A. 
General. No construction shall be undertaken unless an erosion and sediment control plan which explains and illustrates the measures which will be taken to control erosion and sediment transport is submitted to and approved by the Town of Old Lyme. Plans shall be prepared in accordance with the requirements and standards outlined in the most current edition of the "Connecticut Guidelines for Soil Erosion and Sediment Control."
B. 
Stormwater general permits. When a project requires a Connecticut Department of Environmental Protection Agency general permit for the discharge of stormwater and dewatering wastewaters associated with construction activities, copies of the registration form and stormwater pollution control plan submitted to the state shall also be submitted to the Town of Old Lyme prior to the start of any activity.
A. 
General. The practices and measures included in the approved erosion and sediment control plan shall be implemented during the entire construction period and maintained until adequate permanent vegetation is established. Erosion control measures shall be supplemented as field conditions require, or as directed by the Town of Old Lyme.
B. 
Contact person. Prior to the start of any roadway construction, the name, address and day/night telephone numbers of the person designated by the owner to be responsible for the implementation of erosion and sediment control practices and measures shall be provided to the Board of Selectmen, the Town Engineer, and the Director of Public Works.
C. 
Final site cleanup. Following the permanent stabilization of all disturbed areas, all remaining temporary erosion control measures that are not biodegradable, as well as all accumulated sediments, shall be removed from the site and disposed of in a lawful manner. In addition, all accumulated sediments remaining in permanent facilities such as plunge pools, drainage channels, detention areas and catch basins shall be removed and disposed of in a lawful manner. The removal of temporary erosion control measures and accumulated sediments shall be conducted in a manner so as not to disturb existing permanent vegetation. All exposed areas remaining after the removal of erosion control measures shall be immediately seeded and mulched.