Exciting enhancements are coming soon to eCode360! Learn more 🡪
Township of Lower Oxford, PA
Chester County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
[Ord. 1-2014, 1/6/2014]
1. 
Applicants proposing regulated activities in the municipality which are not exempt under § 20-106 shall submit a stormwater management site plan (SWM site plan) to the municipality for review and approval in accordance with Parts 3 and 4. SWM site plans approved by the municipality shall be on site throughout the duration of the regulated activity.
2. 
The stormwater management and runoff control criteria and standards in this chapter shall apply to the total proposed regulated activity, even if it is to take place in stages. The measurement of impervious surfaces shall include all of the impervious surfaces in the total proposed regulated activity, even if the development is to take place in stages.
3. 
No regulated activity within the municipality shall commence until:
A. 
The municipality issues approval of an SWM site plan, which demonstrates compliance with the requirements of this chapter; and
B. 
The applicant has received a letter of adequacy or approval for the erosion and sediment control plan review by the municipality and the Conservation District (if required) and has received all other local, state and federal permit approvals required for the project involving the regulated activity.
4. 
Neither submission of an SWM site plan under the provisions herein nor compliance with the provisions of this chapter shall relieve any person from responsibility for damage to any person or property otherwise imposed by law.
5. 
The applicant shall design the site to minimize disturbances to land, site hydrology, and natural resources and to maintain the natural hydrologic regime, drainage patterns and flow conditions. The applicant shall apply the procedures set forth in § 20-304 for the overall site design and for selection, location and design of features and BMPs to be used to comply with the requirements of this chapter.
6. 
To the maximum extent practicable, post-construction stormwater shall be discharged within the drainage area of the same stream or water body receiving the runoff prior to construction of the proposed regulated activity.
7. 
For regulated activities with one acre or more of proposed earth disturbance, existing drainage peak rate discharges up to and including the one-hundred-year storm onto or through adjacent property(ies) or downgradient property(ies), including diffuse drainage discharge, shall not be altered in any manner without written permission from, and, where applicable as determined by the municipality, an easement and agreement with, the affected landowner(s) for conveyance of discharges onto or through their property(ies). Such discharge shall be subject to any applicable discharge criteria specified in this chapter.
A. 
For regulated activities with one acre or less of proposed earth disturbance the applicant shall provide written notification to the affected landowner(s) describing the proposed regulated activity and proposed discharge(s), unless otherwise required by the municipality.
8. 
Areas located outside of the site (i.e., areas outside of the regulated activity) that drain through a proposed site are not subject to water quality and volume control, infiltration, stream channel protection, or peak flow rate control requirements (as presented in §§ 20-305, 20-306, 20-307, and 20-308). Drainage facilities located on the site shall be designed to safely convey flows from outside of the site through the site.
9. 
If site conditions preclude capture of runoff from limited portions of the disturbed area for achieving water quality volume control standards, stream channel protection standards, and the two-year storm event peak runoff rate reduction standards for new development required by this chapter, the applicant shall propose alternate methods to mitigate the bypass of the BMPs, subject to the approval of the Municipal Engineer. In no case shall resulting peak rate be greater than the predevelopment peak rate for the equivalent design storm.
10. 
For all regulated activities, erosion and sediment control BMPs shall be designed, implemented, operated, and maintained during the regulated activities (i.e., during construction) as required to meet the purposes and requirements of this chapter, to meet the erosion and sediment control requirements of the municipality, if applicable, and to meet all requirements under Title 25 of the Pa. Code and the Clean Streams Law.
11. 
For all regulated activities, permanent BMPs and conveyances shall be designed, implemented, operated, and maintained to meet the purposes and requirements of this chapter and to meet all requirements under Title 25 of the Pennsylvania Code, the Clean Streams Law, and the Storm Water Management Act.
12. 
The design of all BMPs and conveyances shall incorporate sound engineering principles and practices in a manner that does not aggravate existing stormwater problems as identified by the municipality. The municipality reserves the right to disapprove any design that would result in construction in an area affected by existing stormwater problem(s) or continuation of an existing stormwater problem(s).
13. 
Existing wetlands, either on the site or on an adjacent property, shall not be used to meet the minimum design requirements for stormwater management or stormwater runoff quality treatment. Stormwater discharges to existing wetlands shall not degrade the quality or hydrologic integrity of the wetland.
14. 
Hotspot Runoff Controls. Specific structural or pollution prevention practices may be required, as determined to be necessary by the Municipal Engineer, to pretreat runoff from hotspots prior to infiltration. Following is a list of examples of hotspots:
A. 
Vehicle salvage yards and recycling facilities;
B. 
Vehicle fueling stations;
C. 
Vehicle service and maintenance facilities;
D. 
Vehicle and equipment cleaning facilities;
E. 
Fleet storage areas (bus, truck, etc.);
F. 
Industrial sites based on Standard Industrial Classification codes;
G. 
Marinas (service and maintenance areas);
H. 
Outdoor liquid container storage;
I. 
Outdoor loading/unloading facilities;
J. 
Public works storage areas;
K. 
Facilities that generate or store hazardous materials;
L. 
Commercial container nursery;
M. 
Contaminated sites/brownfields;
N. 
Other land uses and activities as designated by the municipality.
15. 
Contaminated and Brownfield Sites. Where BMPs may contribute to the migration of contaminants in groundwater, the water quality and runoff volume, stream channel protection, and peak rate control standards shall be met; however, at the Municipal Engineer's discretion, the minimum infiltration requirement may be reduced or eliminated commensurate with the contaminated area and the required water quality and runoff control measures may be increased to mitigate the reduced infiltration requirement for the contaminated area.
16. 
Additional Water Quality Requirements. The municipality may require additional stormwater control measures for stormwater discharges to special management areas, including, but not limited to:
A. 
Water bodies listed as "impaired" by PADEP.
B. 
Any water body or watershed with an approved total maximum daily load (TMDL).
C. 
Areas of known existing flooding problems.
D. 
Critical areas with sensitive resources (e.g., state-designated special-protection waters, cold-water fisheries, carbonate geology or other groundwater recharge areas that may be highly vulnerable to contamination, drainage areas to water supply reservoirs, etc.).
17. 
Applicants shall utilize the Pennsylvania Stormwater Best Management Practices Manual (PA BMP Manual), as amended, or other sources acceptable to the Municipal Engineer, for testing and design standards for BMPs; and where there is a conflict with the provisions of this chapter, the most restrictive applies.
18. 
For areas underlain by karst or carbonate geology that may be susceptible to the formation of sinkholes and other karst features, the location, type, and design of infiltration BMPs shall be based on a site evaluation conducted by a qualified licensed professional and based on the PA BMP Manual or other design guidance acceptable to the Municipal Engineer.
19. 
