A.
Erosion and sediment control inspection.
(1)
The Town Stormwater Management Office may require
such inspections as necessary to determine compliance with this chapter
and may either approve that portion of the work completed or notify
the applicant wherein the work fails to comply with the requirements
of this chapter and the stormwater pollution prevention plan (SWPPP)
as approved. To obtain inspections, the applicant shall notify the
Town enforcement official at least 48 hours before any of the following
as required by the Stormwater Management Officer:
(a)
Start of construction.
(b)
Installation of sediment and erosion control
measures.
(c)
Completion of site clearing.
(d)
Completion of rough grading.
(e)
Completion of final grading.
(f)
Close of the construction season.
(g)
Completion of final landscaping.
(h)
Successful establishment of landscaping in public
areas.
(2)
If any violations are found, the applicant and developer
shall be notified, in writing, of the nature of the violation and
the required corrective actions. No further work shall be conducted
except for site stabilization until any violations are corrected and
all work previously completed has received approval by the Stormwater
Management Officer.
B.
Stormwater management practice inspections. The Town
Stormwater Management Officer is responsible for conducting inspections
of stormwater management practices (SMPs). All applicants are required
to submit as-built plans for any stormwater management practices located
on site after final construction is completed. The plan must show
the final design specifications for all stormwater management facilities
and must be certified by a professional engineer.
C.
Inspection of stormwater facilities after project
completion. Inspection programs shall be established on any reasonable
basis, including, but not limited to: routine inspections; random
inspections; inspections based upon complaints or other notice of
possible violations; inspection of drainage basins or areas identified
as higher-than-typical sources of sediment or other contaminants or
pollutants; inspections of businesses or industries of a type associated
with higher-than-usual discharges of contaminants or pollutants or
with discharges of a type which are more likely than the typical discharge
to cause violations of state or federal water or sediment quality
standards or the SPDES stormwater permit; and joint inspections with
other agencies inspecting under environmental or safety laws. Inspections
may include, but are not limited to: reviewing maintenance and repair
records; sampling discharges, surface water, groundwater, and material
or water in drainage control facilities; and evaluating the condition
of drainage control facilities and other stormwater management practices.
D.
Submission of reports. The Town Stormwater Management
Officer may require monitoring and reporting from entities subject
to this chapter as are necessary to determine compliance with this
chapter.
E.
Right-of-way inspection. When any new stormwater management facility is installed on private property or when any new connection is made between private property and the public storm water system, the landowner shall grant to the Town the right to enter the property at reasonable times and in a reasonable manner for the purpose of inspection as specified in Subsection C.
A.
Construction completion guarantee. In order to ensure
the full and faithful completion of all land development activities
related to compliance with all conditions set forth by the Town in
its approval of the stormwater pollution prevention plan, the Town
may require the applicant or developer to provide, prior to construction,
a performance bond, cash escrow, or irrevocable letter of credit from
an appropriate financial or surety institution which guarantees satisfactory
completion of the project and names the Town as the beneficiary. The
security shall be in an amount to be determined by the Town based
on submission of final design plans, with reference to actual construction
and landscaping costs. The performance guarantee shall remain in force
until the surety is released from liability by the Town, provided
that such period shall not be less than one year from the date of
final acceptance or such other certification that the facility(ies)
have been constructed in accordance with the approved plans and specifications
and that a one-year inspection has been conducted and the facilities
have been found to be acceptable to the Town. Per annum interest on
cash escrow deposits shall be reinvested in the account until the
surety is released from liability.
B.
Maintenance guarantee. Where stormwater management
and erosion and sediment control facilities are to be operated and
maintained by the developer or by a corporation that owns or manages
a commercial or industrial facility, the developer, prior to construction,
may be required to provide the Town with an irrevocable letter of
credit from an approved financial institution or surety to ensure
proper operation and maintenance of all stormwater management and
erosion control facilities both during and after construction, and
until the facilities are removed from operation. If the developer
or landowner fails to properly operate and maintain stormwater management
and erosion and sediment control facilities, the Town may draw upon
the account to cover the costs of proper operation and maintenance,
including engineering and inspection costs.
C.
Recordkeeping. The Town may require entities subject
to this chapter to maintain records demonstrating compliance with
this chapter.
A.
Notice of violation. When the Town determines that
a land development activity is not being carried out in accordance
with the requirements of this chapter, it may issue a written notice
of violation to the landowner. The notice of violation shall contain:
(1)
The name and address of the landowner, developer or
applicant;
(2)
The address when available or a description of the
building, structure or land upon which the violation is occurring;
(3)
A statement specifying the nature of the violation;
(4)
A description of the remedial measures necessary to
bring the land development activity into compliance with this chapter
and a time schedule for the completion of such remedial action;
(5)
A statement of the penalty or penalties that shall
or may be assessed against the person to whom the notice of violation
is directed;
(6)
A statement that the determination of violation may
be appealed to the municipality by filing a written notice of appeal
within 15 days of service of notice of violation.
B.
Stop-work orders. The Town may issue a stop-work order
for violations of this chapter. Persons receiving a stop-work order
shall be required to halt all land development activates, except those
activities that address the violations leading to the stop-work order.
The stop-work order shall be in effect until the Town confirms that
the land development activity is in compliance and the violation has
been satisfactorily addressed. Failure to address a stop-work order
in a timely manner may result in civil, criminal, or monetary penalties
in accordance with the enforcement measures authorized in this chapter.
C.
Violations. Any land development activity that is
commenced or is conducted contrary to this chapter may be restrained
by injunction or otherwise abated in a manner provided by law.
D.
Penalties. In addition to or as an alternative to
any penalty provided herein or by law, any person who violates the
provisions of this chapter shall be guilty of a violation punishable
by a fine not exceeding $350 or imprisonment for a period not to exceed
six months, or both, for conviction of a first offense; for conviction
of a second offense both of which were committed within a period of
five years, punishable by a fine not less than $350 nor more than
$700 or imprisonment for a period not to exceed six months, or both;
and upon conviction for a third or subsequent offense all of which
were committed within a period of five years, punishable by a fine
not less than $700 nor more than $1,000 or imprisonment for a period
not to exceed six months, or both. However, for the purposes of conferring
jurisdiction upon courts and judicial officers generally, violations
of this chapter shall be deemed misdemeanors and for such purpose
only all provisions of law relating to misdemeanors shall apply to
such violations. Each week's continued violation shall constitute
a separate additional violation.
E.
Withholding of certificate of occupancy. If any building
or land development activity is installed or conducted in violation
of this chapter, the Stormwater Management Officer may prevent the
occupancy of said building or land.
F.
Restoration of lands. Any violator may be required
to restore land to its undisturbed condition. In the event that restoration
is not undertaken within a reasonable time after notice, the Town
may take necessary corrective action, the cost of which shall become
a lien upon the property until paid.
The Town may require any person undertaking
land development activities regulated by this chapter to pay reasonable
costs at prevailing rates for review of SWPPPs, inspections, or SMP
maintenance performed by the Town or performed by a third party for