The following improvements shall be installed by the subdivider. The final plan shall not be approved until final detailed design of the improvements is approved and the improvements are installed or acceptable financial guarantee for installation is provided to the Board of Supervisors.
[Ord. 278, 9/18/1991]
Streets shall be brought to the grades and dimensions drawn on plans, profiles, and cross sections submitted by the subdivider and approved by the Township Engineer. The subdivider must install the required utilities and provide where necessary, adequate subsurface drainage for the streets. The streets shall be designed and constructed to the standards set forth in §§ 22-503 and 22-504 of this chapter.
[Ord. 278, 9/18/1991]
Curbs and sidewalks shall be provided in accordance with the standards set forth in § 22-505 of this chapter.
[Ord. 278, 9/18/1991]
1. 
Public Sewer System. When the subdivision or land development is to be provided with a complete sanitary sewer system connected to a public sanitary sewer system, a statement of approval from the engineer of the sewerage system to which it will be connected shall be submitted to the Board of Supervisors. Where required, DEP planning module approval shall also be obtained for final plan approval.
2. 
On-Lot Sewage Disposal. In subdivisions where public sewers are not available, on-lot sewage disposal systems shall be provided where required. Allegheny County Health Department and Department of Environmental Protection planning module approval shall be obtained for final plan approval.
3. 
Capped Sewer System. Where the sanitary sewer system is not yet accessible but is planned for extension to the subdivision or development, the subdivider shall install sewer lines, including lateral connections, in order to provide service to each lot. The sewer mains shall be suitably capped at the limits of the subdivision and laterals shall be capped at the street right-of-way line when not extended to houses or other structures. When laterals are extended to houses or other structures, the internal plumbing system shall be constructed to accommodate them as well as any septic system required.
[Ord. 278, 9/18/1991]
1. 
Provision of System. The subdivision or land development shall be provided with a complete water main supply system which shall be connected to a municipal water supply or with a community water supply approved by the engineer of the applicable water utility company and the Pennsylvania Department of Environmental Protection with satisfactory provision for the maintenance thereof; except that, when such municipal or community water supply system is not available, each lot in a subdivision shall be capable of being provided with an individual water supply system in accordance with minimum standards approved by the Pennsylvania Department of Environmental Protection.
2. 
Plans. The plans for the installation of the mains of a water supply system shall be prepared for the subdivision or land development with the cooperation of the applicable water supply agency and approved by its engineer. A statement of approval from the engineer of the water supply agency to which the subdivision or land development will be connected shall be submitted to the Board of Supervisors. Upon the completion of the water supply system, one copy of each of the plans for such system shall be filed with the Township.
3. 
Fire Hydrants. Fire hydrants shall be provided as an integral part of any public water supply system. The designated Township official shall be consulted to determine the location of proposed fire hydrants.
[Ord. 278, 9/18/1991]
A storm drainage system shall be provided in accordance with the standards set forth in § 22-506 of this chapter.
[Ord. 278, 9/18/1991]
1. 
Easements for utilities shall have a minimum width of 20 feet.
2. 
To the fullest extent possible, easements for public utilities shall be centered on or adjacent to rear or side lot lines.
3. 
Telephone, electric, T.V. cable and such other utilities shall be installed underground unless impractical and shall be provided within the street right-of-way or easements to be dedicated for such utilities and in accordance with plans approved by the Board of Supervisors and the applicable utility company. Underground installation of the utility distribution and service lines shall be completed without interference to streetpaving and gutter, curbing and sidewalk installation.
[Ord. 278, 9/18/1991]
1. 
Monuments shall be of concrete or stone at least four inches in diameter by 30 inches and marked on top with a copper, brass or lead plug. They shall be set at the intersection of lines forming angles in the boundaries of the subdivision and at straight-line street segments on the interior of the subdivision as directed by the Township Engineer.
2. 
Monument Replacement. Any monuments or markers that are removed must be replaced by a registered land surveyor at the expense of the person responsible for the removal.
[Ord. 278, 9/18/1991]
1. 
Shade trees shall be provided as specified in § 22-510(8) of this chapter.
2. 
Street name signs and traffic control signs conforming to Township specifications shall be provided and installed by the subdivider or developer at all street intersections.
3. 
Open space shall be provided as specified in § 22-510(2) of this chapter.
4. 
Other improvements to promote public safety and health as required by the Board of Supervisors as a condition of approval.
[Ord. 278, 9/18/1991]
All improvements shall be installed according to a time schedule which shall be approved by the Board of Supervisors.
[Ord. 278, 9/18/1991]
At the time each improvement is to be installed and upon its completion, the subdivider shall notify the Board of Supervisors that the adequate inspections can be made. The inspection will be made by the Township Engineer or by designated Township personnel. All costs of undertaking the inspection will be borne by the subdivider.