All regulated activities located within a special flood hazard area designated by the Federal Emergency Management Agency (FEMA) shall comply with applicable municipal ordinances, i.e., Zoning Ordinance [Chapter 27] and/or Floodplain Management Ordinance, and shall be designed to maintain the flood-carrying capacity of the floodway such that the base flood elevations are not increased, either upstream or downstream. The natural conveyance characteristics of the site and the receiving floodplain shall be incorporated into the stormwater management practices proposed for the site.
20. 
Disturbance of existing ground cover during construction of the proposed regulated activity is prohibited within 50 feet of the top-of-bank of all perennial and intermittent waterways, water bodies (lakes, ponds, etc.) and wetlands, except for activities otherwise approved by state or local agencies (e.g. stream restoration projects, road crossings, subsurface utility projects, etc.). At the Municipal Engineer's discretion, and with Conservation District and PADEP approval where necessary, the nondisturbance buffer may be reduced because of setback or other site constraints, but it shall never be less than 10 feet.
21. 
Riparian Corridor Protection.
A. 
In order to protect and improve water quality, a riparian corridor easement shall be created and recorded as part of any subdivision and land development that encompasses a riparian corridor.
B. 
Except as otherwise required by Pa. Code Chapter 102, the riparian corridor easement shall be measured to be the greater of the limit of the one-hundred-year floodplain or 35 feet from the top of streambank (on each side).
C. 
Minimum Management Requirements for Riparian Corridors.
(1) 
Existing native vegetation shall be protected and maintained within the riparian corridor easement.
(2) 
Whenever feasible, invasive vegetation shall be actively removed and the riparian corridor easement shall be planted with native trees, shrubs and other vegetation to create a diverse native plant community appropriate to the intended ecological context of the site.
D. 
The riparian corridor easement shall be incorporated into the deed for the property or lot(s) and shall limit the use of the property located therein. The easement shall allow for continued private ownership and shall count toward the minimum lot area as required by zoning.
E. 
Any permitted use within the riparian corridor easement shall be conducted in a manner that will maintain the extent of the existing one-hundred-year floodplain, improve or maintain the stream stability, and preserve and protect the ecological function of the floodplain.
F. 
The following conditions shall apply when public and/or private recreation trails are permitted within riparian corridors:
(1) 
Trails shall be for nonmotorized use only.
(2) 
Trails shall be designed to have the least impact on native plant species and other sensitive environmental features.
G. 
Septic drainfields and sewage disposal systems shall not be permitted within the riparian corridor easement and shall maintain a minimum distance of 100 feet from the top of streambank.
[Ord. 1-2014, 1/6/2014]
1. 
The following permit or other regulatory requirements may apply to certain regulated activities and shall be met prior to (or as a condition of) final approval by the municipality of the SWM site plan and prior to commencement of any regulated activities, as applicable:
A. 
All regulated activities subject to permit or regulatory requirements by PADEP under regulations at 25 Pa. Code Chapter 102 or erosion and sediment control requirements of the municipality.
B. 
Work within natural drainageways subject to permit by PADEP under 25 Pa. Code Chapter 105.
C. 
Any BMP or conveyance that would be located in or adjacent to surface waters of the commonwealth, including wetlands, subject to permit by PADEP under 25 Pa. Code Chapter 105.
D. 
Any BMP or conveyance that would be located on or discharge to a state highway right-of-way or require access to or from a state highway and be subject to approval by PennDOT.
E. 
Culverts, bridges, storm sewers, or any other facilities which must pass or convey flows from the tributary area and any facility which may constitute a dam subject to permit by PADEP under 25 Pa. Code Chapter 105.
[Ord. 1-2014, 1/6/2014]
1. 
No regulated activity within the municipality shall commence until:
A. 
The municipality receives documentation that the applicant has received:
(1) 
A "letter of adequacy" from the Conservation District or other approval from PADEP in compliance with Title 25, Chapter 102, of the Pennsylvania Code of an erosion and sediment control plan for construction activities, if applicable;
(2) 
A PADEP NPDES construction activities permit as required under 25 Pa. Code Chapter 92a, if applicable;
(3) 
Evidence of any other permit(s) or approvals required for the regulated activities; and
B. 
An erosion and sediment control plan has been approved by the municipality, if required.
2. 
A copy of the erosion and sediment control plan and any required permit(s), as required by PADEP regulations, shall be available on the site at all times.
3. 
Additional erosion and sediment control measures shall be applied where infiltration BMPs are proposed, at a minimum including those required in § 20-306, Subsection 1M.
[Ord. 1-2014, 1/6/2014]
1. 
The applicant shall design the site to minimize the disturbances to land, site hydrology, and natural resources and to maintain the natural hydrologic regime, drainage patterns and flow conditions. For regulated activities with 10,000 or more square feet of proposed earth disturbance OR 2,000 or more square feet of proposed impervious surfaces, the applicant shall demonstrate in its SWM site plan (as required in § 20-402, Subsection 2C) that the design sequence, objectives and techniques described below were applied to the maximum extent practicable in the site design of the regulated activity while complying with all other requirements of this chapter. The site design shall:
A. 
First, identify and delineate all existing natural resources and natural and man-made hydrologic features listed in § 20-402, Subsection 2B(8), that are located within the site, or receive discharge from, or may be impacted by the proposed regulated activity.
B. 
Second, provide a prioritized listing of these resources and features to identify:
(1) 
Those to be incorporated into the site design in a manner that provides protection from any disturbance or impact from the proposed regulated activity;
(2) 
Those to be protected from further disturbance or impact but for which the proposed regulated activity will provide improvement to existing conditions;
(3) 
Those that can be incorporated into and utilized as components of the overall site design in a manner that protects or improves their existing conditions while utilizing their hydrologic function within the limits of their available capacity (e.g., for infiltration, evapotranspiration, or reducing pollutant loads, runoff volume or peak discharge rates, etc.) to reduce the need for or size of constructed BMPs; and
(4) 
Those that may be considered for alteration, disturbance or removal.
C. 
