A.
General design guidelines.
(1)
Stormwater shall not be transferred from one watershed to another,
unless:
(2)
Consideration shall be given to the relationship of the subject property
to the drainage pattern of the watershed. A concentrated discharge
of stormwater to an adjacent property shall be within an existing
watercourse or confined in an easement or returned to a predevelopment
flow type condition.
(3)
Low-impact design stormwater BMPs and recharge facilities are encouraged
(e.g., rooftop storage, dry wells, cisterns, recreation area ponding,
diversion structures, porous pavements, holding tanks, infiltration
systems, in-line storage in storm sewers, and grading patterns). They
shall be located, designed and constructed in accordance with the
latest technical guidance published by PADEP, provided they are accompanied
by detailed engineering plans and performance capabilities and supporting
site-specific soils, geology, runoff and groundwater and infiltration
rate data to verify proposed designs. Additional guidance from other
sources may be accepted at the discretion of the Municipal Engineer
(a preapplication meeting is suggested).
(4)
All existing and natural watercourses, channels, drainage systems
and areas of surface water concentration shall be maintained in their
existing condition unless an alteration is approved by the appropriate
regulatory agency.
(5)
The design of all stormwater management facilities shall incorporate
sound engineering principles and practices. The municipality shall
reserve the right to disapprove any design that would result in the
continuation or exacerbation of a documented adverse hydrologic or
hydraulic condition within the watershed, as identified in the plan.
(6)
The design and construction of multiple-use stormwater detention
facilities are strongly encouraged. In addition to stormwater management,
facilities should, where appropriate, allow for recreational uses,
including ball fields, play areas, picnic grounds, etc. Consultation
with the municipality and prior approval are required before design.
Provision for permanent wet ponds with stormwater management capabilities
may also be appropriate.
(a)
Multiple-use basins should be constructed so that potentially
dangerous conditions are not created.
(b)
Water quality basins or recharge basins that are designed for
a slow release of water or other extended detention ponds are not
permitted for recreational uses, unless the ponded areas are clearly
separated and secure.
(7)
Should any stormwater management facility require a dam safety permit
under PADEP Chapter 105, the facility shall be designed in accordance
with Chapter 105 and meet the regulations of Chapter 105 concerning
dam safety.
B.
Stormwater management facility design considerations. All stormwater
management facilities shall meet the following design requirements:
(1)
No outlet structure from a stormwater management facility or swale
shall discharge directly onto a municipal or state roadway.
(2)
The top or toe of any slope shall be located a minimum of 10 feet
from any property line.
(3)
The minimum horizontal distance between any structure and any stormwater
facility shall be 25 feet. The lowest floor elevation of any structure
constructed immediately adjacent to a detention basin or other stormwater
facility shall be a minimum of two feet above the one-hundred-year
water surface elevation.
(4)
Stormwater management facility bottom (or surface of permanent pool)
elevations must be greater than adjacent floodplain elevations (FEMA
or HEC-RAS analysis). If no floodplain is defined, bottom elevations
must be greater than existing ground elevations 50 feet from top of
stream bank in the facilities' vicinity.
(5)
Basin outflow culverts discharging into floodplains must account
for tailwater. Tailwater corresponding to the one-hundred-year floodplain
elevation must be used for all design storms, or the applicant may
elect to determine flood elevations of the adjacent watercourse for
each design storm. The floodplain is assumed to be 50 feet from top
of stream bank in areas where a floodplain is not designated or no
other evidence is provided.
(6)
The invert of all stormwater management facilities and underground
infiltration/storage facilities shall be located a minimum of two
feet above the seasonal high groundwater table. The invert of stormwater
facilities may be lowered if adequate subsurface drainage is provided.
(7)
Whenever possible the side slopes and basin shape shall be amenable
to the natural topography. Vertical side slopes and rectangular basins
shall be avoided whenever possible.
(8)
Exterior slopes of compacted soil shall not exceed 3:1 and may be
further reduced if the soil has unstable characteristics.