[Ord. 278, 9/18/1991]
1. 
No plat shall be finally approved unless the streets shown on such plat have been improved to a mud-free or otherwise permanently passable condition, or improved as may be otherwise required by this chapter, and any walkways, curbs, gutters, streetlights, fire hydrants, shade trees, water mains, sanitary sewers, storm sewers and other improvements as may be required by this chapter have been installed in accordance with this chapter. In lieu of the completion of any improvements required as a condition for the final approval of a plat, including improvements or fees otherwise required by this chapter, the developer may deposit with the Township financial security in an amount sufficient to cover the related drainage facilities, recreational facilities, open space improvements or buffer or screen plantings which may be required.
2. 
When requested by the developer in order to facilitate financing, the Board of Supervisors shall furnish the developer with a signed copy of a resolution indicating approval of the final plat contingent upon the developer obtaining a satisfactory financial security. The resolution or letter of contingent agreement approval shall expire and be deemed to be revoked if the financial security agreement is not executed within 90 days, unless a written extension is granted by the Board of Supervisors; such extension shall not be unreasonably withheld and shall be placed in writing at the request of the developer.
[Amended at time of adoption of Code (see Ch. AO)]
3. 
Without limitation as to other types of financial security which the Township may approve, which approval shall not be unreasonably withheld, federal or commonwealth chartered lending institution irrevocable letters of credit and restrictive or escrow accounts in such lending institutions shall be deemed acceptable financial security for the purposes of this section.
4. 
Such financial security shall be posted with a bonding company or federal or commonwealth chartered lending institution chosen by the party posting the financial security, provided said bonding company or lending institution is authorized to conduct such business within the commonwealth.
5. 
Such bond, or other security shall provide for, and secure to the public, the completion of any improvements which may be required on or before the date fixed in the formal action of approval or accompanying agreement for completion of the improvements.
6. 
The amount of financial security to be posted for the completion of the required improvements shall be equal to 110% of the cost of completion estimated as of 90 days following the date scheduled for completion by the developer. Annually, the Township may adjust the amount of the financial security by comparing the actual cost of the improvements which have been completed and the estimated cost for the completion of the remaining improvements as of the expiration of the 90th day after either the original date scheduled for completion or a rescheduled date of completion. Subsequent to said adjustment, the Township may require the developer to post additional security in order to assure that the financial security equals said 110%. Any additional security shall be posted by the developer in accordance with this subsection.
7. 
The amount of financial security required shall be based upon an estimate of the cost of completion of the required improvements, submitted by the applicant or developer and prepared by a professional engineer licensed as such in this commonwealth and certified by such engineer to be a fair and reasonable estimate of such cost. The Township, upon the recommendation of the Township Engineer, may refuse to accept such estimate for good cause shown. If the applicant or developer and the Township are unable to agree upon an estimate, then the estimate shall be recalculated and recertified by another professional engineer licensed as such in this commonwealth and chosen mutually by the Township and the applicant or developer. The estimate certified by the third engineer shall be presumed fair and reasonable and shall be the final estimate. In the event that a third engineer is so chosen, fees for the services of said engineer shall be paid equally by the Township and the applicant or developer.
8. 
If the party posting the financial security requires more than one year from the date of posting of the financial security to complete the required improvements, the amount of financial security may be increased by an additional 10% for each one-year period beyond the first anniversary date from posting of financial security or to an amount not exceeding 110% of the cost of completing the required improvements as reestablished on or about the expiration of the preceding one-year period by using the above bidding procedure.
9. 
In the case where development is projected over a period of years, the Board of Supervisors may authorize submission of final plats by sections or stages of development, subject to such requirements or guarantees as to improvement in future sections or stages of development as it finds essential for the protection of any finally approved section of the development.
10. 
As the work of installing the required improvements proceeds, the party posting the financial security may request the Board of Supervisors to release or authorize the release, from time to time, of such portions of the financial security necessary to payment to the contractor or contractors performing the work. Any such requests shall be in writing addressed to the Board of Supervisors, and the Board of Supervisors shall have 45 days from receipt of such request within which to allow the Township Engineer to certify, in writing, to the Board of Supervisors that such portion of the work upon the improvements has been completed in accordance with the approved plat. Upon such certification, the Board of Supervisors shall authorize release by the bonding company or lending institution of an amount as estimated by the Township Engineer fairly representing the value of the improvements completed or, if the Board of Supervisors fails to act within said forty-five-day period, the Board of Supervisors shall be deemed to have approved the release of funds as requested. The Board of Supervisors may, prior to final release at the time of completion and certification by its Engineer, require retention of 10% of the estimated cost of the aforesaid improvements.
