A. 
Before approving any land development plan for recording, the Borough Council must be assured by means of a proper development agreement and performance guarantee that the improvements required by this chapter and the improvements appearing on the plan will be installed in strict accordance with the standards and specifications of this chapter, unless:
(1) 
An applicant chooses to install all required improvements prior to construction of any building; in place of using performance guarantees, in which case, the Borough shall, as deemed necessary, require the applicant to have adequate insurance, hold harmless agreements, an escrow account to cover the costs of inspections and a professional estimate of the costs of the improvements (to be used to establish the amount of the inspections escrow).
B. 
Purpose of security. The security required by this article shall stand as security for compliance with all ordinances, other laws, covenants, stipulations, conditions and rules applicable to the land development for which it is filed.
C. 
No construction of buildings or paving or sales of any individual lot or condominium unit within a land development shall take place unless: (1) there is on file, with the Borough, current duly executed and approved security, or (2) all rough grading is complete and all required public improvements, utilities, streets, drainage facilities, sewers and street lights have been completed and accepted by Borough Council.
A. 
In all cases, the land applicant shall be responsible for the installation of all improvements required by this chapter.
B. 
The Borough Engineer or other designee shall make such inspections of the required improvements at such intervals as may be reasonably necessary to assure compliance with this chapter. The reasonable costs of such inspection shall be borne by the land applicant, making use of an escrow account or other arrangement agreed to by the Borough.
A. 
Development agreement required.
(1) 
All applicants proposing any land development which provides for the installation of improvements required by this chapter or any improvements or amenities which appear on the final plan shall be required to enter into a legally binding development agreement with Borough Council prior to recording of the final plan (or at a date agreed to by Council), unless the applicant agrees to meet § 180-29 concerning the construction of all improvements prior to the construction, of any buildings.
(2) 
The development agreement shall guarantee the installation of said improvements in strict accordance with all Borough requirements.
(3) 
The final plan shall not be approved for recording prior to the execution of this agreement and the delivery of the performance guarantee.
B. 
Terms of development agreement. The development agreement shall be in a form acceptable to the Borough Solicitor. The Borough Council may require that a development agreement include any of the following items, where applicable, and such additional items as are necessary to carry out this chapter:
(1) 
The construction depicted on the approved plans, listed in itemized format, including all approved streets, drainage facilities, utility lines and other improvements.
(2) 
A work schedule setting forth the beginning and ending dates of such work tied to the construction of the development and provisions to allow proper inspection by the Borough Engineer.
(3) 
The provision of a performance guarantee for completion of required improvements in compliance with § 180-45, including a detailed breakdown of the estimated costs of the Improvements, including the total amount of the performance guarantee.
(4) 
Provisions concerning the applicant's responsibilities for damage to other property, including maintenance by the applicant of public liability insurance in the minimum amounts required by Borough Council for the duration of improvements construction, with a hold harmless clause to protect the Borough from liability related to such work. A copy or other evidence of such liability coverage shall be provided to the Borough prior to such work.
(5) 
Provisions concerning measures to prevent erosion, sedimentation and water damage to the subject and adjacent properties.
(6) 
Provisions for the dedication of streets, water and sewer lines and any other easements or improvements approved to be dedicated.
(7) 
Provisions for the applicant to reimburse the Borough for all reasonable engineering costs directly related to the review, construction and inspection of the proposed development and to the review and preparation of the development agreement.
(8) 
Provisions concerning any violations of the development agreement.
(9) 
Any other lawful terms which the Borough Council may require to carry out the provisions of this chapter.
(10) 
Signatures. The development agreement shall be signed by all responsible landowners and/or applicants.
C. 
Ownership of land and guarantee.
(1) 
A certificate of ownership shall be executed in the exact name in which title is held.
(2) 
Change in ownership or applicant. Any conveyance of all or a substantial portion of the unimproved development or public improvements or streets of any land development or change in applicants, whether voluntary or by action of law or otherwise, shall require the prior approval of the Borough. In giving or denying said approval, the Borough shall require that such new landowner and/or applicant fully assume all applicable responsibilities under the development agreement and post all the appropriate security agreements.