(9)
Interior slopes of the basin shall not exceed 3:1.
(10)
Unless specifically designed as a volume control facility, all
stormwater management facilities shall have a minimum slope of 1%,
extending radially out from the principal outlet structure. Facilities
designed as water quality/infiltration BMPs may have a bottom slope
of zero.
(11)
Impervious low-flow channels are not permitted within stormwater
management facilities.
(12)
Unless specifically designed as a volume control or water quality
facility, all stormwater management facilities must empty over a period
of time not less than 24 hours and not more than 72 hours from the
end of the facility's inflow hydrograph. Infiltration tests performed
at the facility locations and proposed basin bottom depths, in accordance
with the BMP Manual, must support time-to-empty calculations if infiltration
is a factor.
(13)
Energy dissipators and/or level spreaders shall be installed
at points where pipes or drainageways discharge to or from basins.
Discharges to drainage swales shall be dissipated or piped to an acceptable
point.
(14)
Landscaping and planting specifications must be provided for
all stormwater management basins and be specific for each type of
basin.
(a)
Minimal maintenance, saturation-tolerant vegetation must be
provided in basins designed as water quality/infiltration BMPs.
(15)
A safety fence may be required, at the discretion of the municipality,
for any stormwater management facility. The fence shall be a minimum
of four feet high and of a material acceptable to the municipality.
A gate with a minimum opening of 10 feet shall be provided for maintenance
access.
(16)
Karst. The following apply to all stormwater management facilities
located within karst topography.
(17)
Principal outlet structures. The primary outlet structure shall
be designed to pass all twenty-four-hour design storms (up to and
including the one-hundred-year event) without discharging through
the emergency spillway. All principal outlet structures shall:
(a)
Be constructed of reinforced concrete or an alternative material
approved by the Municipal Engineer. When approved for use, all metal
risers shall:
[1]
Be suitably coated to prevent corrosion.
[2]
Have a concrete base attached with a watertight connection.
The base shall be sufficient weight to prevent flotation of the riser.
[3]
Provide a trash rack or similar appurtenance to prevent debris
from entering the riser.
[4]
Provide an anti-vortex device, consisting of a thin vertical
plate normal to the basin berm.
(b)
Provide trash racks to prevent clogging of primary outflow structure
stages for all orifices equivalent to 12 inches or smaller in diameter.
(c)
Provide outlet aprons and shall extend to the toe of the basin
slope at a minimum.
(18)
Emergency spillways. Any stormwater management facility designed
to store runoff shall provide an emergency spillway designed to convey
the one-hundred-year post-development peak rate flow with a blocked
primary outlet structure. The emergency spillway shall be designed
per the following requirements:
(a)
The top of embankment elevation shall provide a minimum one
foot of freeboard above the maximum water surface elevation. This
is to be calculated when the spillway functions for the one-hundred-year
post-development inflow with a blocked outlet structure.
(b)
Avoid locating on fill areas, whenever possible.
(c)
The spillway shall be armored to prevent erosion during the
one-hundred-year post-development flow with a blocked primary outlet
structure.
[1]
Synthetic liners or riprap may be used, and calculations sufficient
to support proposed armor must be provided. An earthen plug must be
used to accurately control the spillway invert if riprap is the proposed
armoring material. Emergency spillway armor must extend up the sides
of the spillway and continue at full width to a minimum of 10 feet
past the toe of slope.
(d)
Municipal Engineer may require the use of additional protection
when slopes exceed 4:1 and spillway velocities might exceed NRCS standards
for the particular soils involved.
(e)
Any underground stormwater management facility (pipe storage
systems) must have a method to bypass flows higher than the required
design (up to a one-hundred-year post-development inflow) without
structural failure or causing downstream harm or safety risks.
(19)
Stormwater management basins. Design of stormwater management
facilities having three feet or more of water depth (measured vertically
from the lowest elevation in the facility to the crest of the emergency
spillway) shall meet the following additional requirements:
(a)
The maximum water depth within any stormwater management facility
shall be no greater than eight feet when functioning through the primary
outlet structure.