11. 
Where the Board of Supervisors accepts dedication of all or some of the required improvements following completion, the Board of Supervisors may require the posting of financial security to secure structural integrity of said improvements as well as the functioning of said improvements in accordance with the design and specifications as depicted on the final plat for a term not to exceed 18 months from the date of acceptance of dedication. Said financial security shall be of the same type as otherwise required in this section with regard to installation of such improvements, and the amount of the financial security shall not exceed 15% of the actual cost of installation of said improvements.
12. 
If water mains or sanitary sewer lines, or both, along with apparatus or facilities related thereto, are to be installed under the jurisdiction and pursuant to the rules and regulations of a public utility or municipal authority separate and distinct from the Township, financial security to assure proper completion and maintenance thereof shall be posted in accordance with the regulations of the controlling public utility or municipal authority and shall not be included within the financial security as otherwise required by this section.
13. 
If financial security has been provided in lieu of the completion of improvements required as a condition for the final approval of a plat as set forth in this section, the Township shall not condition the issuance of building, grading or other permits relating to the erection or placement of improvements, including buildings, upon the lots or land as depicted upon the final plan upon actual completion of the improvements depicted upon the approved final plat. Moreover, if said financial security has been provided, occupancy permits for any building or buildings to be erected shall not be withheld following the improvement of the streets providing access to and from public roads to such building or buildings to a mud-free or otherwise permanently passable condition, as well as the completion of all other improvements as depicted upon the approved plat, either upon the lot or lots or beyond the lot or lots in question if such improvements are necessary for the reasonable use of or occupancy of the building or buildings.
[Ord. 278, 9/18/1991]
1. 
When the developer has completed all of the necessary and appropriate improvements, the developer shall notify the Board of Supervisors, in writing, by certified or registered mail, of the completion of the aforesaid improvements and shall send a copy thereof to the Township Engineer. The Board of Supervisors shall, within 10 days after receipt of such notice, direct and authorize the Township Engineer to inspect all of the aforesaid improvements. The Township Engineer shall, thereupon, file a report in writing, with the Board of Supervisors and shall promptly mail a copy of the same to the developer by certified or registered mail. The report shall be made and mailed within 30 days after receipt by the Township Engineer of the aforesaid authorization from the Board of Supervisors; said report shall be detailed and shall indicate approval or rejection of said improvements, either in whole or in part; and if said improvements, or any portion thereof, shall not be approved or shall be rejected by the Township Engineer, said report shall contain a statement of reasons for such nonapproval or rejection.
2. 
The Board of Supervisors shall notify the developer, within 15 days of receipt of the engineer's report, in writing, by certified or registered mail, of the action of said Board of Supervisors with relation thereto.
3. 
If the Board of Supervisors or the Township Engineer fails to comply with the time limitation provisions contained herein, all improvements will be deemed to have been approved and the developer shall be released from all liability, pursuant to its performance guaranty, bond or other security agreement.
4. 
If any portion of the said improvements shall not be approved or shall be rejected by the Board of Supervisors, the developer shall proceed to complete the same; and, upon completion, the same procedure of notification, as outlined herein, shall be followed.
5. 
Nothing herein, however, shall be construed in limitation of the developer's right to contest or question, by legal proceedings or otherwise, any determination of the Board of Supervisors or the Township Engineer.
6. 
Where herein reference is made to the Township Engineer, he shall be a duly registered professional engineer employed by the municipality or engaged as a consultant thereto.
[Amended at time of adoption of Code (see Ch. AO)]
7. 
The applicant or developer shall reimburse the Township for the reasonable and necessary expense incurred for the inspection of improvements according to the schedule of fees adopted by resolution of the Board of Supervisors and as from time to time amended. Such reimbursement shall be subject to and in accordance with the requirements and procedures set forth in the Municipalities Planning Code, § 510(g).[1]
[Amended at time of adoption of Code (see Ch. AO)]
[1]
Editor's Note: See 53 P.S. § 10510(g).
[Ord. 278, 9/18/1991]
In the event that any improvements which may be required have not been installed as provided in this chapter or in accord with the approved final plat, the Board of Supervisors is hereby granted the power to enforce any corporate bond or other security by appropriate legal and equitable remedies. If the proceeds of such bond or other security are insufficient to pay the cost of installing or making repairs or correction to all the improvements covered by said security, the Board of Supervisors may, at its option, install part of such improvements in all or part of the subdivision or land development and may institute appropriate legal or equitable action to recover the moneys necessary to complete the remainder of the improvements. All of the proceeds, whether resulting from the security or from any legal or equitable action brought against the developer, or both, shall be used solely for the installation of the improvements covered by such security and not for any other Township purpose.