrete apron or approved asphaltic apron shall be required for each house driveway proposed to be built in a subdivision.
(2) 
A concrete apron will be required for each recharge basin access road in a subdivision.
(3) 
All aprons to be constructed of 3,000 pound concrete six inches thick.
(4) 
Six-inch-by-six-inch-by-ten-gage wire mesh shall be required in all aprons.
(5) 
See detail drawing at end of chapter for dimensions.
E. 
Road construction.
(1) 
Preparation of subbase. Before any base course material is placed, the subbase shall be carefully shaped to the approved profile and rolled with a roller weighing at least 10 tons. In case unsuitable material is encountered at the subgrade level, such as loam or clay, it shall be removed to a depth of at least 12 inches or as may be directed by the Planning Board's authorized representative and backfilled with suitable material rolled in four-inch layers to subgrade. All loose stones, roots or other debris shall be removed. Upon completion of the subgrade, the developer shall request an inspection by the Planning Board's authorized representative and shall not proceed with further roadway work until such inspection has been made and the work approved.
(2) 
This work shall consist of constructing a pavement course of hot, plant-mixed asphalt concrete on a prepared base in accordance with Section 4-03 of the latest edition of the New York State Department of Transportation Construction and Materials Specifications and in conformity with the lines and grades shown on the plans and thicknesses and typical sections located at the end of this chapter.[4] The road section shall consist of Type 6 asphalt concrete top course, one inch thick; Type 5 asphalt concrete binder course, 1 1/2 inches thick; five-inch thick dense graded aggregate base course (stone blend) on a six-inch stabilized soil subbase course. The stabilized soil subbase shall meet the requirements of Section 304 of the New York State Department of Transportation Construction and Materials Specifications, latest edition.
[4]
Editor's Note: Said diagram is on file in the Village offices.
F. 
Tests. All asphaltic concrete used shall be subject to laboratory tests to determine whether it is in accordance with the specifications. Payment for these tests shall be the responsibility of the Incorporated Village of Port Jefferson.
G. 
Recharge basins.
(1) 
Location of related drainage facilities. The location and relative dimensions of the related drainage facilities of a recharge basin shall be shown on the detail drawing.
(2) 
Excavation. If required by the presence of unsuitable material at or below the bottom elevation, excavation shall be carried down to good leaching material as determined by the Planning Board's authorized representative. Test holes, as directed by the Planning Board's authorized representative, shall then be dug at this level to ensure at least a six-foot stratum of good leaching material. The lower portion of the side slopes shall be composed of good leaching material to an elevation at least seven feet above the approved elevation of the bottom of the recharge basin, even if acceptable clean sand and gravel must be brought in from outside sources to accomplish this. The excavated area below proposed subgrade shall then be backfilled to the proper elevation with clean sand and gravel. All such excavations and backfilling must be inspected by the Planning Board's authorized representative before such operations take place.
(3) 
Bank slopes. The slope of the banks of the recharge basin shall be established at 3 to 1. The top of the slope shall be established at a grade of one foot six inches higher than the finished grade at the property line at least 10 feet distant therefrom. If the topography of the ground does not permit this procedure, then final grades and top of slope location shall be as directed by the Planning Board's authorized representative.
[Amended 2-25-2002 by L.L. No. 4-2002]
(4) 
Erosion protection. In all cases, runoff water shall be directed away from the tops of the bank slopes of recharge basins to prevent erosion and washouts. This may be accomplished by grading, where possible, or by the installation of suitable inlets and piping as directed by the Planning Board's authorized representative.
(5) 
Fencing. Before excavating for a recharge basin, a fence or suitable barrier shall be erected around the area of excavation in accordance with plans and specifications approved by the Planning Board's authorized representative as adequate to safeguard the public or permanently fenced in accordance with the approved plat plan. Excavations, slopes, ramps and grades leading to and surrounding the recharge basin must be inspected and approved by the Planning Board's authorized representative prior to the erection of the permanent fence. The permanent fence, in accordance with these specifications, shall be set six feet from the property line on the developer's property.
(6) 
Planting. In all cases, a planting scheme will be provided for approval by the Planning Board. The plantings will provide screening of the fencing and area, will protect the area from erosion and will provide protection from erosion on and of the faces of the basin's sloped banks and any other excavated areas.
A. 
Layout. The developer's engineer shall furnish accurate line and grade stakes for all construction operations involving site improvements and maintain accurate field checks to ensure correct placement, according to approved line and grade, of all roads, curbs, structures, monuments and engineering works of whatsoever nature prescribed by these general and detail specifications for street improvements.
B. 
As-built drainage plan. Upon the completion of the catch basins, manholes and piping, the developer's engineer or surveyor shall file with the Building Inspector and Planning Board Engineer or representative a plan showing the proposed and as-built elevations at catch-basin corners, top of manholes and all pipe inverts in catch basins, manholes and at the recharge basin headwall. Proposed and as-built pipe gradients shall also be noted. This plan shall be approved before the curbs in this drainage area may be started.
C. 
As-built curb plan. Upon completion of curb construction and before any road work is started, the developer's engineer or surveyor shall file with the Building Inspector and the Planning Board Engineer or representative a plan showing both proposed and as-built curb elevations and the location of the curb in relation to the property line. The plan shall show the proposed elevation opposite all grade stakes used in construction of the curbs and the as-built elevations at these stations.
D. 
As-built construction detail plans. Upon completion of streets right-of-way, curbing, right-of-way grading, drainage, utilities or any other pertinent data, an as-built road record and profile plan shall be submitted to the Planning Board prior to offers of cession of streets, rights-of-way, easements and sites for public use and copies of agreements, covenants or other documents. The as-built street plan and profile shall be on standard profile plan cloth K & E 486026, or equivalent, 24 by 48 inch sheet size, including a three-inch margin along the left side of the sheet. The horizontal plan scale will be one inch equals 50 feet, and the vertical profile scale will be one inch equals five feet. The road record and profile plan shall contain all the data that concerns any construction above or below ground that is contained within or crosses the road right-of-way.