Exciting enhancements are coming soon to eCode360! Learn more 🡪
Township of Winslow, NJ
Camden County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
A. 
Use groups.
(1)
B, H, I-1, I-2, I-3, I-4, M, R-1, R-2, R-3, R-4, R-5, U
Volume x 0.036 (in cubic feet)
(2)
A-1, A-2, A-3, A-4, A-5, E
F-1, F-2, F-3, S-1, S-2
Volume x .027 (in cubic feet)
Up to 1,000,000 cubic feet: $0.0225 per cubic foot. All volume in excess of 1,000,000 cubic feet: $0.010 per cubic foot
(3)
Farm use buildings exclusively used for food, sheltering and livestock
Volume x .0010 (in cubic feet)
(4)
Minimum fee per structure on individual lots (Groups A, B, R)
$200.
B. 
Renovations, alterations and repairs.
(1)
Estimated cost to $50,000.
$35. per $1,000. of estimated cost or fraction thereof
(2)
$50,001. to $100,000.
$28. per $1,000. of estimated cost or fraction thereof
(3)
$100,001. or over
$24. per $1,000. of estimated cost or fraction thereof
(4)
Application fee for the review by the Zoning Officer.
$25.
(5)
Fences, T.V. antennas, satellite dishes, decks, and any other miscellaneous devices.
$35. per $1,000. of estimated cost or fraction thereof
(6)
Roofing and Siding.
Residential
$64.
Commercial
$20. per $1,000. of estimated cost or fraction thereof
C. 
Demolition permits.
(1)
Residential building
$150.
(2)
Commercial building
$300.
D. 
Removal permits.
Removal of building from one (1) location to another, or to a new location on same lot
$500.
E. 
Solar photovoltaic system.
(1)
Use groups R-3, R-4, R-5
$200.
(2)
All other use groups
$500.
F. 
Sign permits.
Construction of sign (calculated on one side only of double-faced signs)
$4.20 per square foot up to 100 square feet
$3.50 per square foot 100 to 350 square feet
$2.50 per square foot 350 square feet & over
$50. minimum
G. 
Asbestos removal.
(1)
Removal of asbestos
$25. per $1,000. of estimated cost or fraction thereof
(2)
Certificate of occupancy for asbestos removal
$14.
H. 
Swimming pools.
(1)
Above-ground pool
$156.
(2)
In-ground pool
$215.
I. 
Foundation permits.
Alteration
$35. per $1,000. of estimated cost or fraction thereof
J. 
Retaining wall.
(1)
Class 3
Less than 550 square feet
$75. per wall
Over 550 square feet
$150. per wall
(2)
Non-Class 3
Less than 550 square feet
$100. per wall
Over 550 square feet
$200. per wall
(3)
Retaining wall based on alteration
$35. per $1,000. of estimated cost or fraction thereof
K. 
Miscellaneous permits.
(1)
Permit for sales trailer
$150.
(2)
Permit for construction trailer
$150.
(3)
Premanufactured construction, industrialized/modular buildings
$15. per $1,000. of estimated cost or fraction thereof
L. 
Plan review. Plan review fees shall be calculated at twenty percent (20%) of the fee charged for the construction permit thereof.
M. 
Variation fees. Fees for review generated by variation in actual construction versus the drawings on which a construction permit was issued shall be as follows:
(1)
Class I buildings
$300
(2)
Class II buildings
$200
(3)
Class III buildings
$100
N. 
State training fees. All new construction shall be assessed a surcharge of $0.00371 per cubic foot in accordance with the New Jersey Uniform Construction Code. The surcharge for all other construction, including alterations, renovations and repairs, shall be $1.90 per $1,000. of value of construction.
[Amended 12-18-18 by Ord. No. O.2018-028]
O. 
Building permits, generally. The minimum fee for any building permit shall be $58. If more than one (1) subcode is involved, the minimum construction permit fee also will apply.
P. 
Construction permits, generally. If more than one (1) subcode is involved, the minimum fee for a construction permit shall be $58. Unless otherwise stated in this chapter, the minimum fee for each subcode permit shall be $58.
A.
Fixtures and stacks. Sinks, urinals, water closets, bathtubs, shower stalls, laundry tubs, floor drains, drinking fountains, dishwashers, garbage disposals, clothes washers, hot water heaters and similar devices, and/or any miscellaneous items not herein mentioned specifically belonging to this class
$15.
B.
Special devices. Grease traps, oil separators, water-cooled air conditioning units, pumps, boilers, furnaces, sewer ejectors, backflow devices, water softeners, commercial dishwashers, solar systems and interceptors
$82.
C.
Utility connections.
(1) Water connections
$82.
(2) Sewer connections
$82.
D.
Fire sprinklers – fire suppression
$56.
E.
Plumbing fees, generally. The minimum fee for any plumbing subcode permit shall be $58. If more than one (1) subcode is involved, the minimum construction permit fee also will apply.
A.
Fixtures and devices.
