Exciting enhancements are coming soon to eCode360! Learn more 🡪
Township of Douglass, PA
Berks County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
[Ord. 2008-1, 4/1/2008, § 301]
1. 
Applicants proposing regulated activities in Schuylkill River Watershed which do not fall under the exemption criteria shown in § 23-142 shall submit a drainage plan consistent with the Schuylkill River Watershed Stormwater Management Plan to the Township of Douglass for review. These criteria shall apply to the total proposed development even if development is to take place in stages.
2. 
The applicant is required to evaluate practicable alternatives to the surface discharge of stormwater, the creation of impervious surfaces and the degradation of waters of the commonwealth, and must maintain as much as possible the natural hydrologic regime.
3. 
The drainage plan must be designed consistent with the sequencing provisions of § 23-124 to ensure maintenance of the natural hydrologic regime and to promote groundwater recharge and protect groundwater and surface water quality and quantity. The drainage plan designer must proceed sequentially in accordance with this Part 1C.
4. 
Existing points of concentrated drainage that discharge onto adjacent property shall not be altered in any manner which could cause property damage without permission of the affected property owner(s) and shall be subject to any applicable discharge criteria specified in this Part.
5. 
Areas of existing diffused drainage discharge shall be subject to any applicable discharge criteria in the general direction of existing discharge, whether proposed to be concentrated or maintained as diffused drainage areas, except as otherwise provided by this Part. If diffused drainage discharge is proposed to be concentrated and discharged onto adjacent property, the applicant must document that adequate downstream conveyance facilities exist to safely transport the concentrated discharge, or otherwise prove that no erosion, sedimentation, flooding or other impacts will result from the concentrated discharge.
6. 
Where a development site is traversed by existing watercourses, drainage easements shall be provided conforming to the line of such watercourses. The terms of the easement shall conform to the stream buffer requirements contained in § 23-126, Subsection 1D.
7. 
Any stormwater management facilities regulated by this Part that would be located in or adjacent to waters of the commonwealth or wetlands shall be subject to approval by Pennsylvania DEP through the joint permit application process, or, where deemed appropriate by Pennsylvania DEP, the general permit process. When there is a question whether wetlands may be involved, it is the responsibility of the applicant or his agent to show that the land in question cannot be classified as wetlands, otherwise approval to work in the area must be obtained from Pennsylvania DEP.
8. 
Any alteration that affects stormwater flow directly or indirectly toward a PennDOT facility shall be subject to PennDOT regulations.
9. 
Minimization of impervious surfaces and infiltration of runoff through seepage beds, infiltration trenches, etc., are encouraged, where soil conditions permit, to reduce the size or eliminate the need for detention facilities or other structural BMPs.
10. 
Roof drains shall not be connected to impervious surfaces in order to promote overland flow and infiltration/percolation of stormwater where advantageous to do so. When site conditions preclude infiltration/percolation, then it shall be permitted on a case by case basis by the Township of Douglass.
11. 
All stormwater runoff shall be treated for water quality.
12. 
Transference of runoff to or from an EV/HQ watershed is prohibited unless otherwise authorized by DEP, DRBC or SRBC.
[Ord. 2008-1, 4/1/2008, § 302]
Permits must be obtained for all relevant regulated activities, in compliance with any and all applicable local, county, state and federal regulations.
[Ord. 2008-1, 4/1/2008, § 303]
1. 
No regulated earth disturbance activities within the Township of Douglass shall commence until the Township of Douglass receives an approval from the Berks County Conservation District of an erosion and sediment control plan for construction activities.
2. 
DEP has regulations that require an erosion and sediment control plan for any earth disturbance activity of 5,000 square feet or more, under 25 Pa. Code § 102.4(b).
3. 
In addition, under 25 Pa. Code, Chapter 92, a DEP "NPDES construction activities" permit is required for regulated earth disturbance activities. Evidence of any necessary permit(s) for regulated earth disturbance activities from the appropriate DEP regional office or Berks County Conservation District must be provided to the Township of Douglass. The issuance of an NPDES construction permit (or permit coverage under the Statewide General Permit (PAG-2) satisfies the requirements Subsection 1.
4. 
A copy of the erosion and sediment control plan and any required permit, as required by DEP regulations, shall be available at the project site at all times.
5. 
Additional erosion and sediment control design standards and criteria are recommended to be applied where infiltration BMPs are proposed shall include the following:
A. 
Areas proposed for infiltration BMPs shall be protected from sedimentation and compaction during the construction phase to maintain maximum infiltration capacity.
B. 
Infiltration BMPs shall not be constructed nor receive runoff until the entire contributory drainage area to the infiltration BMP has achieved final stabilization.
[Ord. 2008-1, 4/1/2008, § 304]
1. 
For projects disturbing one acre or more, the design of all regulated activities shall include evaluation of practicable alternatives to the surface discharge of stormwater, the creation of impervious surfaces, and the degradation of waters of the commonwealth, and must maintain as much as possible the natural hydrologic regime of the site.
A. 
An alternative is practicable if it is available and capable of being done after taking into consideration cost, existing technology and logistics in light of overall project purposes, and other Township requirements.
B. 
All practicable alternatives to the discharge of stormwater are presumed to have less adverse impact on quantity and quality of waters of the commonwealth unless otherwise demonstrated.
