Exciting enhancements are coming soon to eCode360! Learn more 🡪
City of Oak Grove, MO
Jackson County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
[Ord. No. 1042 §3-1, 2-20-1992]
A. 
Applicable standards shall be the latest revisions of the following:
1. 
American Water Works Association (AWWA).
a. 
C600 — installation of ductile-iron water mains and appurtenances.
b. 
C6S1 — disinfecting water mains.
2. 
American Association of State Highway and Transportation Officials (AASHTO).
a. 
T99 — the moisture-density relations of soils using a 5.5-pound (2.5 kg) rammer and a 12-inch (305 mm) drop.
3. 
Kansas City Metropolitan Chapter of the American Public Works Association (APWA).
a. 
Section 2900 — Water line construction and material specification as modified by the City's Technical Specifications and Design Criteria for Utility and Street Construction.
[Ord. No. 1915, 7-16-2018]
[Ord. No. 1042 §3-2, 2-20-1992; Ord. No. 1543 §1, 11-6-2006]
A. 
All installations shall be made in accordance with AWWA C600, APWA Section 2900 as modified by the City's Technical Specifications and Design Criteria for Utility and Street Construction, and with any special applicable supplementary instructions issued by the manufacturers of the equipment being installed. Pertinent parts of AWWA Standards C600 and APWA Section 2900 as modified by the City's Technical Specifications and Design Criteria for Utility and Street Construction shall also be applicable along with manufacturer's instructions for installation of other pipe material specified by the department.
[Ord. No. 1915, 7-16-2018]
B. 
All fittings six (6) inch size or larger shall be installed with suitable concrete thrust blocks poured in place with the concrete deposited against firm, undisturbed earth. All hydrants shall be installed with suitable concrete thrust block or restrained joint connections.
C. 
Mains shall be laid on a loop or grid system with cross mains spaced not more than one thousand (1,000) feet apart and with no dead-end lengths exceeding three hundred (300) feet. Not more than one (1) fire hydrant shall be located on any eight (8) inch dead-end main.
D. 
The horizontal distance between paralleling water mains and existing or projected sewers shall not be less than ten (10) feet, except where the water main is located at a higher elevation (one (1) foot minimum from top of sewer to bottom of water main) than the top of the sewer, in which case a minimum horizontal distance of six (6) feet will be permissible.
E. 
All mains shall be laid with a minimum cover of forty-two (42) inches from top of pipe to finished ground surface grade, except that at obstructions which cannot be relocated or modified, the cover may be reduced as necessary for short lengths (ten (10) to twenty (20) feet) to pass over said obstruction using three (3) flexible joints in the offset within a length of approximately eight (8) feet, but in no case shall depth of cover be less than thirty (30) inches. Approved bedding material shall be used wherever cover is less than forty-two (42) inches and shall completely encase pipe. No tees, valves or house service corporation cocks shall be installed in mains with less than forty-two (42) inches of cover.
F. 
Where depth of cover would be less than thirty (30) inches over top of pipe at obstruction, the water main shall pass under the obstruction clearing the obstruction at least one (1) foot and completely encased up to bottom of obstruction in concrete with not less than six (6) inches of concrete on bottom and sides.
G. 
Limiting Trench Width. Trenches shall be excavated to a width which will provide adequate working space and pipe clearances for proper pipe installation, jointing and embedment. However, the limiting trench widths below an elevation six (6) inches (fifteen (15) cm) above the top of the installed pipe shall be as follows:
Ductile - Iron Pipe
Pipe Size
Minimum Trench Width in Earth
Maximum Trench Width in Earth
Minimum Clearance in Rock
4" (100 mm)
18" (45 cm)
30" (75 cm)
6" (15 cm)
6" (150 mm)
24" (60 cm)
30" (75 cm)
6" (15 cm)
8" (200 mm)
26" (65 cm)
32" (80 cm)
6" (15 cm)
10" (250 mm)
28" (70 cm)
34" (85 cm)
6" (15 cm)
12" (300 mm)
28" (70 cm)
34" (85 cm)
6" (15 cm)
Where necessary to reduce earth load on trench banks to prevent sliding and caving, banks may be cut back on slopes which shall not extend lower than one (1) foot (thirty (30) cm) above the top of the pipe.
H. 
Pipe installed in earth, rock or rock bottom trenches shall be excavated to a grade six (6) inches below bottom of pipe in rock and four (4) inches below bottom of pipe in earth and bedded with approved bedding material, graded to provide a uniform support of each length of pipe with material depression provided at joints. Protective earth backfill or bedding material shall continue to twelve (12) inches above top of pipe.