Third, develop the site design to achieve the following:
(1) 
Recognize and incorporate the priorities identified in § 20-304, Subsection 1B, as the basis for the proposed site layout, grading, construction, and permanent ground cover design;
(2) 
Minimize earth disturbance (both surface and subsurface);
(3) 
Maximize protection of or improvement to natural resources and special management areas;
(4) 
Minimize the disturbance of natural site hydrology, in particular natural drainage features and patterns, discharge points and flow characteristics, natural infiltration patterns and characteristics, and natural channel and floodplain conveyance capacity;
(5) 
Incorporate natural hydrologic features and functions identified in § 20-304, Subsection 1B, into the site design to protect and utilize those features and their hydrologic functions to reduce the need for or size of constructed BMPs;
(6) 
Maximize infiltration and the use of natural site infiltration features, patterns and conditions, and evapotranspiration features;
(7) 
Apply selective grading design methods to provide final grading patterns or preserve existing topography in order to evenly distribute runoff and minimize concentrated flows;
(8) 
Minimize the cumulative area to be covered by impervious surfaces and:
(a) 
Minimize the size of individual impervious surfaces;
(b) 
Separate large impervious surfaces into smaller components;
(c) 
Disconnect runoff from one impervious surface to another; and
(d) 
Utilize porous materials in place of impervious wherever practicable;
(9) 
Minimize the volume and peak discharge rates of stormwater generated;
(10) 
Avoid or minimize stormwater runoff pollutant loads and receiving stream channel erosion;
(11) 
Locate infiltration and other BMPs:
(a) 
At or as near to the source of generation as possible; and
(b) 
At depths that are as shallow as possible;
(12) 
Prioritize the selection and design of BMPs as follows:
(a) 
Nonstructural and vegetation BMPs; then
(b) 
Structural (surface and subsurface) BMPs;
(13) 
For flow volumes requiring conveyance from the source of generation to a BMP for management, give preference to open-channel conveyance techniques that provide infiltration and water quality benefits, and landscape-based management in common open space areas, where practicable; and
(14) 
Consider additional guidance for incorporating natural hydrology into the site and BMP designs, methods and techniques that support the objectives of § 20-304, Subsection 1B and C. Appendix B presents additional discussion of natural hydrology site design and sources of information for "conservation design," "low-impact design," and "sustainable design."[1]
[1]
Editor's Note: Appendix B is included as an attachment to this chapter.
D. 
The procedures set forth above shall be utilized to the maximum extent practicable for the overall site design and selection, location and design of features and BMPs to be used to comply with the requirements of §§ 20-305, 20-306, 20-307 and 20-308.
[Ord. 1-2014, 1/6/2014]
1. 
To control post-construction stormwater impacts from regulated activities and meet state water quality requirements, BMPs shall be provided in the site design that replicate predevelopment stormwater infiltration and runoff conditions, such that post-construction stormwater discharges do not degrade the physical, chemical, or biological characteristics of the receiving waters. The applicant shall comply with the following water quality and runoff volume requirements for all regulated activities, including all new development and redevelopment activities:
A. 
The post-construction total runoff volume shall not exceed the predevelopment total runoff volume for all storms equal to or less than the two-year, twenty-four-hour duration precipitation (design storm). The water quality and runoff volume to be managed shall consist of any runoff volume generated by the proposed regulated activity over and above the predevelopment total runoff volume and shall be captured and permanently retained or infiltrated on the site. Permanent retention options may include, but are not limited to, reuse, evaporation, transpiration, and infiltration.
B. 
For modeling purposes, the predevelopment ground cover conditions shall be determined using the corresponding ground cover assumptions presented in § 20-309, Subsection 4, of this chapter.
C. 
The design of the facility outlet shall provide for protection from clogging and unwanted sedimentation.
D. 
BMPs that moderate the temperature of stormwater shall be used to protect the temperature of receiving waters. The applicant shall fulfill the requirements of the PADEP "Thermal Impact Analysis" for the "PAG-02 Stormwater Discharges Associated with Construction Activities, NOI for Coverage under General or Individual Permit" if they cannot meet the volume control requirements.
E. 
Water quality improvement shall be achieved in conjunction with achieving the infiltration requirements of § 20-306. The infiltration volume required under § 20-306 may be included as a component of the water quality volume. If the calculated water quality and runoff volume is greater than the volume infiltrated, then the difference between the two volumes shall be managed for water quality and runoff volume control through other techniques or practices but shall not be discharged from the site.
F. 
Runoff from the disturbed area shall be treated for water quality prior to entering existing waterways or water bodies. If a stormwater management practice does not provide water quality treatment, then water quality BMPs shall be utilized to provide pretreatment prior to the runoff entering the stormwater management practice.
G. 
The municipality may require additional water quality and runoff control measures for stormwater discharging to special management areas such as those listed in § 20-301, Subsection 16.
H. 
When the regulated activity contains or is divided by multiple drainage areas, the water quality and runoff volume shall be separately addressed for each drainage area.
I. 
Weighted averaging of runoff coefficients shall not be used for manual computations or input data for water quality and runoff volume calculations.
J. 
Areas located outside of the site (i.e., areas outside of the regulated activity) may be excluded from the calculation of the water quality and runoff volume requirements.
K. 
Water quality and volume control practices shall be selected and designed to meet the criteria of § 20-304, Subsection 1C, that apply to water quality and volume control.
[Ord. 1-2014, 1/6/2014]
1. 
Providing for infiltration consistent with the natural hydrologic regime is required to compensate for the reduction in the recharge that occurs when the ground surface is disturbed or impervious surface is created or expanded. The applicant shall achieve the following infiltration requirements:
A. 
Wherever possible, infiltration should be designed to accommodate the entire water quality and runoff volume required in § 20-305.
B. 
For regulated activities involving new development, the volume of a minimum of one inch of runoff from all proposed impervious surfaces shall be infiltrated.
C. 
For regulated activities involving redevelopment, whichever is less of the following volume options shall be infiltrated:
(1) 
The volume of a minimum of one inch of runoff from all proposed impervious surfaces; or
(2) 
The total water quality and runoff volume required in § 20-305 of this chapter.
D. 
If the requirements of Subsection 1B or C of this section cannot be physically accomplished, then the applicant shall be responsible for demonstrating with data or calculations to the satisfaction of the Municipal Engineer why this infiltration volume cannot be physically accomplished on the site (e.g., shallow depth to bedrock or limiting zone, open voids, steep slopes, etc.) and what alternative volume can be infiltrated; however in all cases at least the first 1/2 inch of runoff volume shall be infiltrated.
E. 
Only if a minimum of at least 1/2 inch infiltration requirement cannot be physically accomplished on the site shall a waiver from § 20-306 be considered by the municipality.
F. 
If site conditions preclude capture of runoff from portions of the impervious surfaces, the infiltration volume for the remaining area shall be increased an equivalent amount to offset the loss.
G. 
When a project contains or is divided by multiple watersheds, the infiltration volume shall be separately addressed for each watershed.
H. 
Existing impervious surfaces located in areas outside of the site (i.e., outside of the regulated activity) may be excluded from the calculation of the required infiltration volume.
I. 
A detailed soils evaluation of the site shall be conducted by a qualified professional and at a minimum shall address soil permeability, depth to bedrock, and subgrade stability. The general process for designing the infiltration BMP shall be conducted by a qualified licensed professional and shall be consistent with the PA BMP Manual (as amended) (or other guidance acceptable to the Municipal Engineer) and in general shall:
(1) 
Analyze hydrologic soil groups as well as natural and man-made features within the site to determine general areas of suitability for infiltration practices. In areas where development on fill material is under consideration, conduct geotechnical investigations of subgrade stability; infiltration may not be ruled out without conducting these tests.
