(a) 
Unless specifically defined below, words or phrases used in this chapter shall be interpreted so as to give them the meaning they have in common usage and to give this chapter its most reasonable application.
(b) 
As used in this chapter, the following shall have the meanings indicated:
AH ZONE
Areas subject to inundation by 1% annual chance shallow flooding (usually areas of ponding) where average depths are between one and three feet. Base flood elevations (BFEs) derived from detailed hydraulic analyses are shown in this zone.
AO ZONE
Areas subject to inundation by 1% annual chance shallow flooding (usually sheet flow on sloping terrain) where average depths are between one and three feet.
APPEAL
A request for a review of the Township Engineer's interpretation of any provision of this chapter or a request for a variance.
AREA OF SHALLOW FLOODING
A designated AO or AH Zone on a community's Flood Insurance Rate Map (FIRM) with a 1% or greater annual chance of flooding to an average depth of one to three feet where a clearly defined channel does not exist, where the path of flooding is unpredictable and where velocity flow may be evident. Such flooding is characterized by ponding or sheet flow.
AREA OF SPECIAL FLOOD HAZARD
Land in the floodplain within a community subject to a 1% or greater chance of flooding in any given year. It is shown on the FIRM as Zone V, VE, V1-30, A, AO, A1-A30, AE, A99, or AH.
BASE FLOOD
A flood having a 1% chance of being equaled or exceeded in any given year.
BASE FLOOD ELEVATION (BFE)
The flood elevation shown on a published Flood Insurance Study (FIS), including the Flood Insurance Rate Map (FIRM). For Zones AE, AH, AO, and A1-30, the elevation represents the water surface elevation resulting from a flood that has a 1% or greater chance of being equaled or exceeded in any given year.
BASEMENT
Any area of the building having its floor subgrade (below ground level) on all sides.
BEST AVAILABLE FLOOD HAZARD DATA
The most recent available flood risk guidance FEMA has provided. The best available flood hazard data may be depicted on, but not limited to, advisory flood hazard area maps, work maps or preliminary FIS and FIRM.
BEST AVAILABLE FLOOD HAZARD DATA ELEVATION
The most recent available flood elevation FEMA has provided. The best available flood hazard data elevation may be depicted on an advisory flood hazard area map, work map or preliminary FIS and FIRM.
BREAKAWAY WALL
A wall that is not part of the structural support of the building and is intended through its design and construction to collapse under specific lateral loading forces without causing damage to the elevated portion of the building or supporting foundation system.
DEVELOPMENT
Any man-made change to improved or unimproved real estate, including, but not limited to, buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations, or storage of equipment or materials located within the area of special flood hazard.
ELEVATED BUILDING
A nonbasement building built, in the case of a building in an area of special flood hazard, to have the top of the elevated floor elevated above the base flood elevation plus freeboard by means of piling, columns (posts and piers), or shear walls parallel to the flow of the water, and adequately anchored so as not to impair the structural integrity of the building during a flood up to the magnitude of the base flood. In an area of special flood hazard, "elevated building" also includes a building elevated by means of fill or solid foundation perimeter walls with openings sufficient to facilitate the unimpeded movement of floodwaters.
EROSION
The process of gradual wearing away of land masses.
EXISTING MANUFACTURED HOME PARK OR SUBDIVISION
A manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including, at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed before the effective date of the floodplain management regulations adopted by a community.
FLOOD INSURANCE RATE MAP (FIRM)
The official map on which the Federal Insurance Administration has delineated both the areas of special flood hazard and the risk premium zones applicable to the community.
FLOOD INSURANCE STUDY (FIS)
The official report in which the Federal Insurance Administration has provided flood profiles, as well as the Flood Insurance Rate Map(s) and the water surface elevation of the base flood.
FLOOD or FLOODING
A general and temporary condition of partial or complete inundation of normally dry land areas from:
(1) 
The overflow of inland or tidal waters; and/or
(2) 
The unusual and rapid accumulation or runoff of surface waters from any source.
FLOODPLAIN MANAGEMENT REGULATIONS
Zoning ordinances, subdivision regulations, building codes, health regulations, special purpose ordinances (such as a floodplain ordinance, grading ordinance and erosion control ordinance) and other applications of police power. The term describes such state or local regulations, in any combination thereof, which provide standards for the purpose of flood damage prevention and reduction.
FLOODPROOFING
Any combination of structural and nonstructural additions, changes, or adjustments to structures which reduce or eliminate flood damage to real estate or improved real property, water and sanitary facilities, structures and their contents.
FLOODWAY
The channel of a river or other watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without accumulatively increasing the water surface elevation more than 0.2 foot.
FREEBOARD
A factor of safety usually expressed in feet above a flood level for purposes of floodplain management. "Freeboard" tends to compensate for the many unknown factors that could contribute to flood heights greater than the height calculated for a selected size flood and floodway conditions, such as wave action, bridge openings, and the hydrological effect of urbanization of the watershed.
