No person, firm, partnership or corporation shall construct any new
street or storm sewer in the Township unless and until a building
permit for new street or storm sewer construction has been obtained.
No permit shall be issued until the final plans for the subdivision
or land development within which such construction is to take place
have been submitted to the Township and the required plan and profiles
for the same have been reviewed and approved by the Township Engineer.
The approval granted for such construction shall be valid for a period
of three years, after which time the applicant shall be required to
resubmit plan and profiles for any portions of street or storm sewer
not constructed within the three-year period in accordance with ordinances
in effect at the time of resubmission.
For the initial 500 linear feet of roadway or 1,000 linear feet of
storm sewer or fraction thereof: as set forth from time to time by
resolution of the Board of Supervisors.
For each additional 100 linear feet of roadway or 200 linear feet
of storm sewer or fraction thereof: as set forth from time to time
by resolution of the Board of Supervisors.