(b)
The top of embankment width shall be at least 10 feet.
(c)
A ten-foot-wide access to the basin bottom must be provided
with a maximum longitudinal slope of 10%.
(d)
Berms shall be constructed using soils that conform to the unified
soil classification of CH, MH, CL or ML. The embankments will be constructed
in a maximum of six-inch lifts. The lifts will each be compacted to
a density of 98% of a standard proctor analysis as per each layer
of compacted fill shall be tested to determine its density analysis
per ASTM 698. Each layer of compacted fill shall be tested to determine
its density per ASTM 2922 or ASTM 3017.
(e)
A cutoff and key trench of impervious material shall be provided
under all embankments four feet or greater in height. The cutoff trench
shall run the entire length of the embankment and tie into undisturbed
natural ground.
(f)
Antiseep collars, or a PADEP-approved alternative, must be provided
on all outflow culverts in accordance with the methodology contained
in the latest edition of the PADEP E&S Manual. An increase in
seepage length of 15% must be used in accordance with the requirements
for permanent antiseep collars.
(20)
Construction of stormwater management facilities.
(a)
Basins used for rate control only shall be installed prior to
or concurrent with any earthmoving or land disturbances which they
will serve. The phasing of their construction shall be noted in the
narrative and on the plan.
(b)
Basins that include water quality or recharge components shall
have those components installed in such a manner as to not disturb
or diminish their effectiveness.
(c)
Compaction test reports shall be kept on file at the site and
be subject to review at all times with copies being forwarded to the
Municipal Engineer upon request.
(d)
Temporary and permanent grasses or stabilization measures shall
be established on the sides and base of all earthen basins within
15 days of construction.
(21)
Exceptions to these requirements may be made at the discretion
of the municipality for BMPs that retain or detain water but are of
a much smaller scale than traditional stormwater management facilities.
C.
Stormwater-carrying facilities.
(1)
All storm sewer pipes, grass waterways, open channels, swales and
other stormwater-carrying facilities that service drainage areas within
the site must be able to convey post-development runoff from the ten-year
design storm.
(2)
Stormwater management facilities that convey off-site water through
the site shall be designed to convey the twenty-five-year storm event
(or larger events, as determined by the Municipal Engineer).
(3)
All developments shall include provisions that allow for the overland
conveyance and flow of the post-development one-hundred-year storm
event without damage to public or private property.
(4)
Storm sewers:
(a)
Storm sewers must be able to convey post-development runoff
without surcharging inlets for the ten-year storm event.
(b)
When connecting to an existing storm sewer system, the applicant
must demonstrate that the proposed system will not exacerbate any
existing stormwater problems and that adequate downstream capacity
exists.
(c)
Inlets, manholes, pipes and culverts shall be constructed in
accordance with the specifications set forth in PennDOT's Publication
408, and as detailed in the PennDOT's Publication 72M, Standards for
Roadway Construction (RC), or other detail approved by the Municipal
Engineer. All material and construction details (inlets, manholes,
pipe trenches, etc.), must be shown on the SWM site plan, and a note
added that all construction must be in accordance with PennDOT's Publication
408 and PennDOT's Publication 72M, latest edition. A note shall be
added to the plan stating that all frames, concrete top units, and
grade adjustment rings shall be set in a bed of full mortar according
to Publication 408.
(d)
A minimum pipe size of 15 inches in diameter shall be used in
all roadway systems (public or private) proposed for construction
in the municipality. Pipes shall be designed to provide a minimum
velocity of 2 1/2 feet per second when flowing full, but in all
cases, the slope shall be no less than 0.5%. Arch pipe of equivalent
cross-sectional area may be substituted in lieu of circular pipe where
cover or utility conflict conditions exist.
(e)
All storm sewer pipes shall be laid to a minimum depth of one
foot from subgrade to the crown of pipe.
