Exciting enhancements are coming soon to eCode360! Learn more 🡪
Town of Cohasset, MA
Norfolk County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
[Added 3-29-2008 by Art. 14]
[Amended 4-30-2011 by Art. 21]
It is the express purpose of this bylaw to accommodate large distributed generation, wind energy conversion facilities, hereinafter referred to as a wind turbine(s), in appropriate locations, while minimizing adverse safety and environmental impacts of the facilities. The bylaw enables the review of wind turbines by the Town's Planning Board in keeping with the Town's existing bylaws. This bylaw is intended to be used in conjunction with other regulations adopted by the Town, including historic district regulations, site plan review and other local bylaws designed to encourage appropriate land use, environmental protection, and provision of adequate infrastructure development in Cohasset.
As used in this article, the following terms shall have the meanings indicated:
NACELLE
The frame and housing at the top of the tower that encloses the gearbox and generators and protects them from the weather.
RESIDENCE
A shelter (as a house) in which people live (can include commercial apartments/living facilities).
[Amended 4-30-2011 by Art. 21]
ROTOR
The blades and hub of the wind turbine(s) that rotate during turbine operation.
SETBACK
The base of the tower to the nearest lot line.
SIZE
Only wind turbines greater than 500 kilowatts are covered by this bylaw.
SPECIAL PERMIT GRANTING AUTHORITY (SPGA)
The Planning Board is the special permit granting authority for wind energy conversion facilities.
[Amended 4-30-2018 ATM by Art. 19]
TOTAL HEIGHT
The height of a turbine(s) is measured from the pre-construction grade to the highest point reached by the blades.
[Amended 4-30-2011 by Art. 21]
TOWER HEIGHT
The height of the tower is measured from the pre-construction grade to the highest point reached by the nacelle.
[Amended 4-30-2011 by Art. 21]
WIND ENERGY CONVERSION FACILITY
All equipment, machinery and structures utilized in connection with the conversion of wind to electricity. This includes, but is not limited to, all transmission, storage, collection and supply equipment, substations, transformers, site access, service roads and machinery associated with the use. A wind energy conversion facility may consist of one or more wind turbines.
WIND MONITORING OR METEOROLOGICAL ("TEST" or "MET") TOWERS
Tower used for supporting anemometer, wind vane and other equipment to assess the wind resource at a predetermined height above the ground.
WIND TURBINE
A device that converts kinetic energy of the wind into rotational energy to turn an electrical generator shaft. A wind turbine typically consists of a rotor, nacelle and supporting tower.
WIND TURBINE FLICKERING
The blinking effect while the rotor is in motion.
[Amended 4-30-2011 by Art. 21]
A. 
Use regulations.
(1) 
Wind turbine. The construction of any wind turbine under this bylaw shall be permitted in all zoning districts, subject to issuance of a special permit and provided the proposed use complies with all dimensional and special permit requirements set forth in §§ 300-19.3 and 300-19.4 of this bylaw.
(2) 
Wind monitoring or meteorological towers. Temporary erection of wind monitoring or meteorological towers shall be permitted in all zoning districts subject to the issuance of a building permit for a temporary structure for not more than 18 months.
B. 
Site control. The applicant shall submit with the application documentation of the applicant's legal right to install and use the proposed facility at the subject property. Documentation should also include proof of control over the setback areas.
C. 
Dimensional requirements. All wind turbines shall comply with the requirements set forth in this Subsection C.
(1) 
Height. Wind turbines shall have a maximum tower height of 260 feet (80 meters), as measured from the pre-construction grade to the highest point reached by the nacelle. The SPGA may allow this tower height to be exceeded as part of the special permit process if the project proponent can demonstrate that the additional tower height is essential and that the additional benefits of the higher tower outweigh any adverse impacts, but in no case shall tower height exceed 350 feet (100 meters) to the highest point reached by the nacelle. Monopole towers are the required method of support.
[Amended 4-30-2011 by Art. 21]
(2) 
Setback.
