[Ord. No. 01-061 §§1—8, 5-30-2001]
A. 
No person shall construct a solid waste disposal area waste processing facility or transfer station in a manner that does not comply with the waste facility plan approved by the Division Director or the County Council for such facility or with the requirements of this Chapter.
B. 
Site development plans shall address consideration for minimizing incremental disturbance of land mass by providing a logical and detailed sequence of cell excavation, soil stockpiling, closure and cut/fill activities.
C. 
Construction plans shall provide sufficient detail and quality assurance/quality control protocol including utilization of third (3rd) party independent consulting engineer oversight to assure integrity of major landfill infrastructure components including, but not limited to, the following:
1. 
Recompacted earthen material liners/capping systems.
2. 
Synthetic liners.
3. 
Composite lining/capped systems.
4. 
Leachate underdrain, collection end treatment systems.
5. 
LFG active extraction, recovery and treatment systems.
6. 
Stormwater retention and dissipation structures.
D. 
As-built plans and quality assurance/quality control records documenting incremental completion of construction/installation of the major infrastructure components detailed in the preceding condition shall be prepared by the registered professional engineer or certified environmental professional of record for the project and submitted to the Division of Environmental Services for approval following acceptance and sign-off by the applicant/facility operator.
[Ord. No. 01-061 §§1—8, 5-30-2001]
During any period of construction (initial, expansion or modification) of a solid waste disposal area, waste processing facility or transfer station, the Division Director or authorized staff shall be permitted access to the facility at reasonable times for the purpose of determining whether the construction of the facility conforms to the waste facility plan. The applicant shall be notified of any deficiencies or discrepancies identified during such inspections and provided ten (10) days to respond. The Division Director shall order construction to cease and desist until such discrepancies are satisfactorily resolved upon staff reinspection.
[Ord. No. 01-061 §§1—8, 5-30-2001]
Notwithstanding the final approval of a waste facility plan and issuance of a license to construct and operate a solid waste disposal area, waste processing facility or transfer station, the facility shall not begin to operate and accept waste until there is final approval in writing by the Division Director indicating that a final inspection of the facility following construction has been completed and that the facts then in possession of the Division Director indicate that the facility has been constructed according to the waste facility plan. Final approval in writing by the Division Director is also required for final construction of a facility modification prior to continued operation in an area affected by the construction.