(2) 
Provide field tests such as double-ring infiltrometer or other hydraulic conductivity tests (at the elevation of the proposed infiltration surface) to determine the appropriate hydraulic conductivity rate. Standard septic/sewage percolation tests are not acceptable for design purposes.
(3) 
Design the infiltration facility for the required retention (infiltration) volume based on field-determined infiltration capacity (and apply safety factor as per applicable design guidelines) at the elevation of the proposed infiltration surface.
(4) 
On-lot infiltration features are encouraged; however, it shall be demonstrated to the Municipal Engineer that the soils are conducive to infiltration on the identified lots.
J. 
Infiltration BMPs shall be selected based on suitability of soils and site conditions and shall be constructed on soils that have the following characteristics:
(1) 
A minimum depth of 24 inches between the bottom of the BMP and the top of the limiting zone. Additional depth may be required in areas underlain by karst or carbonate geology (see Subsection 1N of this section).
(2) 
An infiltration rate sufficient to accept the additional stormwater volume and drain completely as determined by field tests conducted by the applicant.
(3) 
The infiltration facility shall completely drain the retention (infiltration) volume within three days (72 hours) from the end of the design storm.
K. 
All infiltration practices shall:
(1) 
Be selected and designed to meet the criteria of § 20-304, Subsection 1C, that are applicable to infiltration;
(2) 
Be set back at least 25 feet from all buildings and features with subgrade elements (e.g., basements, foundation walls, etc.), unless otherwise approved by the Municipal Engineer;
(3) 
For any infiltration practice that collects runoff from shared or multiple features and that is located within 50 feet of a building or feature with subgrade elements (e.g., basements, foundation walls, etc.), the bottom elevation shall be set below the elevation of the subgrade element.
L. 
Infiltration facilities shall, to the maximum extent practicable, be located to avoid introducing contaminants to groundwater:
(1) 
When a hotspot is located in the area draining to a proposed infiltration facility, an evaluation of the potential of groundwater contamination from the proposed infiltration facility shall be performed, including a hydrogeologic investigation (if necessary) by a qualified licensed professional to determine what, if any, pretreatment or additional design considerations are needed to protect groundwater quality.
(2) 
When located within a "wellhead protection area" of a public water supply well, infiltration practices shall be in conformance with the applicable approved source water protection assessment or source water protection plan.
(3) 
The applicant shall provide appropriate safeguards against groundwater contamination for land uses that may cause groundwater contamination should there be a mishap or spill.
M. 
During site construction, all infiltration practice components shall be protected from compaction due to heavy equipment operation or storage of fill or construction material. Infiltration areas shall also be protected from sedimentation. Areas that are accidentally compacted or graded shall be remediated to restore soil composition and porosity. Adequate documentation to this effect shall be submitted to the Municipal Engineer for review. All areas designated for infiltration shall not receive runoff until the contributory drainage area has achieved final stabilization.
N. 
Consideration of infiltration BMPs for areas underlain by karst or carbonate geology is encouraged, but only where the design, supporting calculations, results of soils or other site investigations or other documentation are provided to the municipality demonstrating that the potential or likelihood of subsidence or sinkholes is minimal. Evaluation of site conditions and infiltration design shall rely on guidance in the PA BMP Manual (as amended) or other guidance acceptable to the Municipal Engineer.
O. 
Groundwater quality of the carbonate aquifer shall be protected from infiltration of pollutants. At a minimum, stormwater runoff from hotspots (i.e., sources of significant pollutant runoff) shall first be discharged through a water quality BMP(s) to remove pollutants prior to infiltration. Where soil characteristics are insufficient to provide removal of pollutants from sources other than hotspots, stormwater runoff shall first be discharged through a water quality BMP(s) to remove pollutants prior to infiltration.
P. 
Where sediment transport in the stormwater runoff is anticipated to reach the infiltration system, appropriate permanent measures to prevent or collect sediment shall be installed prior to discharge to the infiltration system.
Q. 
Where roof drains are designed to discharge to infiltration practices, they shall have appropriate measures to prevent clogging by unwanted debris (for example, silt, leaves and vegetation). Such measures shall include but are not limited to leaf traps, gutter guards and cleanouts.
R. 
All infiltration practices shall have appropriate positive overflow controls.
S. 
No sand, salt or other particulate matter may be applied to a porous surface material for winter ice conditions.
T. 
The following procedures and materials shall be required during the construction of all subsurface facilities:
(1) 
Excavation for the infiltration facility shall be performed with equipment that will not compact the bottom of the seepage bed/trench or like facility.
(2) 
The bottom of the bed and/or trench shall be scarified prior to the placement of aggregate.
(3) 
Only clean aggregate with documented porosity, free of fines, shall be allowed.
(4) 
The tops, bottoms and sides of all seepage beds, trenches, or like facilities shall be covered with drainage fabric. Fabric shall be nonwoven fabric acceptable to the Municipal Engineer.
(5) 
Stormwater shall be distributed throughout the entire seepage bed/trench or like facility, and provisions for the collection of debris shall be provided in all facilities.
[Ord. 1-2014, 1/6/2014]
1. 
For regulated activities involving new development with one or more acres of earth disturbance, the applicant shall comply with the following stream channel protection requirements to minimize stream channel erosion and associated water quality impacts to the receiving waters:
A. 
The peak flow rate of the post-construction two-year, twenty-four-hour design storm shall be reduced to the predevelopment peak flow rate of the one-year, twenty-four-hour duration precipitation, using the SCS Type II distribution.
B. 
To the maximum extent practicable, and unless otherwise approved by the Municipal Engineer, the post-construction one-year, twenty-four-hour storm flow shall be detained for a minimum of 24 hours and a maximum not to exceed 72 hours from a point in time when the maximum volume of water from the one-year, twenty-four-hour storm is stored in a proposed BMP (i.e., when the maximum water surface elevation is achieved in the facility). Release of water can begin at the start of the storm (i.e., the invert of the orifice is at the invert of the proposed BMP).
C. 
For modeling purposes, the predevelopment ground cover conditions shall be determined using the corresponding ground cover assumptions presented in § 20-309, Subsection 4, of this chapter.
D. 
The minimum orifice size in the outlet structure to the BMP shall be three inches in diameter, unless otherwise approved by the Municipal Engineer, and a trash rack shall be installed to prevent clogging. For sites with small drainage areas contributing to the BMP that do not provide enough runoff volume to allow a twenty-four-hour attenuation with the three-inch orifice, the calculations shall be submitted showing this condition.
E. 
