The following items shall be included in the stormwater management facilities operations and maintenance plan:
(1) 
Map(s) of the project area, in a form that meets the requirements for recording at the offices of the Recorder of Deeds of Montgomery County, and which shall be submitted on twenty-four-inch by thirty-six-inch or thirty-inch by forty-two-inch sheets. The contents of the map(s) shall include, but not be limited to:
(a) 
Clear identification of the location and nature of permanent stormwater management facilities;
(b) 
The location of the project site relative to highways, municipal boundaries or other identifiable landmarks;
(c) 
Existing and final contours at intervals of two feet, or others as appropriate;
(d) 
Existing streams, lakes, ponds or other bodies of water within the project site area;
(e) 
Other physical features, including flood hazard boundaries, sinkholes, streams, existing drainagecourses, and areas of natural vegetation to be preserved;
(f) 
The locations of all existing and proposed utilities, sanitary sewers, and waterlines within 50 feet of property lines of the project site;
(g) 
Proposed final changes to the land surface and vegetative cover, including the type and amount of impervious area that would be added;
(h) 
Proposed final structures, roads, paved areas and buildings; and
(i) 
A fifteen-foot-wide access easement around all stormwater management facilities that would provide ingress to and egress from a public right-of-way.
(2) 
A description of how each permanent stormwater management facility will be operated and maintained, and the identity of the person(s) responsible for operations and maintenance;
(3) 
The name of the project site, the name and address of the owner of the property, and the name of the individual or firm preparing the plan; and
(4) 
A statement, signed by the landowner, acknowledging that the stormwater management facilities are fixtures that can be altered or removed only after approval by the Township.
A. 
The stormwater management facilities operations and maintenance plan for the project site shall establish responsibilities for the continuing operation and maintenance of all permanent stormwater management facilities, as follows:
(1) 
If a plan includes structures or lots which are to be separately owned and in which streets, sewers and other public improvements are to be dedicated to the Township, stormwater management facilities may also be dedicated to and maintained by the Township.
(2) 
If a plan includes operations and maintenance by a single ownership, or if sewers and other public improvements are to be privately owned and maintained, then the operation and maintenance of stormwater management facilities shall be the responsibility of the owner or private management entity.
B. 
The Township shall make the final determination on the continuing operations and maintenance responsibilities. The Township reserves the right to accept or reject the operations and maintenance responsibility for any or all of the stormwater management facilities.
A. 
The Township shall review the stormwater management facilities operations and maintenance plan for consistency with the purposes and requirements of this chapter and any permits issued by DEP.
B. 
The Township shall notify the applicant in writing whether the stormwater management facilities operations and maintenance plan is approved.
C. 
The Township may require an as-built survey of all stormwater management facilities and an explanation of any discrepancies with the stormwater management facilities operations and maintenance plan.
It shall be unlawful to alter or remove any permanent stormwater management facilities required by an approved stormwater management facilities operations and maintenance plan, or to allow the property to remain in a condition which does not conform to an approved BMP operations and maintenance plan, unless an exception is granted in writing by the Township.
The property owner shall sign an operations and maintenance agreement with the Township covering all stormwater management facilities that are to be privately owned.
A. 
Stormwater management easements are required for all areas used for off-site stormwater control, unless a waiver is granted by the Municipal Engineer.
B. 
Stormwater management easements shall be provided by the property owner if necessary for access for inspections and maintenance or preservation of stormwater runoff conveyance, infiltration, and detention areas and other stormwater management facilities by persons other than the property owner.
The following documents shall be recorded in the office of the Recorder of Deeds for Montgomery County:
A. 
The stormwater management facilities operations and maintenance plan, or a summary thereof;
B. 
Operations and maintenance agreements under § 162-17; and
C. 
Easements under § 162-18.
If stormwater management facilities are accepted by the Township for dedication, the Township may require persons installing such facilities to pay a specified amount to the municipal stormwater management facility operation and maintenance fund to help defray costs of operations and maintenance activities. The amount may be determined as follows:
A. 
If the stormwater management facilities are to be owned and maintained by the Township, the amount shall cover the estimated costs for operations and maintenance for 10 years, as determined by the Township.
B. 
The amount shall then be converted to present worth of the annual series values.