A.
The Municipal Engineer or his municipal designee shall inspect all
phases of the installation of the permanent BMPs and/or stormwater
management facilities as deemed appropriate by the Municipal Engineer.
B.
During any stage of the work, if the Municipal Engineer or his municipal
designee determines that the permanent BMPs and/or stormwater management
facilities are not being installed in accordance with the approved
stormwater management plan, the municipality shall revoke any existing
permits or other approvals and issue a cease and desist order until
a revised drainage plan is submitted and approved, as specified in
this chapter, and until the deficiencies are corrected.
C.
A final inspection of all BMPs and/or stormwater management facilities
shall be conducted by the Municipal Engineer or his municipal designee
to confirm compliance with the approved drainage plan prior to the
issuance of any occupancy permit.