(f)
In curbed roadway sections, the maximum encroachment of water
on the roadway pavement shall not exceed half of a through travel
lane or one inch less than the depth of curb during the ten-year design
storm of five-minute duration. Gutter depth shall be verified by inlet
capture/capacity calculations that account for road slope and opening
area.
(g)
Standard Type "C" inlets with eight-inch hoods shall be used
along curbed roadway networks. Type "C" inlets with ten-inch hoods
that provide a two-inch sump condition may be used with approval of
the Municipal Engineer when roadway longitudinal slopes are 1.0% or
less.
(h)
For inlets containing a change in pipe size, the elevation for
the crown of the pipes shall be the same or the smaller pipe's crown
shall be at a higher elevation.
(i)
All inlets shall provide a minimum two-inch drop between the
lowest inlet pipe invert elevation and the outlet pipe invert elevation.
(j)
On curbed sections, a double inlet shall be placed at the low
point of sag vertical curves, or an inlet shall be placed on each
side of the low point at a distance not to exceed 100 feet, or at
an elevation not to exceed 0.2 feet above the low point.
(k)
At all roadway low points, swales and easements shall be provided
behind the curb or swale and through adjacent properties to channelize
and direct any overflow of stormwater runoff away from dwellings and
structures.
(l)
All inlets in paved areas shall have heavy-duty bicycle safe-grating.
A note to this effect shall be added to the SWM site plan or inlet
details therein.
(m)
Inlets must be sized to accept the specified pipe sizes without
knocking out any of the inlet corners. All pipes entering or exiting
inlets shall be cut flush with the inside wall of the inlet. A note
to this effect shall be added to the SWM site plan or inlet details
therein.
(n)
Inlets shall have weep holes covered with geotextile fabric
placed at appropriate elevations to completely drain the subgrade
prior to placing the base and surface course on roadways.
(o)
Inlets, junction boxes, or manholes greater than five feet in
depth shall be equipped with ladder rungs and shall be detailed on
the SWM site plan.
(p)
Inlets shall not have a sump condition in the bottom (unless
designed as a water quality BMP). Pipe shall be flush with the bottom
of the box or concrete channels shall be poured.
(q)
Accessible drainage structures shall be located on continuous
storm sewer system at all vertical dislocations, at all locations
where a transition in storm sewer pipe sizing is required, at all
vertical and horizontal angle points exceeding 5°, and at all
points of convergence of two or more storm sewer pipes.
(r)
All storm drainage piping shall be provided with either reinforced
concrete headwalls or end sections compatible with the pipe size involved
at its entrance and discharge.
(s)
Outlet protection and energy dissipaters shall be provided at
all surface discharge points in order to minimize erosion consistent
with the E&S Manual.
[1]
Flow velocities and volumes from any storm sewer shall not result
in a degradation of the receiving channel.
(t)
Stormwater roof drains and pipes shall not be connected to storm
sewers or discharge onto impervious areas without approval by the
Municipal Engineer.
(5)
Swale conveyance facilities.
(a)
Swales must be able to convey post-development runoff from a
ten-year design storm with six inches of freeboard to top of the swale.
(b)
Swales shall have side slopes no steeper than 3:1.
(c)
All swales shall be designed, labeled on the SWM site plan,
and details provided to adequately construct and maintain the design
dimension of the swales.
(d)
Swales shall be designed for stability using velocity or shear
criteria. Velocity criteria may be used for channels with less than
ten-percent slope. Shear criteria may be used for all swales. Documentation
must be provided to support velocity and/or shear limitations used
in calculations.
(f)
Manning's "n" values used for swale capacity design must reflect
the permanent condition.
A.
All calculations shall be consistent with the guidelines set forth
in the BMP Manual, as amended herein.
B.
Stormwater runoff from all development sites shall be calculated
using either the Rational Method or the NRCS Rainfall-Runoff Methodology.
Methods shall be selected by the design professional based on the
individual limitations and suitability of each method for a particular
site.
C.
Rainfall values.
(1)
Rational Method. The Pennsylvania Department of Transportation Drainage
Manual, Intensity-Duration-Frequency Curves, Publication 584, Chapter
7A, latest edition, shall be used in conjunction with the appropriate
time of concentration and return period.