2. 
The applicant shall demonstrate that they designed the regulated activities that disturb one acre or more included consideration of the following issues:
A. 
Prepare an existing resource and site analysis map (ERSAM), showing environmentally sensitive areas including, but not limited to, steep slopes, ponds, lakes, streams, wetlands, hydric soils, vernal pools, floodplains, stream buffer zones, hydrologic soil groups A and B (areas conducive to infiltration), special geologic features, any existing recharge areas and any other requirements outlined in the Township Subdivision and Land Development Ordinance [Chapter 22].
B. 
Establish appropriate buffers for each of the delineated environmentally sensitive areas per the Township Zoning Ordinance [Chapter 27] (See § 23-126, Subsection 1D, for stream buffers and § 23-125, Subsection 2K, for special geologic feature buffers).
C. 
Prepare a draft project layout avoiding sensitive areas identified in Subsection 2A.
D. 
Identify site specific existing conditions drainage areas, discharge points, recharge areas and hydrologic soil groups A and B.
E. 
Evaluate nonstructural stormwater management alternatives.
(1) 
Minimize earth disturbance.
(2) 
Minimize impervious surfaces.
(3) 
Break up large impervious surfaces.
F. 
Satisfy infiltration objective (§ 23-125) and provide for stormwater pretreatment prior to infiltration. Pretreatment may not be necessary for rooftop runoff which enters the infiltration facility directly from a roof leader.
G. 
Satisfy water quality (§ 23-126) and stream bank erosion protection objective (§ 23-127).
H. 
Determine what management district the site falls into (Appendix 23-1-D) and conduct an existing conditions runoff analysis.
I. 
Prepare final project design to maintain existing conditions drainage areas and discharge points, to minimize earth disturbance and impervious surfaces, and to the maximum extent possible, to ensure the remaining site development has no surface or point discharge.
J. 
Conduct a proposed conditions runoff analysis based on the final design and to meet the release rate and in turn the overbank flow and extreme event requirements (§ 23-128).
K. 
Manage any remaining runoff through treatment prior to discharge, as part of detention, bioretention, direct discharge or other structural control.
[Ord. 2008-1, 4/1/2008, § 305]
1. 
Maximizing the ground water recharge capacity of the area being developed is required. Design of the infiltration stormwater management facilities shall give consideration to providing ground water recharge to compensate for the reduction in the percolation that occurs when the ground surface is disturbed or impervious surface is created. It is recommended that roof runoff be directed to infiltration BMPs which can be over-designed to compensate for the infiltration losses due to parking areas. It is recommended that roof runoff be directed to infiltration BMPs which may be designed to compensate for the runoff from parking areas. These measures are required to be consistent with § 23-103, and take advantage of utilizing any existing recharge areas.
2. 
Infiltration may not be feasible on every site due to site-specific limitations such as soil type. If it cannot be physically accomplished, due to seasonal high water table, soil permeability rate, soil depth or setback distances from special geologic features, then the design professional shall be responsible to show that this cannot be physically accomplished. If it can be physically accomplished, then the volume of runoff to be infiltrated shall be determined from paragraph .A.3 depending on demonstrated site conditions and shall be the greater of the two volumes.
A. 
Infiltration BMPs shall meet the following minimum requirements:
(1) 
Infiltration Requirements. Regulated activities will be required to infiltrate, where site conditions permit, a portion of the runoff created by the development as part of an overall stormwater management plan designed for the site. The volume of runoff to be infiltrated shall be determined from subparagraphs (3)(a) or (3)(b) depending upon demonstrated site conditions.
(2) 
Infiltration BMPs intended to receive runoff from developed areas shall be selected based on suitability of soils and site conditions and shall be constructed on soils that have the following characteristics:
(a) 
A minimum depth of 24 inches between the bottom of the BMP and the limiting zone.
(b) 
An infiltration and/or percolation rate sufficient to accept the additional stormwater load and drain completely as determined by field tests conducted by the applicant's design professional.
(c) 
The infiltration facility shall be capable of completely infiltrating the required retention (infiltration) volume within four days (96 hours).
(d) 
Pretreatment shall be provided prior to infiltration.
(3) 
The size of the infiltration facility shall be based upon the following volume criteria:
(a)
NRCS Curve Number Equation.
The NRCS runoff equation shall be utilized to calculate infiltration requirements (I) in inches.
Equation 23-125
I (Infiltration requirement, in inches) = (200 / CN) - 2
Where:
CN = SCS (NRCS) curve number of existing conditions contributing to the infiltration facility.
This equation is displayed graphically in, and the infiltration requirement can be determined from Figure 23-125.
It has been determined that infiltrating 0.46 inches of runoff from the impervious areas will aid in maintaining the hydrologic regime of the watershed. However, the rounded number 0.5 inches will be used.
023 Fig 23-125 Infiltration Curve.tif
Figure 23-125. Infiltration requirement based upon NRCS Curve Number.
The retention (infiltration) volume (Rev) required to meet the infiltration requirement would therefore be computed as:
Equation 23-125
Rev = (0.5 or I, whichever is greater)* impervious area (square feet)/(12 in/ft) = Cubic Feet
Where:
I = infiltration requirements (in inches).
