The design and construction of streets shall be governed by the following.
A. 
The cost of design and constructing all grading, curbs, gutters, subbase, base, traveling surfaces and sidewalks shall be borne by the developer.
B. 
All work must be performed under City inspection. Costs of inspection and required testing, including the hiring of an independent engineer to perform said services, at the discretion of the City, shall be borne by the developer.
A. 
All construction work shall be done in conformance with the improvement construction plan previously approved by the City Engineer and the Planning Commission.
B. 
All work shall conform to standard specifications and details and other regulations established by the City of Harrington.
The developer will be responsible for streets and sidewalks until final acceptance and official release of the completion guaranty, including repairs, if necessary, and other reasonable provisions for the convenience and safety of traffic. Until final acceptance and official release of the completion guaranty, the developer will be responsible, also, for the removal of snow from streets when necessary for the convenience or safety of traffic.
Streetlights shall be of a design approved by the Planning Commission and shall be placed at locations approved by the Planning Commission. The cost of installation of streetlights shall be borne by the developer. All electric lines shall be located underground. The cost of electricity for streetlights shall be paid by the developer.