(2)
NRCS Rainfall-Runoff Method. The Soil Conservation Service Type II,
twenty-four-hour rainfall distribution shall be used in conjunction
with rainfall depths from NOAA Atlas 14 or be consistent with the
following table:
Return Interval
(year)
|
24-hour Rainfall Total
(inches)
| |
---|---|---|
1
|
2.36
| |
2
|
2.83
| |
10
|
4.10
| |
25
|
4.95
| |
50
|
5.68
| |
100
|
6.49
|
D.
Runoff volume.
(1)
Rational Method. Not to be used to calculate runoff volume.
(2)
NRCS Rainfall-Runoff Method. This method shall be used to estimate
the change in volume due to regulated activities. Combining curve
numbers for land areas proposed for development with curve numbers
for areas unaffected by the proposed development into a single weighted
curve number is not acceptable.
E.
Peak flow rates.
(1)
Rational Method. This method may be used for design of conveyance
facilities only. Extreme caution should be used by the design professional
if the watershed has more than one main drainage channel, if the watershed
is divided so that hydrologic properties are significantly different
in one versus the other, if the time of concentration exceeds 60 minutes,
or if stormwater runoff volume is an important factor. The combination
of Rational Method hydrographs based on timing shall be prohibited.
(2)
NRCS Rainfall-Runoff Method.
(a)
This method is recommended for design of stormwater management
facilities and where stormwater runoff volume must be taken into consideration.
The following provides guidance on the model applicability:
(b)
The NRCS antecedent runoff condition II (ARC II, previously
AMC II) must be used for all simulations. The use of continuous simulation
models that vary the ARC are not permitted for stormwater management
purposes.
(3)
For comparison of peak flow rates, flows shall be rounded to a tenth
of a cubic foot per second (cfs).
F.
Runoff coefficients.
(1)
Rational Method. Use Table C-1 (Appendix C).[1]
[1]
Editor's Note: Appendix C is attached to this chapter.
(2)
NRCS Rainfall-Runoff Method. Use Table C-2 (Appendix C). Curve numbers
(CN) should be rounded to tenths for use in hydrologic models as they
are a design tool with statistical variability. For large sites, CNs
should realistically be rounded to the nearest whole number.
(3)
For the purposes of predevelopment peak flow rate and volume determination,
existing nonforested pervious areas conditions shall be considered
as meadow (good condition).
(4)
For the purposes of predevelopment peak flow rate and volume determination,
20% of existing impervious area, when present, shall be considered
meadow (good condition).
G.
Design storm.
(1)
All stormwater management facilities shall be verified by routing
the proposed one-, two-, ten-, twenty-five-, fifty- and one-hundred-year
hydrographs through the facility using the Storage Indication Method
or Modified Puls Method. The twenty-four-hour design storm hydrograph
shall be computed using a calculation method that produces a full
hydrograph.
(2)
The stormwater management and drainage system shall be designed to
safely convey the post-development one-hundred-year storm event to
stormwater detention facilities for the purpose of meeting peak rate
control.
(3)
All structures (culvert or bridges) proposed to convey runoff under
a municipal road shall be designed to pass the fifty-year design storm
with a minimum one foot of freeboard measured below the lowest point
along the top of the roadway.
H.
Time of concentration.
(1)
The time of concentration is to represent the average condition that
best reflects the hydrologic response of the area. The following time
of concentration (Tc) computational methodologies
shall be used unless another method is preapproved by the Municipal
Engineer:
(a)
Predevelopment. NRCS's Lag Equation:
Time of Concentration = Tc = [(Tlag/0.6) * 60] (minutes)
|
Where:
| ||||
Tlag
|
=
|
Lag time (hours)
| ||
L
|
=
|
Hydraulic length of watershed (feet)
| ||
Y
|
=
|
Average overland slope of watershed (percent)
| ||
S
|
=
|
Maximum retention in watershed as defined by: S = [(1,000/CN)
- 10]
| ||
CN
|
=
|
NRCS curve number for watershed
|
(b)
Post-development; commercial, industrial, or other areas with
large impervious areas (greater than 20% impervious area) - NRCS Segmental
Method. The length of sheet flow shall be limited to 100 feet. Tc for channel and pipe flow shall be computed using Manning's
equation.
