[Adopted 12-20-1995]
[Amended 9-17-2002 by Res. No. 2002-10; 5-6-2003 by Res. No. 2003-09; 3-1-2005 by Res. No. 2005-04; 11-15-2005 by Res. No. 2005-10A; 2-6-2007 by Res. No. 2007-03; 10-3-2007 by Res. No. 2007-08; 1-5-2009 by Res. No. 2009-01]
A. 
The following fee schedule is hereby adopted.
(1) 
Building permits: $60, plus $3 per thousand of construction over $2,000.
[Amended 11-21-2017 by Res. No. 2017-12]
(2) 
Zoning permits: $60, plus $3 per thousand of construction over $2,000
[Amended 11-21-2017 by Res. No. 2017-12]
(3) 
Demolition permits: $75.
[Amended 11-21-2017 by Res. No. 2017-12]
(4) 
Inspection fees: 15% above inspection agency.
(5) 
Tool / tent sales: $150.
[Amended 11-21-2017 by Res. No. 2017-12]
(6) 
Business occupancy permit: $50.
(7) 
Land development: $175, plus engineering fees.
[Amended 11-21-2017 by Res. No. 2017-12]
(8) 
Subdivision: $75 per lot.
[Amended 11-21-2017 by Res. No. 2017-12]
(9) 
Major subdivision: $300 first lot; $25 for each additional lot; plus engineers' cost.
[Amended 11-21-2017 by Res. No. 2017-12]
(10) 
Junkyard license, to be allocated for the type of activity conducted within the yard (recycling, scrap or salvage):
[Amended 4-16-2013 by Res. No. 2013-03; 11-21-2017 by Res. No. 2017-12]
(a) 
One activity: $200.
(b) 
Any two activities: $300.
(c) 
All three activities: $400.
(11) 
Sewer tap: $750.
[Amended 11-21-2017 by Res. No. 2017-12]
(12) 
Sewer surcharge: $8 per thousand gallons of usage.
[Amended 2-5-2013 by Res. No. 2013-02; 12-3-2013 by Res. No. 2013-08; 8-18-2015 by Res. No. 2015-06; 7-19-2016 by Res. No. 2016-07]
(13) 
Vacating alleys and streets: $350.
(14) 
Variance from Zoning Hearing Board: $400.
[Amended 11-21-2017 by Res. No. 2017-12]
(15) 
Conditional use: $400.
[Amended 11-21-2017 by Res. No. 2017-12]
(16) 
Trailer park permits: $75 per year, plus $20 per trailer.
[Amended 11-21-2017 by Res. No. 2017-12]
(17) 
Road occupancy permits: $125.
[Amended 11-21-2017 by Res. No. 2017-12]
(18) 
Driveway permits: $125.
[Amended 11-21-2017 by Res. No. 2017-12]
(19) 
Timbering permits: $150.
[Amended 11-21-2017 by Res. No. 2017-12; 7-18-2023 by Res. No. 2023-03]
(20) 
Mining permits: $500.
[Amended 11-21-2017 by Res. No. 2017-12]
(21) 
On-lot sewer permits: $600.
[Amended 11-3-2009 by Res. No. 2009-13A]
(22) 
Inspection of Township roads that are to be bonded:
[Added 9-18-2017 by Res. No. 2017-09]
(a) 
For each road to be inspected, including the before-bonding and the after-bonding inspection: $95.
(b) 
Intermittent inspections of bonded roads (if required): $49.50 for each additional inspection.
(23) 
Food truck permit: $25 annual fee.
[Added 7-18-2023 by Res. No. 2023-03]
(24) 
Floodplain management permit: $50.
[Added 7-18-2023 by Res. No. 2023-03]
(25) 
Peddling and solicitation permit: $50.
[Added 7-18-2023 by Res. No. 2023-03]
B. 
Any violations of required permits will result in fees being doubled.
[Added 5-6-2003 by Res. No. 2003-09]
This schedule may be replaced or amended at any time by resolution of the Board of Supervisors.