When the calculated orifice size is below three inches, gravel filters (or other methods) are recommended to discharge low-flow rates, subject to the Municipal Engineer's satisfaction. When filters are utilized, maintenance provisions shall be provided to ensure filters meet the design function.
F. 
All proposed stormwater facilities shall make use of measures to extend the flow path and increase the travel time of flows in the facility.
G. 
When a regulated activity contains or is divided by multiple drainage areas, the peak flow rate control shall be separately addressed for each drainage area.
[Ord. 1-2014, 1/6/2014]
1. 
The applicant shall comply with the following peak flow rate control requirements for all regulated activities, including those that involve new development and redevelopment:
A. 
Post-construction peak flow rates from any regulated activity shall not exceed the predevelopment peak flow rates as shown for each of the design storms specified in Table 308.1.
Table 308.1
Peak Rate Control Standards
(Peak Flow Rate of the Post-Construction Design Storm Shall be Reduced to the Peak Flow Rate of the Corresponding Predevelopment Design Storm Shown in the Table)
Post-Construction Design Storm Frequency (24-hour duration)
Predevelopment Design Storm
New Development Regulated Activities
Redevelopment Regulated Activities
2-year
1-year
2-year
5-year
5-year
5-year
10-year
10-year
10-year
25-year
25-year
25-year
50-year
50-year
50-year
100-year
100-year
100-year
B. 
For modeling purposes, the predevelopment ground cover conditions shall be determined using the corresponding ground cover assumptions presented in § 20-309, Subsection 4, of this chapter.
C. 
For regulated activities involving only redevelopment, no peak flow rate controls are required when and only if the total proposed impervious surface area is at least 20% less than the total existing impervious surface area to be disturbed by the regulated activity. In all cases where this requirement is not met, the redevelopment regulated activity shall achieve the peak flow rate controls presented in Table 308.1, using the redevelopment ground cover assumptions presented in § 20-309, Subsection 4.
D. 
Only the area of the proposed regulated activity shall be subject to the peak flow rate control standards of this chapter. Undisturbed areas for which the discharge point has not changed are not subject to the peak flow rate control standards.
E. 
Areas located outside of the site (i.e., areas outside of the regulated activity) that drain through a proposed site are not subject to peak flow rate control requirements. Drainage facilities located on the site shall be designed to safely convey flows from outside of the site through the site.
F. 
When a regulated activity contains or is divided by multiple drainage areas, the peak flow rate controls shall be separately addressed for each drainage area.
G. 
The effect of structural and nonstructural stormwater management practices implemented as part of the overall site design may be taken into consideration when calculating total storage volume and peak flow rates.
[Ord. 1-2014, 1/6/2014]
1. 
Stormwater runoff from all regulated activity sites with a drainage area of greater than five acres shall be calculated using a generally accepted calculation technique(s) that is based on the NRCS Soil Cover Complex Method. Table 309.1 summarizes acceptable computation methods. The method selected for use shall be based on the individual limitations and suitability of each method for a particular site. The use of the Rational Method to estimate peak discharges for drainage areas greater than five acres shall be permitted only upon approval by the Municipal Engineer.
Table 309.1
Acceptable Computation Methodologies for SWM Site Plan
Method
Developed By
Applicability
TR-20 (or commercial computer package based on TR-20)
USDA NRCS
Applicable where use of full hydrology computer model is desirable or necessary
TR-55 (or commercial computer package based on TR-55)
USDA NRCS
Applicable for land development plans where limitations described in TR-55 are met
HEC-1/HEC-HMS
US Army Corps of Engineers
Applicable where use of a full hydrologic computer model is desirable or necessary
Rational Method (or commercial computer package based on Rational Method)
Emil Kuichling (1889)
For sites up to 5 acres, or as approved by the municipality
Other methods
Varies
Other computation methodologies approved by the municipality
2. 
All calculations using the Soil Cover Complex Method shall use the appropriate design rainfall depths for the various return period storms consistent with this chapter. Rainfall depths used shall be obtained from NOAA Atlas 14 values consistent with a partial duration series. When stormwater calculations are performed for routing procedures or infiltration, water quality and runoff volume functions, the duration of rainfall shall be 24 hours.
3. 
All calculations using the Rational Method shall use rainfall intensities consistent with appropriate times-of-concentration (duration) and storm events with rainfall intensities obtained from NOAA Atlas 14 partial duration series estimates, or the latest version of the PennDOT Drainage Manual (PDM Publication 584). Times-of-concentration shall be calculated based on the methodology recommended in the respective model used. Times-of-concentration for channel and pipe flow shall be computed using Manning's Equation.
4. 
The applicant shall utilize the following ground cover assumptions for all predevelopment water quality and runoff volume, infiltration volume and peak flow rate calculations:
A. 
For regulated activities involving new development, the following ground cover assumptions shall be used:
(1) 
For areas that are woods (as defined in Part 2 of this chapter), predevelopment calculations shall assume ground cover of "woods in good condition."
(2) 
For all other areas (including all impervious surfaces), predevelopment calculations shall assume ground cover of "meadow."
B. 
For regulated activities involving redevelopment, the following ground cover assumptions shall be used:
(1) 
For areas that are woods (as defined in Part 2 of this chapter), predevelopment calculations shall assume ground cover of "woods in good condition."
(2) 
For areas that are not woods or not impervious surfaces, predevelopment calculations shall assume ground cover of "meadow."
(3) 
For areas that are impervious surfaces, predevelopment calculations shall assume at least 20% of the existing impervious surface area to be disturbed as "meadow" ground cover.
C. 
The applicant shall determine which stormwater standards apply to the proposed regulated activity as follows:
(1) 
Stormwater standards for new development shall apply to all proposed regulated activities that involve only new development activities as defined in this chapter.
(2) 
Stormwater standards for redevelopment shall apply to all proposed regulated activities that involve only redevelopment activities as defined in this chapter.
(3) 
At the discretion of the Municipal Engineer, regulated activities that involve a combination of both new development and redevelopment activities, as defined in this chapter, may either:
(a) 
Apply the stormwater standards (redevelopment or new development) that are associated with the activity that involves the greatest amount of land area; or
(b) 
Apply the redevelopment and new development stormwater standards to the corresponding redevelopment and new development portions of the proposed regulated activity.
5. 
Runoff curve numbers (CN) for both predevelopment and proposed (post-construction) conditions to be used in the Soil Cover Complex Method shall be obtained from Table C-1 in Appendix C of this chapter.[1]
[1]
Editor's Note: Appendix C is included as an attachment to this Chapter.
6. 
Runoff coefficients (C) for both predevelopment and proposed (post-construction) conditions for use in the Rational Method shall be obtained from Table C-2 in Appendix C of this chapter.
7. 
Weighted averaging of runoff coefficients shall not be used for manual computations or input data for water quality and runoff volume calculations.