(a) 
Each wind energy conversion facility and its associated equipment shall comply with the building setback provisions of the zoning district in which the facility is located.
(b) 
In addition, a wind turbine may not be sited within:
[1] 
A distance equal to the total height of the wind turbine from buildings, critical infrastructure, or private or public ways that are not part of the wind energy facility;
[2] 
Three times the total height of the turbine from the nearest existing residential structure; or
[3] 
One and five-tenths times the total height of the turbine from the nearest property line not delineating properties each owned in whole by the applicant.
[Amended 4-30-2011 by Art. 21]
The SPGA may grant a special permit only if it finds that the proposal complies with the provisions of this bylaw and is consistent with the applicable criteria for granting special permits.
A. 
General. Proposed wind turbine(s) shall comply with all applicable local, state and federal requirements, including but not limited to all applicable electrical, construction, noise, safety, environmental and communications requirements.
(1) 
Color. Wind turbine(s) shall be painted a non-reflective color.
(2) 
Lighting and signage. Wind turbine(s) shall be lighted only if required by the Federal Aviation Administration (FAA). The proponent shall provide a copy of the FAA's determination to establish the required marking and/or lights for the structure.
(a) 
Lighting of equipment structures and any other facilities on site (except lighting) required by the FAA shall be shielded from abutting properties.
(b) 
Signs on the facility shall be limited to:
[1] 
Those needed to identify the property and the owner and warn of any danger; and
[2] 
Educational signs providing information on the technology and renewable energy usage.
(c) 
All signs shall comply with the requirements of the Town's sign regulations unless relief is granted by the SPGA.
[Amended 11-17-2008 by Art. 10]
B. 
Performance standards.
(1) 
Land clearing/open space/rare species. Wind turbines shall be designed to minimize land clearing and fragmentation of open space areas and shall avoid permanently protected open space when feasible. Wind turbines should be sited to make use of previously developed areas wherever possible. Wind turbine facilities shall also be located in a manner that does not have significant negative impacts on rare species in the vicinity (particularly avian species, bats, etc.) as may be applicable law.
(2) 
Stormwater. Stormwater runoff and erosion control shall be managed in a manner consistent with all applicable state and local law.
(3) 
Noise.
(a) 
The wind turbine and associated equipment shall conform to Massachusetts noise regulations (310 CMR 7.10). An analysis prepared by a qualified engineer shall be presented to demonstrate compliance with these noise standards and shall be consistent with Massachusetts Department of Environmental Protection guidance for noise measurement. Additionally, a noise source will be considered in violation of this bylaw if the source:
[1] 
Increases the broadband sound level by more than 10 dB(A) above ambient at the property line; (or)
[2] 
Increases the broadband sound level by more than eight dB(A) at the nearest residence; (or)
[3] 
Produces a "pure tone" condition, when any octave band center frequency sound-pressure level exceeds the two adjacent center frequency sound-pressure levels by three decibels or more at the property line or at the nearest permitted residence; (or)
[4] 
Adds to the noise generated by existing turbines within 1/2 mile, such that the cumulative total of sound level calculations increases the broadband sound level by more than 10 dB(A) above ambient at the property line or increases the broadband sound level by more than eight dB(A) at the nearest residence.
(b) 
"Ambient" is defined as:
[1] 
The background A-weighted sound level that is exceeded 90% of the time; (and)
[2] 
Measured during the hours 7:00 p.m. to 7:00 a.m.; (and)
[3] 
No wind turbines within 1/2 mile of the proposed project in operation.
(c) 
A noise analysis shall be performed within 90 days of initial operation and a certified test report, prepared by an engineer board certified by the Institute of Noise Control Engineering (INCE), shall be submitted after initial operation of the facility to demonstrate compliance with these noise regulations and with the noise level analysis submitted by the applicant. Additional tests shall be performed from time to time upon the request of the SPGA and certified test reports submitted. If any analyses indicate noise levels in excess of those permitted by regulations, remedial measures shall be undertaken to bring noise levels into compliance. Test methods shall be consistent with Massachusetts Department of Environmental Protection guidelines for noise measurement.