(b)
Annual Recharge — Water Budget Approach. If the goals of subparagraph (3)(a) cannot be achieved, then 0.5 inches of rainfall shall be infiltrated from all impervious areas, up to an existing site conditions curve number of 81. Above a curve number of 81, Equation 23-125 or the curve in Figure 23-125 should be used to determine the infiltration requirement.
The retention (infiltration) volume (Rev) required again would therefore be computed as:
Rev = (0.5 or I, whichever is greater)* impervious area (square feet)/(12 in/ft) = Cubic Feet
B. 
Soils. A detailed soils evaluation of the project site shall be required where practicable to determine the suitability of infiltration facilities. The evaluation shall be performed by a qualified design professional, and at a minimum, address soil permeability, depth to bedrock and subgrade stability. The general process for designing the infiltration BMP shall be:
(1) 
Analyze hydrologic soil groups as well as natural and man-made features within the site to determine general areas of suitability for infiltration practices. In areas where development on fill material is under consideration, conduct geotechnical investigations of sub-grade stability; infiltration is not permitted to be ruled out without conducting these tests.
(2) 
Provide field tests such as double ring infiltrometer or hydraulic conductivity tests (at the level of the proposed infiltration surface) to determine the appropriate hydraulic conductivity rate. Percolation tests are not recommended for design purposes.
(3) 
Design the infiltration structure for the required retention (Rev) volume based on field determined capacity at the level of the proposed infiltration surface.
(4) 
If on-lot infiltration structures are proposed by the applicant's design professional, it must be demonstrated to the Township of Douglass that the soils are conducive to infiltrate on the lots identified.
C. 
Carbonate Areas. The applicant is required to investigate the ability of all areas on the site which are not underlain by carbonate rock to meet the infiltration requirements of Subsection 2A. If this investigation proves infeasible, infiltration can occur on areas underlain by carbonate rock by following the recommended procedure below in conjunction with Figure 23-B-1 in Appendix 23-1-B. However, the applicant is not required to use infiltration in carbonate areas even if the site falls into the "recommended" range on Figure 23-B-1 in Appendix 23-1-B. If infiltration is not proposed, the calculated infiltration volume (Subsection 2A) shall be treated by an acceptable BMP.
Infiltration BMP loading rate percentages in Figure 23-B-1 in Appendix 23-1-B shall be calculated as follows:
023 Equation.tif
The area tributary to the infiltration BMP shall be weighted as follows:
Area Description
Weighting
All disturbed area to be made impervious
100%
All disturbed areas to be made pervious
50%
All undisturbed impervious areas
100%
All undisturbed pervious areas
0%
Soil thickness is to be measured from the bottom of any proposed infiltration BMP. The effective soil thickness in Figure 23-B-1 in Appendix 23-1-B is the measured soil thickness multiplied by the thickness factor based on soil permeability, as follows:
Permeability Range
Thickness Factor
6.0 to 12.0 inches/hr
0.8
2.0 to 6.0 inches/hr
1.0
1.0 to 2.0 inches/hr
1.4
0.75 to 1.0 inches/hr
1.2
0.5 to 0.75 inches/hr
1.0
The design of all facilities over Karst shall include an evaluation of measures to minimize adverse effects.
D. 
Stormwater Hotspots.
(1) 
Following is a list of examples of designated hotspots. If a site is designated as a hotspot, it has important implications for how stormwater is managed. First and foremost, untreated stormwater runoff from hotspots shall not be allowed to recharge into groundwater where it may contaminate water supplies. Therefore, the Rev requirement shall not be applied to development sites that fit into the hotspot category (the entire WQv must still be treated). Second, a greater level of stormwater treatment shall be considered at hotspot sites to prevent pollutant wash-off after construction. EPA's NPDES stormwater program requires some industrial sites to prepare and implement a stormwater pollution prevention plan.
(a) 
Examples of Hotspots:
1) 
Vehicle salvage yards and recycling facilities.
2) 
Vehicle fueling stations.
3) 
Vehicle service and maintenance facilities.
4) 
Vehicle and equipment cleaning facilities.
5) 
Fleet storage areas (bus, truck, etc.).
6) 
Industrial sites (based on Standard Industrial Codes).
7) 
Marinas (service and maintenance).
8) 
Outdoor liquid container storage.
9) 
Outdoor loading/unloading facilities.
10) 
Public works storage areas.
11) 
Facilities that generate or store hazardous materials.
12) 
Commercial container nursery.
13) 
Other land uses and activities as designated by an appropriate review authority.
(b) 
The following land uses and activities are not normally considered hotspots:
1) 
Residential streets and rural highways.
2) 
Residential development.
3) 
Institutional development.
4) 
Office developments.
5) 
Nonindustrial rooftops.
6) 
Pervious areas, except golf courses and nurseries (which may need an integrated pest management (IPM) plan).
(2) 
While large highways (average daily traffic volume (ADT) greater than 30,000) are not designated as a stormwater hotspot, it is important to ensure that highway stormwater management plans adequately protect groundwater.
E. 
Caution shall be exercised where infiltration is proposed in source water protection areas as defined by the Township of Douglass or water authority.
F. 
Infiltration facilities shall be used in conjunction with other innovative or traditional stormwater control facilities that are found within the Pennsylvania DEP State BMP Manual.
G. 