I. 
Bedding material shall be crushed stone or gravel with at least ninety-five percent (95%) passing one-half (½) inch sieve and at least ninety-five percent (95%) retained on a No. 4 sieve. It shall be sound material with not more than fifteen percent (15%) loss after five (5) cycles when tested with sodium sulfate as described in AASHTO T104.
J. 
All material used for backfilling of trenches shall be free of excessive amounts of deleterious materials such as all organic matter, frozen clods and sticky masses of clay and gumbo which are difficult to properly compact. Any rock materials used for backfill shall be no larger than four (4) inches in greatest dimension and shall not be placed within twelve (12) inches of the installed pipe in any direction, including under, around and on top of the pipe. The pipe shall be embedded in a good quality earth or approved bedding material.
1. 
Backfill shall be placed in six (6) inch layers from the bottom of the trench to a point at least twelve (12) inches above the top of the pipe. Above this point, backfill shall be deposited in layers of a thickness which will permit compaction to a density as specified hereinafter.
2. 
Wherever pipe is installed in open fields or areas which carry no vehicular traffic, the remaining trench shall be filled with backfill compacted to prevent significant future settlement and slightly humped to provide for future settlement. The top portion of the backfill areas which are to be seeded or resodded shall be composed of topsoil at least six (6) inches in depth.
3. 
The layers of material shall be compacted to a density of at least ninety-five percent (95%) of the maximum density at optimum moisture content as determined by the AASHO T99 under all pavements, shoulders and areas for future pavements. Pavement shall not be restored over trenches until the backfill material has been tested and determined as satisfactory according to the tests.
4. 
Back slopes, berms, median strips and yards shall be compacted to a density of at least ninety percent (90%) of the maximum density at optimum moisture conditions.
K. 
All mains, branches and dead ends shall be equipped with blowoffs and/or hydrants of adequate size and number to develop a velocity in the main of at least two and one-half (2½) feet per second. Branches of five (5) feet in length or less from tee or cross to valve, or blind flange or plug need not be equipped with a blowoff provided a tablet of chlorine releasing compound is installed and fixed in place in the branch during construction. All lines shall be thoroughly flushed through the blowoffs and/or hydrants provided immediately prior to testing for final acceptance by the department. Water used will be provided by the department at no charge to the developer or contractor installing the main.
[Ord. No. 1042 §3-3, 2-20-1992]
A. 
Corporation cocks shall be provided for disinfection by the installing contractor at locations designated by the department. The department will monitor the chlorination of the lines and test their cleanliness before permitting connections for service. The disinfection will be done by the contractor according to APWA Section 2902.9. The department will take samples for bacteriological testing after chlorination and flushing, prior to the water line being placed in service.
1. 
After installation, the entire main shall be flushed and disinfected by chlorination. Flushing shall be carried out until a turbidity-free water is obtained from all points along the main.
2. 
Chlorination by the contractor shall conform to AWWA C601 and be performed using a one percent (1%) chlorine solution prepared from granular calcium hypochlorite (one (1) pound (0.45 kg) of HTH per eight (8) gallons (30.3 litre) of water). Water entering the new main shall receive a dose of the chlorine solution fed at a constant rate such that the water will have not less than twenty-five (25) mg/l free chlorine.
Chlorine Required to Produce 25 mg/l Concentration
in 100 Feet (30.5 m) of Pipe
Pipe Diameter
One Percent (1%) Chlorine Solution
In
mm
Gallon
Litres
4
100
0.16
0.61
6
150
0.36
1.36
8
200
0.65
2.46
10
250
1.02
3.86
12
300
1.44
5.45
3. 
The chlorinated water shall be retained in the main for at least twenty-four (24) hours, during which time all valves and hydrants in the section treated shall be operated in order to disinfect the appurtenances.
4. 
At the end of the twenty-four (24) hour period, the treated water in all portions of the main shall have a residual of not less than ten (10) mg/l free chlorine.
5. 
Mains shall be flushed prior to placing in service. The flushing water shall be disposed of without damage to public or private property.
6. 
The contractor shall repeat disinfection procedure should initial treatment fail to yield satisfactory results.
B. 
Not more than four thousand (4,000) feet of main shall be installed without testing and disinfection. Contractor shall not proceed with construction until preceding section has been accepted by the department.
[Ord. No. 1042 §3-4, 2-20-1992]
Water mains shall be tested by the procedures as outlined in APWA Section 2902.9.