8. 
Hydraulic computations to determine the capacity of pipes, culverts, and storm sewers shall be consistent with methods and computations contained in the Federal Highway Administration Hydraulic Design Series Number 5 (Publication No. FHWA-NHI-01-020 HDS No. 5, as amended). Hydraulic computations to determine the capacity of open channels shall be consistent with methods and computations contained in the Federal Highway Administration Hydraulic Engineering Circular Number 15 (Publication No. FHWA-NHI-05-114 HEC 15, as amended). Values for Manning's roughness coefficient (n) shall be consistent with Table C-3 in Appendix C of this chapter.
9. 
Runoff calculations shall include the following assumptions:
A. 
Average antecedent moisture conditions (for the Soil Cover Complex Method only, for example, TR-55, TR-20).
B. 
A Type II distribution storm (for the Soil Cover Complex Method only, for example, TR-55, TR-20).
[Ord. 1-2014, 1/6/2014]
1. 
Any BMP intended to hold standing water for four days or longer shall be designed to incorporate biologic controls consistent with the West Nile Guidance found in Appendix D,[1] PADEP Document 363-0300-001, "Design Criteria - Wetlands Replacement/Monitoring" (as amended), (or contact the Pennsylvania State Cooperative Wetland Center or the Penn State Cooperative Extension office for design information.)
[1]
Editor's Note: Appendix D is included as an attachment to this chapter.
2. 
Any stormwater basin required or regulated by this chapter designed to store runoff and requiring a berm or earthen embankment shall be designed to provide an emergency spillway to safely convey flow up to and including the one-hundred-year proposed conditions. The height of embankment shall provide a minimum one foot of freeboard above the maximum pool elevation computed when the facility functions for the one-hundred-year proposed conditions inflow. Should any BMP require a dam safety permit under Pa. Code Chapter 105 regulations, the facility shall be designed in accordance with and meet the regulations of Pa. Code Chapter 105 concerning dam safety. Pa. Code Chapter 105 may require the safe conveyance of storms larger than the one-hundred-year event.
3. 
Any drainage conveyance facility and/or channel not governed by Pa. Code Chapter 105 regulations shall be designed to convey, without damage to the drainage facility or roadway, runoff from the twenty-five-year storm event. Larger storm events (fifty-year and one-hundred-year storms) shall also be safely conveyed in the direction of natural flow without creating additional damage to any drainage facilities, nearby structures, or roadways.
4. 
Conveyance facilities to or exiting from stormwater management facilities (i.e., detention basins) shall be designed to convey the design flow to or from the facility.
5. 
Roadway crossings or structures located within designated floodplain areas shall be able to convey runoff from a one-hundred-year design storm consistent with Federal Emergency Management Agency National Flood Insurance Program - Floodplain Management Requirements.
6. 
Any facility located within a PennDOT right-of-way shall comply with PennDOT minimum design standards and permit submission and approval requirements.
7. 
Adequate erosion protection and energy dissipation shall be provided along all open channels and at all points of discharge. Design methods shall be consistent with the Federal Highway Administration Hydraulic Engineering Circular Number 11 (Publication No. FHWA-IP-89-016, as amended) and the PADEP Erosion and Sediment Pollution Control Program Manual (Publication No. 363-2134-008, as amended), or other design guidance acceptable to the Municipal Engineer.
[Ord. 1-2014, 1/6/2014]
[Ord. 1-2014, 1/6/2014]
1. 
All storm sewer pipes, grass waterways, open channels, swales and other water-carrying facilities that service drainage areas within the site shall be designed to convey the twenty-five-year storm event unless, in the opinion of the Township or Township Engineer, the character of development and potential damage warrant design for the fifty- or one-hundred-year storm.
2. 
Stormwater management facilities that convey off-site water through the site shall be designed to convey the fifty-year storm event.
3. 
All developments shall include provisions that allow for the overland conveyance and flow of the post-developed one-hundred-year storm event without damage to public or private property.
4. 
Conveyance facilities shall comply with the design criteria in the following table:
Conveyance Facility Design Criteria
Location
Within Public Street Right-of-Way
Outside Public Street Right-of-Way
Loading
All
Vehicular Loading
Nonvehicular Loading
A.
Pipe design
(1)
Material
SLHDPE, RCP
PVC, SLHDPE, RCP
PVC, SLHDPE, RCP
(2)
Slope (minimum)
0.5%
0.5%
0.5%
(3)
Cover
1 foot to stone subgrade
1 foot to stone subgrade
1 foot to surface
(4)
Diameter (minimum)
15 inches
15 inches
8 inches
(5)
Street crossing angle
75° to 90°
N/A
N/A
(6)
Access /maintenance port frequency (maximum)
400 feet
400 feet
600 feet
B.
Inlet design
(1)
Material
Concrete
Concrete
N/A
(2)
Grate depression
2 inches
2 inches
1 inch minimum
C.
Manhole design
(1)
Material
Concrete
Concrete
Concrete
D.
Swale design
(1)
Freeboard (minimum)
6 inches
N/A
6 inches
(2)
Velocity (maximum)
Stability check
N/A
Stability check
(3)
Slope (minimum)
1%
N/A
1%
(4)
Side slopes (residential area)
4:1 max
N/A
4:1 max
(5)
Side slopes (nonresidential area)
4:1 max
N/A
3:1 max
(6)
Bottom width to flow depth ratio
12:1
N/A
12:1
E.
Outlet design
(1)
End treatment
Headwall/endwall
N/A
Headwall/ endwall or flared end section
(2)
Energy dissipater
Required
N/A
Required
KEY:
N/A = Not applicable or no criteria specified.
SLHDPE = Smooth lined high-density polyethylene pipe.
PVC = Polyvinyl chloride.
RCP = Reinforced concrete pipe.
5. 
All storm sewer pipes, culverts, manholes, inlets, endwalls and end sections shall be constructed in accordance with Pennsylvania Department of Transportation, Form 408, as amended.
6. 
Storm sewer pipes, culverts, manholes, inlets, endwalls, and end sections proposed for dedication or located along streets shall conform to the requirements of the Pennsylvania Department of Transportation, Bureau of Design, Standards for Roadway Construction, Publication No. 72, in effect at the time the design is submitted.
7. 
The roughness coefficient (Manning "n" values) used for conveyance pipe capacity calculations shall be determined in accordance with PennDOT Publication 584, PennDOT Drainage Manual, or per the manufacturer's specifications.
8. 