Caution shall be exercised where salt or chloride (Township salt storage) would be a pollutant since soils do little to filter this pollutant and it may contaminate the groundwater. The qualified design professional shall evaluate the possibility of groundwater contamination from the proposed infiltration facility and perform a hydrogeologic justification study if necessary.
H. 
The infiltration requirement in high quality or exceptional value waters shall be subject to the Department's Chapter 93 antidegradation regulations.
I. 
Dependant upon certain land use or hotspots an impermeable liner will be required in detention basins where the possibility of groundwater contamination exists. A detailed hydrogeologic investigation may be required by the Township of Douglass.
J. 
The Township of Douglass shall require the applicant to provide safeguards against groundwater contamination for land uses that may cause groundwater contamination should there be a mishap or spill.
K. 
For projects that disturb one acre or more, unless otherwise specified in the Zoning Ordinance [Chapter 27], the following setbacks for infiltration facilities shall apply.
(1) 
One hundred feet from water supply wells.
(2) 
Ten feet downslope or 100 feet upslope from building foundations.
(3) 
Fifty feet from septic system drainfields.
(4) 
Fifty feet from a geologic contact with carbonate bedrock, unless a preliminary site investigation is done in the carbonate bedrock to show the absence of special geologic features within 50 feet of the proposed infiltration area.
(5) 
One hundred feet from the property line unless documentation is provided to show all setbacks from wells, foundations and drainfields on the neighboring property will be met.
[Ord. 2008-1, 4/1/2008, § 306]
1. 
The applicant shall comply with the following water quality requirements of this Part 1A:
A. 
Developed areas shall provide adequate storage and treatment facilities necessary to capture and treat stormwater runoff. The infiltration volume computed under § 23-125 may be a component of the water quality volume if the applicant chooses to manage both components in a single facility. If the infiltration volume is less than the water quality volume, the remaining water quality volume may be captured and treated by methods other than infiltration BMPs. The required water quality volume (WQv) is the storage capacity needed to capture and treat a portion of stormwater runoff from the developed areas of the site.
The following calculation formula is to be used to determine the water quality storage volume, (WQv), in acre-feet of storage for the Schuylkill River watershed:
Equation 23-126
WQv =[(P)(Rv)(A)]/12
WQv = Water Quality Volume (acre-feet)
P = 1 inch
A = Total contributing drainage area to the water quality BMP (acres)
Rv = 0.05 + 0.009(I) where I is the percent of the area that is impervious surface ((impervious area/A)*100)
This volume requirement can be accomplished by the permanent volume of a wet basin or the detained volume from other BMPs.
Release of water can begin at the start of the storm (i.e., the invert of the water quality orifice is at the invert of the facility). The design of the facility shall provide for protection from clogging and unwanted sedimentation.
B. 
For areas within defined special protection subwatersheds which include Exceptional Value (EV) and High Quality (HQ) waters, Cold Water Fishery (CWF) the temperature and quality of water and streams shall be maintained.
C. 
To accomplish the above, the applicant shall use innovative or traditional stormwater control facilities that are found within the Pennsylvania DEP State BMP Manual.
D. 
If a perennial or intermittent stream passes through the site, the applicant shall create a stream buffer extending a minimum of 50 feet to either side of the top-of-bank of the channel. The buffer area shall be maintained with appropriate native vegetation (Reference to Appendix H of Pennsylvania Handbook of Best Management Practices for Developing Areas for plant lists). If the applicable rear or side yard setback is less than 50 feet, the buffer width may be reduced to 25% of the setback to a minimum of 10 feet. If an existing buffer is legally prescribed (i.e., deed, covenant, easement, etc.) and it exceeds the requirements of this Part, the existing buffer shall be maintained.
E. 
Evidence of any necessary permit(s) for regulated earth disturbance activities from the appropriate DEP regional office must be provided to the Township of Douglass. The issuance of an NPDES construction permit (or permit coverage under the statewide general permit) satisfies the requirements of paragraph .A.
[Ord. 2008-1, 4/1/2008, § 307]
1. 
In addition to control of the water quality volume, in order to minimize the impact of stormwater runoff on downstream stream bank erosion, the primary requirement is to design a BMP to detain the proposed conditions two-year, twenty-four-hour design storm to the existing conditions one-year peak flow using the SCS Type II distribution. Additionally, provisions shall be made (such as adding a small orifice at the bottom of the outlet structure) so that the proposed conditions one-year storm takes a minimum of 24 hours to drain from the facility from a point where the maximum volume of water from the one-year storm is captured (i.e., the maximum water surface elevation is achieved in the facility). Release of water can begin at the start of the storm (i.e., the invert of the water quality orifice is at the invert of the facility).
2. 
The minimum orifice size in the outlet structure to the BMP shall be a three-inch diameter orifice and a trash rack shall be installed to prevent clogging. On sites with small contributing drainage areas to this BMP that do not provide enough runoff volume to allow a twenty-four-hour attenuation with the three-inch orifice, the calculations shall be submitted showing this condition. Orifice sizes less than three inches can be utilized provided that the design will prevent clogging of the intake.
[Ord. 2008-1, 4/1/2008, § 308]
1. 
The Schuylkill River Watershed has been divided into stormwater management districts as shown on the Management District Map in Appendix 23-1-D.
