[Ord. 705, 4/28/2011]
Fees shall be established by Warminster Township to cover plan review and construction inspection costs incurred by Warminster Township. All fees shall be paid by the applicant at the time of SWM site plan submission. No permit to begin any work on the project shall be issued until the requisite fees have been paid. A review and inspection fee schedule shall be established by resolution of the Board of Supervisors based on the size of the regulated activity and based on Warminster Township's costs for reviewing SWM site plans and conducting inspections pursuant to § 26-541. Warminster Township shall periodically update the review and inspection fee schedule to ensure that review costs are adequately reimbursed.
[Ord. 705, 4/28/2011]
The fees required by this Part 5 (unless otherwise waived by Warminster Township) shall, at a minimum, cover:
A. 
Administrative costs.
B. 
The review of the stormwater (SWM) site plan by Warminster Township and its Township Engineer. Review shall mean all technical review, meetings, and discussions relative to the plan.
C. 
Stormwater management permit issuance.
D. 
The review of as-built drawings. Review shall mean all technical review, meetings, and discussions relative to the plan.
E. 
The site inspections.
F. 
The inspection of SWM facilities and drainage improvements during construction.
G. 
The final inspection at the completion of the construction of the SWM facilities and drainage improvements presented in the SWM site plan.
H. 
Any additional work required to enforce any permit provisions regulated by this Part 5, correct violations, and assure proper completion of stipulated remedial actions.