Construction inspections. The Stormwater Management Officer may require such inspections as necessary to determine compliance with this chapter and may either approve that portion of the work completed or notify the applicant wherein the work fails to comply with requirements of this chapter and the stormwater pollution prevention plan (SWPPP) as approved. To obtain inspections, the applicant shall notify the Stormwater Management Officer at least 48 hours before any of the following as required by said officer:
(1) 
Start of construction.
(2) 
Installation of sediment and erosion control measures.
(3) 
Completion of site clearing.
(4) 
Completion of rough grading.
(5) 
Completion of final grading.
(6) 
Close of the construction season.
(7) 
Completion of final landscaping.
(8) 
Successful establishment of landscaping in public areas.
B. 
Stormwater management practice inspections. The Stormwater Management Officer is responsible for conducting inspections of stormwater management practices (SMPs). All applicants are required to submit as-built plans for any stormwater management practices located on site after final construction is completed. The plan must show the final design specifications for all stormwater management facilities and must be certified by a professional engineer.
C. 
Inspection of stormwater facilities after completion. Inspection programs shall be established on any reasonable basis, including but not limited to routine inspections; random inspections; inspections based upon complaints or other notice of possible violations; inspection of drainage basins or areas identified as higher-than-typical sources of sediment or other contaminants or pollutants; inspections of businesses or industries of a type associated with higher-than-usual discharges of contaminants or pollutants or with discharges of a type which are more likely than the typical discharge to cause violations of state or federal water or sediment quality standards or the SPDES stormwater permit; and joint inspections with other agencies inspecting under environmental or safety law. Inspections may include, but are not limited to, reviewing maintenance and repair records; sampling discharges, surface water, groundwater, and material or water in drainage control facilities; and evaluating the condition of drainage control facilities and other stormwater management practices.
D. 
Submission of reports. The Stormwater Management Officer may require monitoring and reporting from entities subject to this chapter as are necessary to determine compliance with this chapter.
E. 
Right of entry for inspection. When any new stormwater management facility is installed on private property or when any new connection is made between private property and the public stormwater system, the landowner shall grant to the Village of Port Chester the right to enter the property at reasonable times and in a reasonable manner for the purpose of inspection as specified in § 281-21C.
A. 
Construction completion guarantee. In order to ensure the full and faithful completion of all land development activities related to compliance with all conditions set forth by the Village of Port Chester in its approval of the stormwater pollution prevention plan, the Village may require the applicant or developer to provide, prior to construction, a performance bond, cash escrow, or irrevocable letter of credit from an appropriate financial or surety institution which guarantees satisfactory completion of the project and names the Village of Port Chester as the beneficiary. The security shall be in an amount to be determined by the Village of Port Chester based on submission of final design plans, with reference to actual construction and landscaping costs. The performance guarantee shall remain in force until the surety is released from liability by the Village of Port Chester, provided that such period shall not be less than one year from the date of final acceptance or such other certification that the facility(ies) has (have) been constructed in accordance with the approved plans and specifications and that a one-year inspection has been conducted and the facilities have been found to be acceptable to the Stormwater Management Officer. Per annum interest on cash escrow deposits shall be reinvested in the account until the surety is released from liability.
B. 
Maintenance guarantee. Where stormwater management and erosion and sediment control facilities are to be operated and maintained by the developer or by a corporation that owns or manages a commercial or industrial facility, the developer, prior to construction, may be required to provide the Village of Port Chester with an irrevocable letter of credit from an approved financial institution or surety to ensure proper operation and maintenance of all stormwater management and erosion control facilities both during and after construction and until the facilities are removed from operation. If the developer or landowner fails to properly operate and maintain stormwater management and erosion and sediment control facilities, the Village of Port Chester may draw upon the account to cover the costs of proper operation and maintenance, including engineering and inspection costs.
C. 
Recordkeeping. The Village of Port Chester may require entities subject to this chapter to maintain records demonstrating compliance with this chapter.
A. 
Notice of violation. When the Village of Port Chester determines that a land development activity is not being carried out in accordance with the requirements of this chapter, it may issue a written notice of violation to the landowner. The notice of violation shall contain:
(1) 
The name and address of the landowner, developer or applicant.
(2) 
The address, when available, or a description of the building, structure or land upon which the violation is occurring.
(3) 
A statement specifying the nature of the violation.
(4) 
A description of the remedial measures necessary to bring the land development activity into compliance with this chapter, and a time schedule for the completion of such remedial action.
(5) 
A statement of the penalty or penalties that shall or may be assessed against the person to whom the notice of violation is directed.
B. 
Stop-work order. The Village of Port Chester may issue a stop-work order for violations of this chapter. Persons receiving a stop-work order shall be required to halt all land development activities, except those activities that address the violations leading to the stop-work order. The stop-work order shall be in effect until the Stormwater Management Officer confirms that the land development activity is in compliance and the violation has been satisfactorily addressed. Failure to address a stop-work order in a timely manner will result in immediate efforts to compel compliance as set forth hereinafter in this chapter.
C. 
Violations. Any land development activity that is commenced or is conducted contrary to this chapter may be restrained by injunction or otherwise abated in a manner provided by law.
D. 
Penalties. Each day a violation of this chapter is allowed to exist after the allotted time for its cure, if any, shall constitute a separate and distinct violation. In addition to or as an alternative to any penalty provided herein or by law, any person who violates the provisions of this chapter shall be guilty of a first offense shall be subject to a fine not exceeding $700 for each violation and/or imprisonment up to 15 days, and each such offense shall constitute a violation. Persons found guilty of a second offense, both of which were committed within a period of 10 years, shall be subject to a fine of not less than $700 nor more than $1,400 and/or imprisonment up to one year, and shall constitute a misdemeanor; upon conviction of a third or subsequent offense, all of which offenses were committed within a period of 10 years, shall be subject to a fine not less than $1,400 and/or imprisonment up to one year, and shall constitute a misdemeanor.
If any building or land development activity is installed or conducted in violation of this chapter, the Stormwater Management Officer may withhold the issuance of a certificate of occupancy.
Any violator may be required to restore land to its undisturbed condition. In the event that restoration is not undertaken within a reasonable time after notice, the Village may take necessary corrective action, the cost of which shall become a lien upon the property until paid after due notice thereof.