Editor’s Note: Former Article VI, Residential Code For One- And Two-Family Dwellings, containing Section 500.070, was repealed 7-5-2017 by § 6 of Ord. No. 17-061. See now Section 500.150.
[Ord. No. 17-061 § 6, 7-5-2017; Ord. No. 23-102, 11-13-2023]
St. Charles County hereby adopts the 2021 St. Charles County Fuel Gas Code, a copy of which shall be deposited in the Office of the County Registrar with this ordinance, with the following amendments by additions, insertions, deletions and changes so that such section and subsections read as follows:
(CHAPTER 1 SCOPE AND ADMINISTRATION)
(SECTION 101 (IFGC) SCOPE AND GENERAL REQUIREMENTS)
101.1. Title. These regulations shall be known as the Fuel Gas Code of St. Charles County, Missouri, hereinafter referred to as "this code."
(SECTION 103 (IFGC) CODE COMPLIANCE AGENCY)
103.1 Creation of enforcement agency. The Division of Building and Code Enforcement within the Department of Community Development is hereby created and the official in charge thereof shall be known as the Code Official. The function of the agency shall be the implementation, administration and enforcement of the provisions of this code.
103.2 Appointment. The Code Official shall be appointed as provided by ordinance.
(SECTION (IFGC) 106 PERMITS)
106.5.3 Expiration. Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within one hundred eighty (180) days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of one hundred eighty (180) days after the time the work is commenced.
106.5.3.1 Reinstatement. A permit that has expired may be reinstated where approved by the Code Official. The request for reinstatement shall be in writing and justifiable caused demonstrated.
106.5.4 Extensions. The Code Official is authorized to grant, in writing, one (1) or more extensions of time for periods not more than one hundred eighty (180) days each. The extension shall be requested in writing and justifiable cause demonstrated.
(SECTION 107 (IFGC) CONSTRUCTION DOCUMENTS)
107.1 General. Construction documents, engineering calculations, diagrams and other data shall be submitted as required by the Code Official, with each application for a permit. The Code Official shall require construction documents, computations and specifications to be prepared and designed by a registered design professional where required by State law. Where special conditions exist, the Code Official is authorized to require additional construction documents to be prepared by a registered design professional. Construction documents shall be drawn to scale and shall be of sufficient clarity to indicate the location, nature and extent of the work proposed and show in detail that the work conforms to the provisions of this code. Construction documents for buildings more than two (2) stories in height shall indicate where penetrations will be made for mechanical systems, and the materials and methods for maintaining required structural safety, fire resistance rating and fireblocking.
Exception: The Code Official shall have the authority to waive the submission of construction documents, calculations or other data if the nature of the work applied for is such that reviewing of construction documents is not necessary to determine compliance with this code.
107.1.2 Electronic submission. Where design documents, including, but not limited to, plot plans, site plans, design drawings, specifications, etc. are originally created electronically, the Building Official is authorized to require electronic submittal of documents in a portable document format (PDF) or similar format for review. Where design documents were originally prepared on paper and are submitted in a paper form, the Code Official is authorized to charge a fee for converting those drawings to PDF equal to the cost incurred by County staff recreating the document and not to exceed more than one dollar ($1.00) per page.
Exception: Where submittal documents were originally prepared by hand and are eleven (11) inches by seventeen (17) inches or less, the fee for document conversion shall not be charged.
(SECTION 113 (IFGC) MEANS OF APPEALS)
113.1 General. For the purposes of this code, all appeals shall be in accordance with the procedure established for the Building Code of St. Charles County, Missouri, in Section 113 of Section 500.100.
113.2 Limitations on authority. Delete in its entirety.
113.3 Qualifications. Delete in its entirety.
113.4 Administration. Delete in its entirety
(SECTION 114 (IFGC) BOARD OF APPEALS)
114.1 Membership of board. The Board of Appeals shall consist of five (5) members as outlined in Article XV, Chapter 500 of the St. Charles County, Missouri, adopting ordinance.
(SECTION 115 (IFGC) VIOLATIONS)
115.4 Violation penalties. Persons who shall violate a provision of this code or shall fail to comply with any of the requirements thereof or who shall erect, install, alter or repair work in violation of the approved construction documents or directive of the Code Official, or a permit or certificate issued under the provisions of this code, shall be guilty of a misdemeanor and upon conviction thereof shall be punishable by a fine of not more than five hundred dollars ($500.00). Each day that a violation continues after due notice has been served shall be deemed a separate offense.
(SECTION 116 (IFGC) STOP WORK ORDER)
116.2 Issuance. The stop work order shall be in writing and shall be given to the owner of the property involved, the owner's authorized agent or the person performing the work. Upon issuance of a stop work order, the cited work shall immediately cease. The stop work order shall state the reason for the order and the conditions under which the cited work will be permitted to resume. Any person served with a stop work order shall pay an administrative penalty of up to two hundred fifty dollars ($250.00)