[Ord. No. 5.000 § V, 9-9-1991]
Construction drawings and specifications shall be prepared by a Missouri Registered Professional Engineer. Three (3) complete sets with the Engineer's seal affixed shall be submitted for review by the City. One (1) set stamped approved and signed by the City Engineer shall be returned to the designer. On completion of the project, the designer shall develop a set of as-built corrections to the original drawings and submit one (1) corrected set to the City.
[Ord. No. 5.000 § V, 9-9-1991]
The drawings shall include as the first sheet a drainage area map. This map shall show contour elevations to five-foot intervals as a minimum. The basin tributary to each principal facility shall be delineated and numbered. A table listing basin areas, time of concentration, runoff co-efficient, return period or probability of event, and flow shall be included. Receiving systems, if any, shall be identified and flow capacities of key elements listed. Scale as required.
[Ord. No. 5.000 § V, 9-9-1991]
Plan drawings shall delineate all proposed and existing utilities, streets, and appurtenances in the project area. Property lines, right of way lines, easements, the one percent (1%) probability flood plain, and the two percent (2%) probability flood plain shall be delineated. Finish grading shall be shown in two-foot contour intervals for storm water channels. Any test borings or surface rock features shall be located. Plan drawings shall generally be scaled one (1) inch equals twenty (20) feet.
[Ord. No. 5.000 § V, 9-9-1991]
Elevation drawings shall be provided for all enclosed systems and channels. Existing and final surface grades shall be delineated. Pipe lines shall have pipe size, material, and slope identified. Channels shall have gradient delineated. Invert elevations and top elevations for each structure shall be given. Test borings and rock features shall be located. All crossings utilities shall be located and identified. Elevation drawings shall generally be scaled one (1) inch equals five (5) feet.
[Ord. No. 5.000 § V, 9-9-1991]
Detail sheets shall show all standard drawings and original drawings for the project. Separate plan/profile/detail sheets shall be included for culverts crossing streets.
[Ord. No. 5.000 § V, 9-9-1991]
A. 
Specifications for construction are required in a separate bound copy. At a minimum, all materials used in construction shall be covered including pipe, inlets, manholes, and other appurtenances. General specifications for excavation and backfill, concrete, sodding and seeding, and other pertinent areas are required. The City may require that insurance certificates and maintenance bond be attached to the specifications. The specifications shall provide specific directions to the contractor(s) on the control of erosion during the construction process. Provisions shall be included that will preclude accidental release of contaminants such as fuels, oils, fertilizers, and the like to the waters of the State.
B. 
Construction drawings and specifications for storm water facilities may be included with, or made a part of, general plan and specifications for a project.