Inlets shall be placed on both sides of the street at low spots, at changes in the horizontal or vertical directions of storm sewers, and at points where the flow in gutters exceeds three inches. Inlets shall normally be along the curbline at or beyond the curb radius points. For the purpose of inlet location at corners, the depth of flow shall be considered for each gutter. At intersections, the depth of flow for the twenty-five-year storm across the through streets shall not exceed one inch. Inlets shall be depressed below the grade of the roadside swale, curbline, or ground surface as indicated in the above design chart. An access/maintenance port may either be an inlet or manhole. Manholes may be substituted for inlets at locations where inlets are not required to collect surface runoff.
9. 
Material consistency and placement depths for storm sewer pipe backfill shall be (at a minimum) per all applicable pipe manufacturer's recommendations, further providing it should be free of large (not exceeding six inches in any dimension) stone, rock, or other objectionable or detritus material.
10. 
Within the public street right-of-way, the gutter spread based on the twenty-five-year storm shall be no greater than 1/2 of the travel lane and have a maximum depth of three inches at the curbline. A parking lane shall not be considered as part of the travel lane.
11. 
Inlets or manholes shall be placed at all points of change in the horizontal or vertical directions of conveyance pipes. Curved pipe sections are prohibited.
12. 
All inlets placed in paved areas shall have heavy-duty bicycle-safe grating consistent with PennDOT Publication 72M, latest edition. A note to this effect shall be added to the stormwater management site plan or inlet details therein.
13. 
Inlets, junction boxes, or manholes greater than five feet in depth shall be equipped with nonaluminum ladder rungs and shall be detailed on the stormwater management site plan.
14. 
Where the connecting pipe has a diameter of 18 inches or greater, headwalls and endwalls shall be provided with a protective barrier device to prevent entry of the storm sewer pipe by unauthorized persons. Such protection devices shall be designed to be removable for cleaning.
15. 
In addition to the material requirements in this section, culverts designed to convey waters of the commonwealth may be constructed with either a corrugated metal arch or a precast concrete culvert.
16. 
Flow velocities from any storm sewer shall not result in a degradation of the receiving channel.
17. 
Energy dissipaters shall be placed at the outlets of all storm sewer pipes where flow velocities exceed maximum permitted channel velocities.
18. 
The capacities of swales shall be computed from the Manning Equation using the following design parameters: Permissible open channel velocities and design standards shall be in accordance with good engineering practice as documented in the Engineering Field Manual for Conservation Practices, USDA, SCS, or in Design Charts for Open-Channel Flow, Hydraulic Design Series No. 3, United States Department of Transportation.
A. 
Vegetated swales:
(1) 
The first condition shall consider swale stability based upon a low degree of retardance ("n" = 0.03);
(2) 
The second condition shall consider swale capacity based upon a higher degree of retardance ("n" = 0.05); and
B. 
The "n" factors to be used for paved or riprap swales or gutters shall be based upon accepted engineering design practices, as approved by the Township Engineer.
C. 
All swales shall be designed to maximize infiltration and concentrate low flows to minimize siltation and meandering, unless geotechnical conditions do not permit infiltration.
[Ord. 1-2014, 1/6/2014]
1. 
Aboveground storage facilities shall consist of all stormwater facilities which store, infiltrate/evaporate/transpire, clean, release, or otherwise affect stormwater runoff and the top of which is exposed to the natural environment. Aboveground storage facilities shall be located above the finished ground elevation. Aboveground storage facilities do not include stormwater management facilities designed for conveyance, or cisterns.
2. 
Facilities with a facility depth greater than eight feet shall not be permitted in residential areas.
3. 
Aboveground storage facilities shall comply with the design criteria in the following table:
Aboveground Storage Facility Design Criteria
Facility Depth
Less than 2 Feet
2 Feet to 8 Feet
Greater Than 8 Feet
A.
Embankment Geometry
(1)
Top width (minimum)
2 feet
5 feet
8 feet
(2)
Interior side slope (maximum)
2:1
3:1
5:1
(3)
Exterior side slope (maximum)
2:1
3:1
3:1
B.
Embankment construction
(1)
Key trench
Not required
Required
Required
(2)
Pipe collar
Not required
Required
Required
(3)
Compaction density
Not required
Required
Required
C.
Internal Construction
(1)
Dewatering feature
N/A
Required
Required
(2)
Pretreatment elements*
Not required
Required
Required
D.
Outlet Structure
(1)
Pipe size (minimum)
6 inches
12 inches
15 inches
(2)
Pipe material
SLHDPE, PVC, RCP
SLHDPE, RCP
RCP
(3)
Anticlogging devices
Required
Required
Required
(4)
Antivortex design
Not required
Required
Required
(5)
Water-tight joints in piping?
No
Yes
Yes
E.
Spillway Requirements
(1)
Spillway freeboard (minimum)
Not required
6 inches
12 inches
(2)
Width (minimum)
Not required
10 feet
20 feet
(3)
Width (maximum)
Not required
50 feet
50 feet
(4)
Spillway channel design
Not required
Required
Required
(5)
Routing of 100-year storm
Permitted
Permitted
Permitted
KEY:
*
Pretreatment required for infiltration BMPs unless shown to be unnecessary.
N/A = Not applicable.
SLHDPE = Smooth lined high-density polyethylene pipe.
PVC = Polyvinyl chloride.
RCP = Reinforced concrete pipe.
4. 
If required, pretreatment elements shall be designed according to the BMP Manual.
5. 
All aboveground storage facilities shall be structurally sound and shall be constructed of sound and durable materials. All discharge control devices with appurtenances shall be made of reinforced concrete and stainless steel. Bolts/fasteners shall be stainless steel. The completed structure and the foundation of all basins shall be stable under all probable conditions of operation. Spillways shall be capable of discharging the peak discharge of a post-development one-hundred-year storm event through the emergency spillway facilities, in a condition that assumes the primary outlet(s) are blocked, which will not damage the integrity of the facility or the downstream drainage areas. Use of the spillway to convey flows greater than the fifty-year design storm shall be permitted.
6. 
The effect on downstream areas if the aboveground storage facility embankment fails shall be considered in the design of all basins. The basin shall be designed to minimize the potential damage caused by such failure of the embankment.
7. 
An easement shall be provided from the spillway outfall to a natural or artificial watercourse.
8. 
The maximum depth of water for aboveground storage facilities without restricted access shall not exceed six feet unless approved by modification by the Supervisors. Access to basins with a maximum depth of water greater than six feet shall be restricted by fencing that will discourage access.
9. 
Aboveground storage facilities without restricted access shall have impoundment areas with side slopes no greater than the horizontal to vertical ratios in the design chart. Access to basins with steeper side slopes than those shown in the chart shall be restricted by fencing that will discourage access.
10. 
All detention basins shall include an outlet structure to permit draining the rate control volume within 24 hours, exclusive of BMP storage.
11. 
All outlet structures and emergency spillways shall include a satisfactory means of dissipating the energy of flow at their outlet to assure conveyance of flow without endangering the safety and integrity of the basin and the downstream drainage area.