D. 
Utility agreements. If a development will connect into a public water or public sanitary sewage system, the applicable authority, agency or company may also require separate development agreements.
The performance guarantee for completion of required improvements shall meet the following requirements:
A. 
Security.
(1) 
The guarantee shall be secured by the credit of any of the following:
(a) 
An irrevocable and unconditional letter of credit of a federal or state-chartered lending institution.
(b) 
A restrictive or escrow account in a federal or state-chartered lending institution.
(c) 
Such other financial security approved by the Borough (which approval shall not be unreasonably withheld), but not including a second or third mortgage on the unimproved lands.
(2) 
Such approved security shall provide for, and secure to the public, the completion of any improvements which may be required within one year of the date fixed in the development schedule (§ 180-46F) for the completion of such improvements.
(3) 
Such financial security shall be posted with a federally insured or state-chartered lending institution chosen by the party posting the financial security, or such other approved entity, provided such institution or entity is authorized to conduct such business within the state.
(a) 
The Borough may require that evidence be provided that such institution or entity has sufficiently adequate and secure assets to cover the security.
(b) 
The Borough shall be the authorized signatory on any account in which the escrow funds are held.
B. 
Amount.
(1) 
The amount of financial security to be posted for the completion of the required improvements shall be equal to 110% of the cost of completion estimated as of 90 days following the date scheduled for completion by the applicant in the official development schedule, and within the process for increases to cover inflation as permitted by the Pennsylvania Municipalities Planning Code.
(2) 
The cost of the improvements shall be established by an estimate prepared by a Design Professional, which shall be reviewed by the Borough Engineer, within the arbitration process permitted by the Pennsylvania Municipalities Planning Code.
(3) 
If the party posting the financial security requires more than one year from the date of posting of the financial security to complete the required improvements, the amount of financial security may be increased by a maximum of an additional 10% or each one-year period beyond the first anniversary date from posting of financial security or to an amount not exceeding 110% of the cost of completing the required improvements as reestablished on or about the expiration of the preceding one-year period by using the above procedure.
(4) 
Inspection fees. The amount of financial security shall also include an additional 5% of the estimated cost of completion of the work to guarantee payment of inspection fees and related engineering costs.
C. 
Multi-year or multi-stage development. In the case where development is projected over a period of years, the Borough may authorize submission of final plans by phases/stage of development subject to such requirements or improvement guarantees concerning future improvements as it finds necessary for the proper functioning of each phase and for the eventual development as a whole.
A. 
In general. As the work of installing the required improvements proceeds, the party posting the financial security may request the Borough to release or authorize the release, from time to time, portions of the financial security necessary for payment to the contractors performing the work.
B. 
Notice by applicant of work on improvements. The applicant or his/her representative should provide a minimum of three days' notice to the Borough Engineer prior to beginning each major facet of construction, in order to allow the scheduling of inspections.
C. 
Engineer's report.
(1) 
Within 30 days of the receipt of such request, the Borough Engineer shall submit a written report certifying which improvements have been completed in accordance with the approved plan to the Borough and mail a copy of such, by certified or registered mail, to the applicant or his/her representative at his/her last known address.
(2) 
This report shall be based on the inspections made according to the approved inspection schedule included in the development agreement and shall recommend approval or rejection of the improvements, either in whole or in part.
(3) 
If the Borough Engineer finds any or all of the improvements to be not as required, he/she shall include a statement of the reasons for recommending their rejection in the report.
D. 
Decision by Borough.
(1) 
At its first regularly scheduled meeting after receiving the Engineer's report [but not later than 45 days, of the receipt of the request] the Borough shall review the Borough Engineer's report and shall authorize release of an amount as estimated by the Borough Engineer fairly representing the value of the improvements completed.
(2) 
The Borough shall be deemed to have approved the release of funds as requested if the Borough fails to act within 45 days of receipt of the applicant's request.
(3) 
Until final release (completion of all improvements), the Borough may require retention of a maximum of 10% of the cost of each completed improvement.
