If compliance with any of the requirements of this Part 7 would
result in an exceptional hardship to a prospective builder, developer
or landowner, the Township may, upon request and with good cause shown,
grant relief from the strict application of the requirements.
Requests for grant of variance relief shall be considered in accordance with the procedures set forth in Article XV and the following:
A.Â
No variance shall be granted and no application for variance as to
same shall be accepted:
(1)Â
For any construction, development, use or activity within any floodway
area that would cause any increase in the base flood elevation (BFE);
(2)Â
For any construction, development, use or activity within any AE
Area Without Floodway that would, together with all other existing
and anticipated development, increase the BFE one foot or more at
any point; or
[Amended 5-23-2017 by Ord. No. 2017-10]
(3)Â
From the general requirement that all structures must be designed
and constructed so as to have the capability of resisting the one-percent-annual-chance
flood event.
[Amended 5-23-2017 by Ord. No. 2017-10]
C.Â
If granted, a variance shall involve only the least modification
necessary to provide relief that is warranted in the circumstances.
D.Â
E.Â
If a variance is granted, such reasonable conditions and safeguards
as are considered to be necessary to protect the public health, safety
and welfare and to achieve the objectives of this Part 7 may be attached
to the grant of relief.
F.Â
Forms used by the Township for variance requests shall state that
the grant of the variance may result in increased premium rates for
flood insurance and that such variance may increase the risks to life