In addition to the requirements specified in Table 128-1 below, the groundwater recharge (§ 23-125), water quality (§ 23-126), and stream bank erosion control (§ 23-127), requirements shall be implemented.
Standards for managing runoff from each subarea in the Schuylkill River Watershed for the two-year through one-hundred-year design storms are shown in Table 128-1. Development sites located in each of the Districts must control proposed conditions runoff rates to existing conditions runoff rates for the design storms in accord with Table 128-1.
Table 128-1 — Water Quantity Requirements
Management District
Proposed Condition Design Storm
Existing Condition Design Storm
A
2-year
Reduce to
1-year
5-year
5-year
10-year
10-year
25-year
25-year
50-year
50-year
100-year
100-year
B
2-year
Reduce to
1-year
5-year
2-year
10-year
5-year
25-year
10-year
50-year
25-year
100-year
50-year
Equivalent Release Rate
C*
2-year
Reduce to
1-year
100%
5-year
5-year
100%
10-year
10-year
100%
25-year
25-year
100%
50-year
50-year
100%
100-year
100-year
100%
Unclassified Management District**
Proposed Condition Design Storm
Existing Condition Design Storm
Remaining areas of Douglass Township, excluding areas within the Swamp Creek Watershed
2-year
Reduce to
1-year
5-year
5-year
10-year
10-year
25-year
25-year
50-year
50-year
100-year
100-year
*
The minimum performance standard for development sites in District C is that stormwater management controls must be provided to limit the post-development peak rate of stormwater runoff to a rate that is equal to or less than the existing peak rate of stormwater runoff. This minimum performance criteria was set through a policy directive of the Pennsylvania Department of Environmental Protection. However, in the previous development of the Act 167 Plan, this district was originally established as a conditional no-detention district such that development sites which could discharge directly to the main channel of the Schuylkill River and its major tributaries, or indirectly to the main channel through an existing stormwater drainage system (i.e., storm sewer or open channel) could do so without control of the post-development peak rate of runoff.
**
The Unclassified Management District includes all areas of the Township of Douglass shown as unmapped, in "white," on the Watershed Map in Appendix 23-1-D, excluding the Swamp Creek Watershed which is located in the extreme northeast corner of the Township, and is covered by a separately available ordinance for the Swamp Creek Act 167 Plan [Part 2].
All areas, regardless of the release rate, must still meet the requirements of the groundwater recharge criteria (§ 23-125), water quality criteria (§ 23-126), and streambank erosion criteria (§ 23-127).
2. 
General. Proposed condition rates of runoff from any regulated activity shall not exceed the peak release rates of runoff prior to development for the design storms specified on the Stormwater Management District Watershed Map (Appendix 23-1-D) and § 23-128, of this Part.
3. 
District Boundaries. The boundaries of the Stormwater Management Districts are shown on an official map that is available for inspection at the Township office. A copy of the official map at a reduced scale is included in the Appendix 23-1-D. The exact location of the Stormwater Management District boundaries as they apply to a given development site shall be determined by mapping the boundaries using the two-foot topographic contours (or most accurate data required) provided as part of the drainage plan.
4. 
Sites Located in More than One District. For a proposed development site located within two or more stormwater management district category subareas, the peak discharge rate from any subarea shall meet the management district criteria for which the discharge is located, as indicated in § 23-128. The calculated peak discharges shall apply regardless of whether the grading plan changes the drainage area by subarea. An exception to the above may be granted if discharges from multiple subareas recombine in proximity to the discharge site. In this case, peak discharge in any direction shall follow Management District A criteria provided that the overall site discharge meets the management district criteria for which the discharge is located.
5. 
Off-Site Areas. Off-site areas that drain through a proposed development site are not subject to release rate criteria when determining allowable peak runoff rates. However, on-site drainage facilities shall be designed to safely convey off-site flows through the development site.
6. 
Site Areas. Where the site area to be impacted by a proposed development activity differs significantly from the total site area, only the proposed impact area utilizing stormwater management measures shall be subject to the management district criteria. In other words, unimpacted areas bypassing the stormwater management facilities would not be subject to the management district criteria.
[Ord. 2008-1, 4/1/2008, § 309]
1. 
Applicants may select a combination of runoff control techniques that are most suitable to control stormwater runoff from the site. All controls shall be subject to approval of the Township of Douglass. The Township Engineer may request specific information on design and/or operating features of the proposed stormwater controls in order to determine their suitability and adequacy in terms of the standards of this Section.
2. 
The applicant shall consider the effect of the proposed stormwater management techniques on any special soil conditions or geological hazards that may exist on the development site. In the event such conditions are identified on the site, the Township Engineer may require in-depth studies by a geotechnical engineer.
3. 
Basins and Impoundments. Any BMP that is a dam, as defined in 25 Pa. Code, Chapter 105, shall be designed according to the requirements in those regulations. Any stormwater BMP that does not constitute a dam under 25 Pa. Code, Chapter 105, but is designed to store runoff and requires a berm or earthen embankment (i.e., detention basin), shall be designed to comply with the following:
A. 