HIGHEST ADJACENT GRADE
The highest natural elevation of the ground surface prior to construction next to the proposed or existing walls of a structure.
HISTORIC STRUCTURE
Any structure that is:
(1) 
Listed individually in the National Register of Historic Places (a listing maintained by the Department of the Interior) or preliminarily determined by the Secretary of the Interior as meeting the requirements for individual listing on the National Register;
(2) 
Certified or preliminarily determined by the Secretary of the Interior as contributing to the historical significance of a registered historic district or a district preliminarily determined by the Secretary to qualify as a registered historic district;
(3) 
Individually listed on a state inventory of historic places in states with historic preservation programs which have been approved by the Secretary of the Interior; or
(4) 
Individually listed on a local inventory of historic places in communities with historic preservation programs that have been certified either:
a. 
By an approved state program as determined by the Secretary of the Interior; or
b. 
Directly by the Secretary of the Interior in states without approved programs.
LOWEST FLOOR
The lowest floor of the lowest enclosed area (including basement). An unfinished or flood-resistant enclosure, usable solely for the parking of vehicles, building access or storage in an area other than a basement is not considered a building's lowest floor, provided that such enclosure is not built so to render the structure in violation of other applicable nonelevation design requirements of 44 CFR 60.3.
MANUFACTURED HOME
A structure, transportable in one or more sections, which is built on a permanent chassis and is designed for use with or without a permanent foundation when attached to the required utilities. The term "manufactured home" does not include a recreational vehicle.
MANUFACTURED HOME PARK or MANUFACTURED HOME SUBDIVISION
A parcel (or contiguous parcels) of land divided into two or more manufactured home lots for rent or sale.
NEW CONSTRUCTION
Structures for which the start of construction commenced on or after the effective date of a floodplain regulation adopted by a community and includes any subsequent improvements to such structures.
NEW MANUFACTURED HOME PARK OR SUBDIVISION
A manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including, at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed on or after the effective date of the floodplain management regulations adopted by the municipality.
PRELIMINARY FLOOD INSURANCE RATE MAP (PRE FIRM)
The draft version of the FIRM released for public comment before finalization and adoption.
RECREATIONAL VEHICLE
A vehicle which is built on a single chassis; 400 square feet or less when measured at the longest horizontal projections; designed to be self-propelled or permanently towable by a light-duty truck; and designed primarily not for use as a permanent dwelling but as temporary living quarters for recreational, camping, travel, or seasonal use.
START OF CONSTRUCTION
For other than new construction or substantial improvements under the Coastal Barrier Resources Act (P.L. No. 97-348), 16 U.S.C. §§ 3501 to 3509, includes substantial improvements and means the date the building permit was issued, provided the actual start of construction, repair, reconstruction, rehabilitation, addition, placement, or other improvement was within 180 days of the permit date. The actual start means either the first placement of permanent construction of a structure on a site such as the pouring of a slab or footings, the installation of pilings, the construction of columns, or any work beyond the stage of excavation, or the placement of a manufactured home on a foundation. Permanent construction does not include land preparation, such as clearing, grading and filling nor does it include the installation of streets and/or walkways, nor does it include excavation for a basement, footings or piers, or foundations or the erection of temporary forms, nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not part of the main structure. For a substantial improvement, the actual start of construction means the first alteration of any wall, ceiling, floor, or other structural part of a building, whether or not that alteration affects the external dimensions of the building.
STRUCTURE
A walled and roofed building, a manufactured home, or a gas or liquid storage tank that is principally above ground.
SUBSTANTIAL DAMAGE
Damage of any origin sustained by a structure whereby the cost of restoring the structure to its condition before damage would equal or exceed 50% of the market value of the structure before the damage occurred.
SUBSTANTIAL IMPROVEMENT
Any reconstruction, rehabilitation, addition, or other improvement of a structure, the cost of which equals or exceeds 50% of the market value of the structure before the start of construction of the improvement. This term includes structures which have incurred substantial damage, regardless of the actual repair work performed. The term does not, however, include either:
(1) 
Any project for improvement of a structure to correct existing violations of state or local health, sanitary or safety code specifications which have been identified by the local code enforcement officer and which are the minimum necessary to ensure safe living conditions; or
(2) 
Any alteration of an historic structure, provided that the alteration will not preclude the structure's continued designation as an historic structure.
VARIANCE
A grant of relief from the requirements of this chapter that permits construction in a manner that would otherwise be prohibited by this chapter.
VIOLATION
The failure of a structure or other development to be fully compliant with this chapter. A new or substantially improved structure or other development without the elevation certificate, other certifications, or other evidence of compliance required in 44 CFR 60.3(b)(5), (c)(4), (c)(10), (e)(2), (e)(4), or (e)(5) is presumed to be in violation until such time as that documentation is provided.