[Ord. No. 1042 §3-5, 2-20-1992]
Water mains not meeting requirements of these standards shall be replaced or repaired in a manner approved by the department. Defective materials shall be completely removed and replaced with new materials.
[Ord. No. 1042 §3-6, 2-20-1992]
Blasting, where required, shall be done with care in accordance with all applicable Federal, State and local laws, ordinances and regulations and shall not be done within a distance of twenty-five (25) feet from previously laid pipeline or a previously installed structure if, in the opinion of the department, the safety or soundness of existing facilities are in any manner endangered.
[Ord. No. 1042 §3-7, 2-20-1992]
During construction operations, care should be exercised to protect, brace, support and maintain all underground pipes, conduits, drains, and other underground structures uncovered or otherwise affected by the construction work being performed. All pavement, surfacing, driveways, curbs, walks, buildings, utility poles, guy wires and other surface structures, together with all sod and shrubs in yards and parkings crossed by or adjacent to the main under construction, shall be maintained and if removed or otherwise damaged, shall be replaced or restored to the original condition thereof. All replacements of such underground and surface structures or parts thereof shall be made with new materials. All damage resulting from construction operations to streets, roads, highways, shoulders, ditches, embankments, culverts, bridges or other public or private property or facility, regardless of location or character, which may be caused by construction and/or by moving, hauling or otherwise transporting equipment, materials or men to or from the work or any part of site thereof shall be the responsibility of the developer, his/her contractor or subcontractor. Satisfactory arrangements shall be made without delay with the owner or owners of, or the agency or authority having jurisdiction over, the damaged property, surface, structure or facility concerning its repair or replacement and payment of cost incurred in connection with said damage.
[Ord. No. 1042 §3-8, 2-20-1992]
A. 
Maintenance Of Traffic. Construction operations shall be scheduled so as to interfere as little as possible with public travel, whether vehicular or pedestrian. Whenever it is necessary to cross or interfere with roads, driveways and walks, whether public or private, suitable and safe bridges, detours or other temporary expedients for the accommodation of public and private travel shall be provided and maintained. Reasonable notice shall be given to owners of private drives before interfering with them.
B. 
Barricades And Lights. All streets, roads, highways and other public thoroughfares which are closed to traffic, under the authority of a proper permit, shall be protected by means of effective barricades on which shall be placed acceptable warning signs; such barricades being located at the nearest intersecting public highway or street on each side of the blocked section of such public thoroughfare.
1. 
All open trenches and other excavations shall be provided with suitable barriers, signs and lights to the extent that adequate protection is provided to the public against accident by reason of such open construction. Obstructions, such as material piles and equipment, shall be provided with similar warning signs and lights.
2. 
All barricades and obstructions shall be illuminated by means of acceptable warning lights at night, and all lights used for this purpose shall be kept burning from sunset to sunrise. Materials stored upon or alongside public streets, roads and highways shall be so placed, and the work at all times shall be so conducted, as to cause the minimum obstruction and inconvenience to the traveling public.
3. 
All barricades, signs, warning lights and other protective devices shall be installed and maintained in conformity with applicable statutory requirements and, where within public thoroughfare rights-of-way, as required by the authority having jurisdiction thereover.
C. 
Operations Along Streets And Highways. No equipment, pipeline or excavated materials shall be stored on the pavement, or on shoulders of uncurbed roads, or in ditches or at other locations obstructing traffic or drainage.
1. 
Construction operations shall be confined to no more than one thousand (1,000) feet under construction with a maximum open trench of three hundred (300) feet. "Under construction" shall include all operations between start of excavation of the trench to final tamping of backfill and/or restoration of pavement to public use. Traffic shall not be obstructed in more than one (1) lane during construction operations. The length of one (1) lane traffic shall be limited to three hundred (300) feet. Two (2) flagmen shall be provided to control traffic. Advance warning signs shall be provided. All obstructions shall be removed and the pavement cleaned at all road crossings at the end of each day's operation.
2. 
All pipe strung along the right-of-way shall be blocked to prevent movement.
[Ord. No. 1042 §3-9, 2-20-1992]
A. 
The attached City standard detail drawings shall be utilized in the design, the furnishing of materials and the construction of water mains in Oak Grove, Missouri:
1. 
Pipe bedding.
2. 
Concrete pavement removal and replacement.
3. 
Asphalt pavement removal and replacement.
4. 
Fire hydrant and isolation valve.
5. 
Pipe shaft type valve box.
6. 
Horizontal thrust blocks.
7. 
Thrust block sizes.
8. 
Typical main, valve and hydrant locations.