Basins with earthen embankments shall be designed with an emergency spillway that has capacity and stability to accommodate the one-hundred-year post-development hydrograph, in a manner that will not damage the integrity of the facility and will not create a downstream hazard emergency spillway design shall assume that all other basin outlets are nonfunctional. Where practical, the emergency spillway shall be constructed in undisturbed ground, and locations in fill should be avoided. Regardless of location, appropriate stabilization measures shall be provided.
B. 
The height of the embankment shall be designed to provide a minimum 1.0 foot of freeboard above the maximum elevation computed when the one-hundred-year peak post-development flow passes through the emergency spillway. Embankment heights shall not exceed 15 feet, unless approved by the Township of Douglass.
C. 
The minimum top width of earthen embankments shall be equal to three-fourths of the embankment height, but in no case shall the top width be less than eight feet.
D. 
Interior and exterior embankment side slopes shall not be greater than three horizontal to one vertical.
E. 
All pipes, conduits, etc., passing through basin embankments shall have properly spaced concrete anti-seep collars. Minimum collar projection beyond the pipe shall be two feet, and maximum collar spacing is 14 times the projection. The joint between collar and pipe shall be watertight.
F. 
A key trench of relatively impervious material shall be provided within all basin embankments. The key trench shall be at least two feet deep, or extend down to stable subgrade, whichever is deeper. Minimum bottom width for key trench shall be four feet. Maximum side slopes for the key trench shall be one horizontal to one vertical. A compacted impervious core at least three feet wide at the top, having maximum side slopes of one horizontal to one vertical shall extend for the full length of the embankment, and the top elevation shall be set at the ten-year design water surface elevation.
G. 
All basins shall be structurally sound and shall be constructed of durable materials. The completed structure and the foundation of all basins shall be stable under all probable conditions of operation. Embankments shall be placed in maximum eight-inch lifts to a minimum of 95% of maximum dry density, as established by ASTM D-1557. Compaction test results shall be provided to the Township of Douglass upon request. Embankments shall be constructed six inches above design elevations to allow for settlement.
H. 
All basins not including groundwater recharge and/or water quality storage shall include an outlet structure to permit draining the basin to a completely dry condition within 24 hours following the end of the design rainfall.
I. 
All discharge control devices with appurtenances (except discharge pipes) shall be made of reinforced concrete and stainless or hot dip galvanized steel. Bolts/fasteners and any orifice plates are to be stainless or galvanized steel. Outlet barrels/pipes shall have a minimum diameter of 15 inches and shall be made of reinforced concrete pipe with watertight joints, or approved equivalent. Where installation conditions merit, structural calculations that address the actual design requirements will be required.
J. 
All basins employing small orifices (i.e., less than six inches diameter or equivalent area), shall be provided with an apron of concrete or similar durable material which abuts the orifice invert and extends a minimum of 18 inches in all directions from the orifice, to prevent potential blockage by vegetative growth or debris, and to allow for easy cleaning of the area approaching the orifice. Appropriate trash racks are required for all orifice openings.
K. 
Low flow channels shall be provided from each water carrying facility to the outlet structure for all basins that do not include groundwater recharge and/or water quality storage. Low flow channels shall be 1% minimum slope and shall be designed to enable ease of maintenance. All basins that do include groundwater recharge and/or water quality storage shall not be required to have a low flow channel.
L. 
Minimum slope within a basin that does not include groundwater recharge and/or water quality storage shall be 2% positive grade to the low flow channel.
M. 
Design storms for the computation of retention basin volumes shall be based upon a twenty-four-hour storm with one-hundred-year return period (SCS Type II storm).
N. 
The effect on downstream areas if the basin embankment fails shall be considered in the design of all basins. The basin shall be designed to minimize the potential damage caused by such failure of the embankment.
O. 
All structures (detention basins, cisterns, etc.), other than those used for groundwater recharge volume and water quality volume, must completely drain within 24 hours after the end of the design storm.
P. 
Soils used for the construction of basins shall have low erodibility factors ("K" factors).
Q. 
Minimum floor elevations for all structures that would be affected by a basin, other temporary impoundments, or open conveyance systems where ponding may occur shall be two feet above the one-hundred-year water surface. If basement or underground facilities are proposed, detailed calculations addressing the effects of stormwater ponding on the structure and water-proofing and/or flood-proofing design information shall be submitted for approval.
4. 
Stormwater Collection and Conveyance Systems. Gutters, inlets, pipes, conduits, swales, ditches and any other means for collecting and/or conveying stormwater shall be designed to comply with the following:
A. 
All storm sewer pipes, culverts and bridges (excluding detention and retention basin outfall structures), gutters and swales conveying water originating only from within the boundaries of the development site shall be designed for a twenty-five-year storm event. All storm sewer pipes, culverts and bridges (excluding detention and retention basin outfall structures) conveying water originating from off site shall be designed for a fifty-year storm event. Facilities that convey runoff to stormwater management facilities (e.g., detention basins, etc.) shall be designed for the one-hundred-year storm event, unless adequate alternate means for conveying one-hundred-year flow to the facilities are provided. Drainage easements having widths no less than 20 feet shall be provided to contain and convey the one-hundred-year frequency flood throughout the development site. Easements shall begin at the furthest upstream property line of the proposed development site in a watershed.
B. 