(4) 
The Borough shall notify the applicant in writing by certified or registered mail of the decision.
E. 
Completion of unapproved improvements. The applicant shall proceed to complete any improvements not approved by the Borough and, upon completion, request approval in conformance with the procedures.
F. 
Final release.
(1) 
When the applicant has completed all of the necessary and appropriate improvements, the applicant shall request final release in conformance with the procedures specified in this section. See time limitations and procedures in § 510 of the Municipalities Planning Code, 53 P.S. § 10510.
(2) 
Such final release shall include all moneys retained.
G. 
Appeal. Nothing herein, however, shall be construed to limit the applicant's right to contest or question by legal proceedings or otherwise any determination of the Borough or the Borough Engineer.
A. 
Enforcement of security.
(1) 
In the event that any improvements which may be required have not been installed as provided in this chapter or in accord with the approved final plan, or in the event of the bankruptcy of the owner or applicant, the Borough is hereby granted the power to elect to enforce any security posted under this chapter by appropriate legal and equitable remedies.
(a) 
This may include taking all actions necessary to obtain moneys under said security, including, but not limited to, seizure of undeveloped lots, seizure of escrow funds, revocation of zoning permits and prosecution under this chapter.
(2) 
Rate of construction. Failure of an applicant to construct streets and other public improvements reasonably at the same time or prior to the construction of the buildings served by those streets or public improvements, and at the same rate in time at which buildings are completed, shall be a violation of this chapter and a cause for default of the security.
B. 
Completion by Borough. If the proceeds of such security are insufficient to pay the cost of installing or making repairs or corrections to all the improvements covered by said security, the Borough may, at its option, install part of such improvements in all or part of the subdivision or land development and may institute appropriate legal or equitable action to recover the moneys necessary to complete the remainder of the improvements.
C. 
Proceeds for installation of improvements. The proceeds from use of the security and/or from any legal or equitable action brought against the applicant shall be used solely for the installation of the improvements covered by such security.
A. 
Maintenance guarantee required. All applicants proposing any land development which provides for the dedication of improvements required by this chapter shall be required to provide a legally binding maintenance guarantee to the Borough prior to acceptance of dedication of the improvements by the Borough. In most cases, this guarantee will be part of the security agreement.
B. 
Terms of maintenance guarantee. The maintenance guarantee shall be acceptable in legal form to the Borough Solicitor and in content to the Borough Council, and shall include all of the following:
(1) 
That the applicant make any repair or reconstruction of any improvement stipulated in the maintenance agreement which is specified by the Borough if needed because of faulty construction, workmanship, or materials, prior to acceptance of such improvement by the Borough.
(2) 
That the applicant maintain at his/her own cost all improvements stipulated in the maintenance agreement, up to a maximum period of 18 months from the date of completion, except for any special purpose escrow or maintenance agreements required by the Borough.
(3) 
That the applicant post financial security to secure structural integrity of said improvements as well as the functioning of said improvements in accordance with the design and specifications as depicted on the final plan, for a maximum term of 18 months from the date of completion.
(4) 
That the applicant plow snow and maintain all streets until such time as the Borough may accept such streets.
C. 
Type of security. The maintenance guarantee shall be secured by the same form of security as is permitted for the improvements guarantees.
D. 
Terms. Such maintenance guarantee shall be in the form approved by the Borough Solicitor and Borough Council, payable to the Borough, to guarantee the maintenance and repair of the streets and other public improvements in the land development for 18 months from the date of completion. The applicant shall prove to the satisfaction of the Borough that there will be an acceptable system for the long-term maintenance of any stormwater detention basins.
E. 
Amount. The amount of the maintenance guarantee shall be determined by the applicants engineer, conditioned upon acceptance by the Borough, but shall not exceed 15% of the actual cost of installation of such improvements.
F. 
Release. After a maximum of 18 months from the date of completion of said improvements, the Borough shall release the maintenance guarantee to the applicant (or party that posted the guarantee) if all improvements are in satisfactory condition, as determined by the Borough.