[Amended 4-30-2011 by Art. 21]
(4) 
Shadowing/flicker. A shadow flicker analysis shall be performed by a qualified engineer using industry recognized software to determine the worst-case shadow flicker that could be experienced by all private structures occupied during daylight hours within 1/2 mile of the base of each turbine. The maximum allowable worst-case daily shadow flicker for each applicable structure shall not exceed 30 minutes for each day.
[Amended 4-30-2011 by Art. 21]
Wind turbines may be used to locate telecommunications antennas, subject to applicable law governing such uses and structures, and subject to the following additional requirements:
A. 
All ground-mounted telecommunications equipment shall be located in either a shelter, within the wind turbine tower or otherwise screened from view year-round (either through effective landscaping or existing natural vegetated buffers);
B. 
Antennas shall be flush-mounted to be in keeping with the design of the wind turbine tower; and
C. 
All cabling associated with the personal wireless facility shall be contained within the tower structure or enclosed within a conduit painted to match the turbine mount.
A. 
After the wind turbine is operational, the applicant shall submit to the SPGA, at annual intervals from the date of issuance of the special permit, a report detailing operating data for the facility (including but not limited to days of operation, energy production in accordance with the special permit conditions).
B. 
The applicant shall maintain the wind energy conversion facility in good condition. Such maintenance shall include, without limitations, painting, structural integrity of the foundation and support structure and security barrier (if applicable), and maintenance of the buffer areas and landscaping if present.
C. 
Notice shall be provided to the SPGA of any change in ownership of the facility.
A. 
Within six months that a wind turbine(s) is scheduled to be discontinued, the applicant will notify the SPGA by certified U.S. mail of the proposed date of abandonment or discontinuance of operations. In the event that an applicant fails to give such notice, the facility shall be considered abandoned or discontinued if the facility is inoperable for 190 days. In the case of a multi-turbine facility, the SPGA shall determine in its decision what proportion of the facility would be inoperable for the facility to be considered abandoned.
B. 
Upon abandonment or discontinuation of use, the owner shall physically remove the wind turbine(s) within 90 days from the date of abandonment or discontinuation of use. This period may be extended at the request of the owner and at the discretion of the SPGA. "Physically remove" shall include, but not be limited to:
[Amended 11-17-2008 by Art. 10]
(1) 
Removal of the wind turbine(s) and tower(s), all machinery, equipment, equipment shelters, security barriers and all appurtenant structures from the subject property.
(2) 
Proper disposal of all solid or hazardous materials and wastes from the site in accordance with local and state solid waste disposal regulations.
(3) 
Restoration of the location of the wind turbine(s) to its natural condition, except that any landscaping, grading or below-grade foundation may remain in the after-condition.
C. 
If an applicant fails to remove a wind turbine in accordance with this section of this bylaw, the Town shall have the authority to enter the subject property and physically remove the facility. The SPGA may in its decision require the applicant provide a form of surety (i.e. post a bond, letter of credit or establish an escrow account or other) at the SPGA's election to cover costs of removal in the event the Town must remove the facility. The amount of such surety shall be equal to 150% of the cost of removal of the facility as determined by a qualified engineer. After 10 and 20 years, the original bond requirement may be adjusted to reflect then-current anticipated decommissioning/deconstruction costs.
[Amended 4-30-2011 by Art. 21]
A special permit issued for any wind turbine(s) facility shall be valid for 25 years unless extended or renewed. At the end of that time period, the wind turbine(s) shall be removed by the applicant.
[Amended 11-17-2008 by Art. 10]
A. 
Special permit granting authority (SPGA). The SPGA for wind energy conversion facilities, also referred to as wind turbine(s) in this bylaw shall be the Planning Board.
[Amended 4-30-2011 by Art. 21; 4-28-2014 ATM by Art. 23]
In granting a special permit under this article, the SPGA may impose conditions and limitations specially designed to safeguard the property, health, safety, and economic value of occupants of the premises and of other land, as well as the Town and its residents.