Water obstructions shall convey runoff from the twenty-five-year design storm with a minimum of 2.0 feet of freeboard measured below the lowest point along the top of the roadway, without damage to the drainage structure or the roadway, unless more restrictive local, state and/or federal regulations apply. A concentrated discharge of stormwater to an adjacent property shall be within an existing watercourse or otherwise an easement and appropriate agreements shall be required.
C. 
Storm sewer pipes other than those used as roof drains, detention basin underdrains, and street subbase underdrains, shall have a minimum diameter of 15 inches and be either Class III reinforced concrete pipe (RCP) or smooth-lined corrugated high-density polyethylene pipe (HDPE). Corrugated metal pipe is not permitted. HDPE pipe joints shall be silt-tight at a minimum (e.g., ADS N-12 ST/IB, or equal), and RCP joints shall have pre-lubed O-ring gaskets. Watertight specification is required in areas of carbonate geology and elsewhere as may be specified by the Township of Douglass. Where installation conditions merit (e.g., deep fills) structural calculations that address the actual design requirements will be required.
D. 
Storm sewer pipes and culverts shall be installed on sufficient slopes to provide a minimum velocity of three feet per second when flowing full.
E. 
Storm sewers shall be placed within in the cartway of curbed streets and parallel to the road shoulders of streets without curbs. At curbed street intersections, inlets shall be placed on the tangent and not on the curved portion of the curbing. Storm sewer crossings of streets shall be perpendicular to the street center line to the maximum extent practicable.
F. 
Storm facilities not located within a public right-of-way shall be contained in and centered within an easement not less than 20 feet wide. Easements shall follow property boundaries where possible.
G. 
Manning "n" values used for design of pipes and culverts shall be in accordance with generally accepted engineering practice. Adequate documentation shall be provided in support of the chosen values.
H. 
All storm sewer pipe and culverts shall have a minimum cover of 18 inches. Embedment for all storm sewer pipe and culverts shall consist of AASHTO No. 8 (1B) aggregate from a minimum of six inches of bedding beneath the pipe, to a minimum of 12 inches over the pipe. Aggregate requirements for street construction shall take precedence over the 1B specification, but in no case shall total aggregate cover over the pipe be less than 12 inches. Compaction shall be in conformance with manufacturer's specifications. Select backfill shall complete the trench to pavement subgrade or topsoil layer in grassed areas.
I. 
Curves, tees, elbows and wyes are not permitted in pipes other than those used as roof drains, detention basin under drains, and street subbase underdrains. Manholes or inlets are required to facilitate such configurations.
J. 
Manholes and inlets shall not be spaced more than 400 feet apart for pipes with diameters of 24 inches and less, and not more than 500 feet apart for pipes of greater diameter. Ladder rungs shall be placed in manholes and inlets with depths exceeding five feet.
K. 
When there is a change in the pipe size in a manhole or inlet, the elevations of the top of the pipes shall be the same, or the smaller pipe(s) higher. A minimum drop of 0.1 foot shall be provided from the inlet invert elevation(s) to the outlet invert elevation.
L. 
Manholes, inlets, headwalls, endwalls and end sections proposed for dedication or located along streets or subject to vehicular traffic, shall conform to the requirements of PennDOT, or to specifications as otherwise modified by the Township of Douglass. Manhole covers shall have the word "STORM" cast clearly on the lid.
M. 
Inlets along curbed streets shall be spaced to limit depth along the curb to a maximum of three inches during a ten-year storm. Inlet capacities and by-pass calculations shall be determined by PennDOT design techniques.
N. 
Pipe underdrains and/or pavement base drains shall be provided in areas known or otherwise documented to have a seasonal high water table, and as directed by the Township of Douglass Engineer.
O. 
Appropriate headwalls, endwalls or end sections shall be used where stormwater runoff enters or leaves the storm sewer horizontally from a natural or man-made channel. Such facilities shall conform to the requirements of PennDOT, or to specifications as otherwise modified by the Township of Douglass.
P. 
Adequate erosion and sediment control protection shall be provided along all open channels, and at all points of discharge.
Q. 
Stormwater roof drains, sump pumps, and pipes shall not directly discharge water into a street right-of-way or discharge into a sanitary sewer or storm sewer.
R. 
All existing and natural watercourses, channels, drainage systems, wetlands and areas of surface water concentration shall be maintained in their existing condition unless an alteration is approved by the Township of Douglass and any other necessary approving body.
S. 
Flow velocities from any storm sewer may not result in erosion of the receiving channel.
T. 
Energy dissipaters shall be placed at the outlets of all storm sewer pipes, culverts, and bridges where flow velocities exceed maximum permitted channel velocities as specified in the Pennsylvania DEP Erosion and Sediment Pollution Control Manual, as amended.
U. 
The following conditions shall be met for all swales:
(1) 
Capacities and velocities shall be computed using the Manning equation Stabilization (i.e., linings, etc.) shall be as specified in the Pennsylvania DEP Erosion and Sediment Pollution Control Manual, as amended.
(2) 
All vegetated swales shall have a minimum slope of 1% unless approved by the Township of Douglass.
(3) 
"N" factors shall be based upon accepted engineering design practices as approved by the Township of Douglass.
(4) 
All swales shall be designed to concentrate low flows to minimize siltation and meandering.
[Ord. 2008-1, 4/1/2008, § 310]
1. 
