The developer shall install, at no expense to Clinton Township, all the improvements that he and the Planning Commission agree upon, in accordance with the standards outlined in Article
IV and with the requirements of this article.
Storm sewers, culverts, sumps, and related installations shall
be provided to permit the unimpeded flow of natural watercourses,
to ensure the drainage of all low points along the lines of streets
and to intercept stormwater runoff along streets at intervals reasonably
related to the extent and grade of the area drained.
A. In designing the drainage system, the developer shall adhere to the requirements of Chapter
127, Stormwater Management.
[Amended 7-13-2020 by Ord. No. 2020-01]
B. Areas that contain habitual swamp conditions, have no drainage outlet
or harbor insects or other disease carrying or producing agents shall
be identified even though not otherwise to be developed.
C. Where storm drainage must cross a property adjoining the developer's
plan, he shall secure approval, in writing, from the owner or owners
of the affected property for passage of stormwater.
D. The minimum diameter of any storm drainpipe shall be 15 inches.
Street name signs shall be placed at all street intersections
with the development and at the intersection of existing streets and
streets entering the development. The Clinton Township Board of Supervisors
shall approve their design and location.
Upon completion of the required improvements, plans and profiles
of the improvements in the subdivision or land development as constructed
(commonly known as "as-built" plans) shall be filed with the municipality
in which the subdivision or land development is located.