(1)
Lighting outlets, wall switches, fluorescent fixtures, receptacles and similar fixtures, and motors or devices less than 1 h.p. or 1 kW:
(a) One (1)—twenty-five (25)
$49.
(b) Twenty-six (26)—seventy-five (75)
$15.
(2)
Electrical ranges, heaters, hot water heaters, dryers, dishwashers, garbage disposals, air-conditioning units, water pumps and similar devices—each outlet of a single unit of 20 kW or less
$58.
(3)
Each additional outlet for devices of 20 kW or more
$30.
B.
Baseboard heaters.
(1)
One (1) - five (5)
$46.
(2)
Six (6) - ten (10)
$36.
(3)
Eleven (11) or more
$10.
C.
Furnaces and welders (see motor schedule).
D.
Motors or generators.
(1)
Single unit or group not exceeding five (5) motors whose total capacity does not exceed 1 h.p. or 1 kW
$15.
(2)
1 h.p. to 20 h.p. or 20 kW
$59.
(3)
20 h.p. or 20 kW to 75 h.p. or 75 kW
$135.
(4)
Over 75 h.p. or 75 kW
$579.
(5)
Transformers
$579.
E.
Service and meter equipment (new, relocated, replaced or added to original installation).
(1)
Up to 225 amp service
$64.
(2)
226 to 1000 amp service
$176.
(3)
Greater than 1000 amp service
$615.
F.
Swimming pools.
(1)
Above-ground
$75.
(2)
In-ground
$175.
(3)
Fence (new)
$58.
G.
Protective signaling system.
Smoke alarms, smoke detectors, heat detectors, alarm bells and lights, pull stations, exit lights, emergency lights and any other similar devices:
(1)
First twenty (20) devices or fraction thereof
$45.
(2)
Each additional five (5) devices or fraction thereof
$15.
H.
Telephone jack wiring.
(1)
For the first five (5) jacks
$15.
(2)
Over five (5) jacks
$5.
I.
Burglar alarm system.
$49.
J.
Electrical signs.
$64.
K.
Solar photovoltaic systems.
(1)
One (1) to fifty (50) kW
$115.
(2)
Fifty-one (51) to one hundred (100) kW
$215.
(3)
Greater than one hundred (100) kW
$576.
L.
Electrical permits, generally.
The minimum fee for any electrical permit shall be $58. If more than one (1) subcode is involved, the minimum construction permit fee also will apply.
A.
Fireplaces.
$68.
B.
Wood burning stoves.
$68.
C.
Gas and/or oil heaters.
$68.
D.
Tank installation or removal.
(1)
One (1) to one thousand (1,000) gallons
$139.
(2)
Over one thousand (1,000) gallons
$189.
E.
Pre-engineered system (commercial).
$129.
F.
Commercial kitchen exhaust system.
$134.
G.
Standpipes.
$299.
H.
Fire protection systems.
(1)
One (1) to twelve (12)
$89.
(2)
Thirteen (13) to one hundred (100)
$164.
(3)
One hundred one (101) to two hundred (200) (Commercial)
$289.
(4)
Two hundred one (201) to four hundred (400) (Commercial)
$795.
(5)
Four hundred one (401) to one thousand (1,000) (Commercial)
$1,049.
(6)
Over one thousand (1,000) (Commercial)
$1,475.
I.
Fire alarm devices.
Smoke alarms, smoke detectors, heat detectors, alarm bells and lights, pull stations, exit lights, emergency lights and any other similar devices:
(a)
One (1) to twelve (12)
$49.
(b)
Thirteen (13) to twenty (20)
$58.
(c)
Twenty-one (21) to one hundred (100)
$135.
(d)
One hundred one (101) to two hundred (200)
$193.
(e)
Two hundred one (201) to one thousand (1,000)
$640.
(f)
Over one thousand (1,000)
$798.
J.
Fire subcode fees, generally.
The minimum fee for any fire subcode permit shall be $58. If more than one (1) subcode is involved, the minimum construction permit fee also will apply.
[Added 7-17-18 by Ord. No. 2018-017]
A.
The fees in this Section 113-5 are in lieu of plumbing fees when the mechanical subcode is used and for replacement work.
B.
Use groups R-3 or R-5 only.
C.
Fees.
(1)
Water heater
$65.00
(2)
Steam or hot water boiler, furnace
$85.00
(3)
Air conditioning only
$50.00
(4)
Air conditioning when replaced with a furnace
no fee
(5)
Hydronic piping Hydronic piping for geothermal, baseboard, floor heating, etc. (includes hydrostatic pressure test where applicable)
$35.00
(6)
Fireplaces
$50.00
(7)
Generator or pool heater
$50.00
(8)
Fuel oil tank up to 1000 gallons
$139.00
(9)
Fuel oil tank 1000 to 2000 gallons
$189.00
(10)
Gas, oil or LPG systems (including rearrangement, extension or new).
(a) Use Group R-3 or R-5 piping
$65.00
(b) All other use group piping
$95.00