Stormwater runoff from all development sites with a drainage area of greater than 200 acres shall be calculated using a generally accepted calculation technique that is based on the NRCS Soil Cover Complex Method. Table 23-130 summarizes acceptable computation methods and the method selected by the design professional shall be based on the individual limitations and suitability of each method for a particular site. The Township of Douglass may allow the use of the Rational Method to estimate peak discharges from drainage areas that contain less than 200 acres. The Soil Cover Complex Method shall be used for drainage areas greater than 200 acres.
Table 23-130
Acceptable Computation Methodologies for Stormwater Management Plans
Method
Method Developed by
Applicability
TR-20 (or commercial computer package based on TR-20)
USDA NRCS
Applicable where use of full hydrology computer model is desirable or necessary.
TR-55 (or commercial computer package based on TR-55)
USDA NRCS
Applicable for land development plans within limitations described in TR-55.
HEC-1/HEC-HMS
US Army Corps of Engineers
Applicable where use of full hydrologic computer model is desirable or necessary.
PSRM
Penn State University
Applicable where use of a hydrologic computer model is desirable or necessary; simpler than TR-20 or HEC-1.
Rational Method (or commercial computer package based on Rational Method)
Emil Kuichling (1889)
For sites less than 200 acres and with time of concentration less than 60 minutes (tc<60min), or as approved by the Township of Douglass.
Other Methods
Varies
Other computation methodologies approved by the Township of Douglass.
Note:
*
Successors to the above methods are also acceptable. These successors include WINNTR55 for TR55 and WINTR20 for TR20 and SWMM.
2. 
All calculations consistent with this Part using the Soil Cover Complex Method shall use the appropriate design rainfall depths for the various return period storms according to NOAA's National Weather Service Precipitation Frequency Data Server (PFDS), or NOAA Atlas 14. If a hydrologic computer model such as PSRM or HEC-1/HEC-HMS is used for stormwater runoff calculations, then the duration of rainfall shall be 24 hours.
3. 
For the purposes of existing conditions flow rate determination, undeveloped land shall be considered as "meadow" in good condition, unless the natural ground cover generates a lower curve number or Rational "C" value (i.e., forest), as listed in Tables 23-1-B-1 or 23-1-B-2 in Appendix 23-1-B of this Part.
4. 
All calculations using the Rational Method shall use rainfall intensities consistent with appropriate times-of-concentration for overland flow and return periods from NOAA's National Weather Service Precipitation Frequency Data Server (PFDS), or NOAA Atlas 14.
5. 
Times of concentration shall be calculated using the methodology presented in Chapter 3 of Urban Hydrology for Small Watersheds, NRCS, TR-55 (as amended or replaced from time to time by NRCS). Times of concentration for channel and pipe flow shall be computed using Manning's equation.
6. 
Runoff curve numbers (CN) for both existing and proposed conditions to be used in the Soil Cover Complex Method shall be obtained from Table 23-1-B-1 in Appendix 23-1-B of this Part.
7. 
Runoff coefficients (C) for both existing and proposed conditions for use in the Rational Method shall be obtained from Table 23-1-B-2 in Appendix 23-1-B of this Part.
8. 
Where uniform flow is anticipated, the Manning equation shall be used for hydraulic computations, and to determine the capacity of open channels, pipes, and storm sewers. Values for Manning's roughness coefficient (n) shall be consistent with Table 23-1-B-3 in Appendix 23-1-B of the Part. Full flow shall be assumed for closed conduits.
9. 
Outlet structures for stormwater management facilities shall be designed to meet the performance standards of this Part using any generally accepted hydraulic analysis technique or method.
10. 
The design of any stormwater detention facilities intended to meet the performance standards of this Part shall be verified by routing the design storm hydrograph through these facilities using the Storage-Indication Method. For drainage areas greater than 200 acres in size, the design storm hydrograph shall be computed using a calculation method that produces a full hydrograph (i.e., TR-20, TR-55, HEC-1, PSRM). The Township of Douglass may approve the use of any generally accepted full hydrograph approximation technique that shall use a total runoff volume that is consistent with the volume from a method that produces a full hydrograph.
[Ord. 2008-1, 4/1/2008, § 311]
1. 
All wet basin designs shall incorporate biologic minimization controls consistent with the West Nile guidance found in Appendix 23-1-F.
2. 
Any facilities that constitute water obstructions (e.g., culverts, bridges, outfalls, or stream enclosures), water encroachments, and any work involving wetlands governed by Pennsylvania DEP 25 Pa. Code, Chapter 105, regulations (as amended or replaced from time to time by Pennsylvania DEP), are subject to Pennsylvania DEP 25 Pa. Code, Chapter 105, regulations.
3. 
Adequate erosion protection shall be provided along all open channels, and at all points of discharge (DEP Erosion and Erosion, Sediment and Pollution Control Manual).
4. 
The Township of Douglass reserves the right to disapprove any design that would result in the construction in or continuation of a stormwater problem area.
5. 
No stormwater detention facility shall be placed within 50 feet of a special geologic feature. No stormwater conveyance facility shall be constructed within 50 feet of a special geologic feature, unless it is constructed of durable pipe utilizing watertight joints.
6. 
Stormwater controls, conveyance facilities and BMPs are subject to additional design and construction criteria as may be included in a separate stormwater specifications document.