(c)
Post-development; residential, cluster, or other low-impact
designs less than or equal to 20% impervious area - NRCS Lag Equation
or NRCS Segmental Method.
(2)
Additionally, the following provisions shall apply to calculations
for time of concentration:
(a)
The post-development Tc shall never be
greater that the predevelopment Tc for any
watershed or subwatershed. This includes when the designer has specifically
used swales to reduce flow velocities. In the event that the designer
believes that the post-development Tc is greater,
it will still be set by default equal to the predevelopment Tc for modeling purposes.
(b)
The minimum Tc for any watershed shall
be five minutes.
(c)
The designer may choose to assume a five-minute Tc for any post-development watershed or subwatershed
without providing any computations.
(d)
The designer must provide computations for all predevelopment
Tc paths. A five-minute Tc cannot be assumed for predevelopment.
(e)
Undetained fringe areas (areas that are not tributary to a stormwater
facility but where a reasonable effort has been made to convey runoff
from all new impervious coverage to best management practices) may
be assumed to represent the predevelopment conditions for purpose
of Tc calculation.
I.
Drainage areas tributary to sinkholes or closed depressions in areas
underlain by limestone or carbonate geologic features shall be excluded
from the modeled point of analysis defining predevelopment flows.
If left undisturbed during construction activities, areas draining
to closed depressions may also be used to reduce peak runoff rates
in the post-development analysis. New additional contributing runoff
should not be directed to existing sinkholes or closed depressions.
J.
Where uniform flow is anticipated, the Manning's equation shall be
used for hydraulic computations and to determine the capacity of open
channels, pipes and storm sewers. The Manning's equation should not
be used for analysis of pipes under pressure flow or for analysis
of culverts. Manning's "n" values shall be obtained from PennDOT's
Drainage Manual, Publication 584. Inlet control shall be checked at
all inlet boxes to ensure the headwater depth during the ten-year
design event is contained below the top of grate for each inlet box.
K.
The municipality may approve the use of any generally accepted full
hydrograph approximation technique that shall use a total runoff volume
that is consistent with the volume from a method that produces a full
hydrograph.
L.
The municipality has the authority to require that computed existing
runoff rates be reconciled with field observations, conditions and
site history. If the designer can substantiate, through actual physical
calibration, that more appropriate runoff and time of concentration
values should be utilized at a particular site, then appropriate variations
may be made upon review and recommendation of the municipality.
A.
Any downstream or off-site hydraulic capacity analysis conducted
in accordance with this chapter shall use the following criteria for
determining adequacy:
(1)
Natural or man-made channels or swales must be able to convey the
post-development runoff associated with a ten-year return period event
within their banks at velocities consistent with protection of the
channels from erosion. Acceptable velocities shall be based upon criteria
included in the PADEP Erosion and Sediment Pollution Control Program
Manual.
(2)
Natural or man-made channels or swales must be able to convey the
post-development twenty-five-year return period runoff without creating
any hazard to persons or property.
(3)
Culverts, bridges, storm sewers or any other facilities which must
pass or convey flows from the tributary area must be designed in accordance
with PADEP Chapter 105 regulations (if applicable) and, at a minimum,
pass the post-development twenty-five-year return period runoff.
(4)
It must be demonstrated that the downstream conveyance channel, other
stormwater facilities, roadways or overland areas must be capable
of safely conveying the one-hundred-year design storm without causing
additional damage to buildings or other infrastructure.
B.
Where the downstream conveyance channel or other facility is located
within a special flood hazard area (as documented on the Flood Insurance
Rate Map), it must be demonstrated that the limits of said flood hazard
area are not increased by the proposed activity.