A.
Construction drawings and engineering specifications shall be submitted
following stormwater management plan approval but prior to the issuance
of any construction or building permits.
B.
Construction drawings and engineering specifications shall be submitted
to the Township Clerk in accordance with reasonable information requirements
and calculations specified by the Township Engineer.
A.
Engineering drawings and specifications shall be reviewed and approved
by the Township Engineer.
B.
A building permit, construction permit or certificate of occupancy
shall not be issued unless the detailed engineering drawings and specifications
meet the standards of this chapter, additional requirements of the
Township Engineer, and any applicable requirements of other government
agencies.
The peak rate of stormwater discharge from upstream and off-site
locations for both the ten- and one-hundred-year-frequency storm event
shall be included in detailed engineering drawings and specifications.
Stormwater runoff conveyed by watercourses and conveyed via overland
flow shall be determined.
Engineering design standards approved by the Township shall
be the basis for the Township Engineer's review of engineering
drawings and specifications.