12. 
An impervious core/key trench, if required, shall consist of a cutoff trench (below existing grade) and a core trench (above existing grade). A key trench may not be required wherever the facility depth is less than two feet or where it can be shown that another design feature, such as the use of an impermeable liner, accomplishes the same purpose. Materials used for the core shall conform to the Unified Soil Classification GC, SC, CH, or CL and must have at least 30% passing a No. 200 sieve.
A. 
The dimensions of the core shall provide a minimum trench depth of two feet below existing grade, a minimum width of four feet and a side slope of 1H:1V or flatter.
B. 
The core should extend up to the twenty-five-year water surface elevation or six inches below the emergency spillway elevation, whichever is lower.
C. 
The core shall extend four feet below any pipe penetrations through the impervious core. The core shall be installed along or parallel to the center line of the embankment.
D. 
Compaction requirements shall be the same as those for the embankment to assure maximum density and minimum permeability.
13. 
All pipe collars, if required, shall be designed in accordance with Chapter 7 of the PADEP Erosion and Sediment Control Manual. The material shall consist of concrete or otherwise nondegradable material around the outfall barrel and shall be watertight.
14. 
The embankment fill material shall be free of roots, stumps, wood, rubbish, stones greater than six inches, and frozen or other objectionable materials.
15. 
The minimum freeboard for spillways shall be provided about the one-hundred-year design elevation of the water surface at the emergency spillway in a condition that assumes the primary outlet(s) is/are blocked.
16. 
Wherever possible, basins shall have a nonuniform (naturalistic) shape, rather than a geometric design in the form of a square or rectangle.
17. 
The minimum bottom slope of facilities not designed for infiltration shall be 1%. A flatter slope may be used if an equivalent dewatering mechanism is provided.
18. 
If required, dewatering shall be provided through the use of underdrain, surface device, or an alternate approved by the Township Engineer. If the facility is to be used for infiltration, the dewatering device should be capable of being disconnected and only be made operational if the basin is not dewatering within the required time frame.
19. 
Within basins designed for infiltration, existing native vegetation shall be preserved, if possible. For existing unvegetated areas or for infiltration basins that require excavation, a planting plan shall be prepared in accordance with this chapter and the BMP Manual.
[Ord. 1-2014, 1/6/2014]
1. 
Stormwater runoff volume controls shall be implemented using the Design Storm Method of Subsection 1A below.
A. 
The Design Storm Method (CG-1 in the BMP Manual) is applicable to any size of regulated activity. The method requires detailed modeling based on site conditions.
(1) 
The post-development total runoff volume shall not increase for all storms equal to or less than the two-year, twenty-four-hour storm event.
(2) 
For modeling purposes:
(a) 
Existing (predevelopment) nonforested pervious areas must be considered meadow in good condition.
(b) 
Twenty percent of existing impervious area, when present, shall be considered meadow in good condition in the model for existing conditions.
(c) 
The maximum loading ratio for volume control facilities in karst areas shall be 3:1 impervious drainage area to infiltration area and 5:1 total drainage area to infiltration area. The maximum loading ratio for volume control facilities in non-karst areas shall be 5:1 impervious drainage area to infiltration area and 8:1 total drainage area to infiltration area. A higher ratio would be acceptable if proper justification is submitted and approved.
B. 
Any portion of the volume control storage that meets the following conditions may also be used as rate control storage:
(1) 
Volume control storage that depends on infiltration and is designed according to the infiltration standards in this chapter and the BMP Manual.
(2) 
The volume control storage which will be used for rate control is that storage which is available within 24 hours from the end of the design storm based on the stabilized infiltration rate and/or the evapotranspiration rate.
C. 
Volume Control BMPs and pretreatment elements shall be designed in accordance with the BMP Manual and the soil and infiltration testing requirements of § 20-501.
D. 
All applicable worksheets from Chapter 8 of the BMP Manual must be used when establishing volume controls.
[Ord. 1-2014, 1/6/2014]
1. 
Subsurface storage facilities shall consist of all stormwater facilities which store, infiltrate/evaporate/transpire, clean, release, or otherwise affect stormwater runoff and the top of which is not exposed to the natural environment. Subsurface facilities shall be located below the finished ground elevation. Subsurface facilities shall not include stormwater management facilities designed for conveyance.
2. 
Subsurface storage facilities shall comply with the design criteria in the following table:
Subsurface Storage Facility Design Criteria
Facility Type
Infiltration and Storage
Storage without Infiltration
A
Facility Geometry
(1)
Depth from surface (maximum)
2 feet less than limiting zone
N/A
(2)
Loading ratio (maximum)
Per BMP Manual*
N/A
B.
Distribution System Requirements
(1)
Pipe size (minimum)
4 inches
4 inches
(2)
Loading/balancing
Required
Not required
(3)
Observation/access ports
Required
Required
NOTES:
*
Unless otherwise determined by professional geologic evaluation.
3. 
The facility shall be designed according to the BMP Manual to provide pretreatment to eliminate solids, sediment, and other debris from entering the subsurface facility.
4. 
The facility shall be designed to provide a means of evenly balancing the flow across the surface of the facility to be used for infiltration.
5. 
For facilities with the bottom less than five feet below the average grade of the ground surface, a cleanout shall be an acceptable observation port. For facilities with the bottom five feet or more below the average grade of the ground surface, a manhole or other means acceptable to the Township shall be provided for access to and monitoring of the facility. The number of access points shall be sufficient to flush or otherwise clean out the system.
6. 
Storage and distribution system piping shall be PVC, SLHDPE, or RCP.
7. 
The stone used for infiltration beds shall be clean, washed, uniformly graded coarse aggregate. The void ratio for design shall be assumed to be 40%.
8. 
Material consistency and placement depths for backfill shall be (at a minimum) per all applicable pipe manufacturer's recommendations, further providing it should be free of large (not exceeding six inches in any dimension) stone, rock, or other objectionable or detritus material. Select nonaggregate material should be indigenous to the surrounding soil material for nonvehicular areas. Backfill within vehicular areas shall comply with this section unless otherwise specified in governing municipal road/street or subdivision and land development ordinances. Furthermore, if the design concept includes the migration of runoff through the backfill to reach the infiltration facility, the material shall be well-drained, free of excess clay or clay-like materials and generally uniform in gradation.
9. 
Nonwoven geotextiles shall be placed on all sides of subsurface infiltration facilities.
10. 
When located under pavement, the top of the subsurface facility shall be a minimum of three inches below the bottom of the pavement subbase. Where located under vegetative cover, the top of the subsurface facility shall be a minimum of 12 inches below the surface elevation or as required to establish vegetation.
11. 
Subsurface facilities shall be designed to safely convey and/or bypass flows from storms exceeding the design storm.