Improvement guarantees shall be provided prior to issuance of
a zoning permit, prior to the recording of final subdivision plats
or as a condition of final site plan approval to ensure the Township
of the proper installation and maintenance of on-site and on-tract
improvements.
[Ord. No. 00-04 § XI;
amended 4-3-2019 by Ord. No. 19-01]
a.
Before the filing of final subdivision plats, or the recording of
a minor subdivision deed, or as a condition of final site plan approval
or as a condition to the issuance of a zoning permit pursuant to N.J.S.A.
40:55D-65, the developer shall have installed under the inspection
of the Township Engineer, certain improvements required (sometimes
hereafter referred to as "bonded" or "required improvement"), unless
the applicant has posted and the Township Committee has accepted a
performance guarantee providing for such installation of only those
improvements required by an approval, a developer’s agreement
or ordinance to be dedicated to the Township or other public entity,
and that have not yet been installed. The amount of the guarantee
shall be determined by the Township Engineer, not to exceed 120% of
the estimated cost of constructing the improvements including: streets,
curbs, pavement, gutters, sidewalks, streetlighting, shade trees,
surveyors monuments as shown on the final map and required by the
"Map Filing Law,"Law,"or N.J.S.A. 46:26B-1 through N.J.S.A. 46:26B-8,
community septic systems, drainage structures, public improvements
of open space, traffic street signage, pavement markings, and, if
applicable, sanitary sewers and any grading necessitated by the preceding
improvements; as well as privately owned perimeter buffer landscaping
as required by ordinance or imposed as a condition of approval for
each section or phase of the development. The Township Engineer shall
prepare an itemized cost estimate of the improvements covered by the
performance guarantee, which itemized cost estimate shall be appended
to each performance guarantee posted by the obligor.
b.
At
the developer's option, a separate performance guarantee may be posted
for the privately owned perimeter buffer landscaping.
c.
In
the event that the developer seeks a temporary certificate of occupancy
for a development, unit, lot, building or phase of development, as
a condition of the issuance thereof, the developer shall furnish a
separate temporary certificate of occupancy guarantee in an amount
equal to 120% of the cost of installation of only those improvements
or items which remain to be completed or installed under the terms
of the temporary certificate of occupancy and which are required to
be installed or completed as a condition precedent to the issuance
of the permanent certificate of occupancy, and which are not covered
by an existing performance guarantee. The scope and amount of the
temporary certificate of occupancy shall be determined by the Township
Engineer and accepted by resolution from the governing body. At no
time shall more than one guarantee be held by the Township for the
same improvement. The temporary certificate of occupancy guarantee
shall be released by the governing body upon the issuance of a permanent
certificate of occupancy with regard to the unit, lot, building or
phase as to which the temporary certificate of occupancy guarantee
relates.
d.
In addition to the performance guarantee pursuant to Subsection a above the developer shall also post a safety and stabilization guarantee in favor of the Township to be available solely for the purpose of returning property that has been disturbed to a safe and stable condition or otherwise implementing measures to protect the public from access to an unsafe or unstable condition, only in the circumstance that:
1.
Site
disturbance has commenced and, thereafter, all work on the development
has ceased for a period of at least 60 consecutive days following
such commencement for reasons other than force majeure; and
2.
Work
has not recommenced within 30 days following the provision of written
notice by the Township to the developer of the Township's intent to
claim payment under the guarantee. The Township shall not serve notice
of its intent to claim payment under a safety and stabilization guarantee
until a period of at least 60 days has elapsed during which all work
on the development has ceased for reason other than force majeure.
The Township shall provide written notice to a developer by certified
mail or other form of delivery providing proof of receipt.
e.
The
amount of the safety and stabilization guarantee for a development
with bonded improvements in the amount not exceeding $100,000 shall
be $5,000. The amount of the safety and stabilization guarantee for
a development with bonded improvements exceeding $100,000 shall be
calculated as a percentage of the bonded improvements costs of the
development or phase of development as follows:
f.
At
the developer's option, the safety and stabilization guarantee may
be provided as a separate guarantee or as a line item in the performance
guarantee.
[Ord. No. 00-04 § XI; Ord. No. 01-30 § II; Ord. No. 2014-07]
Performance guarantees shall be submitted in the following form:
a.
A minimum of 10% of the performance guarantee must be posted in cash.
b.
The remaining 90% of the performance guarantee amount shall be posted
in cash, certified check, irrevocable standby letter of credit or
surety bond in accordance with N.J.S.A. 40:55D-53a and N.J.A.C. 5:39.
c.
All guarantees shall provide for construction of the required improvements within the time provided in Section 35-10-5 hereof. This time period may be extended by the Township Committee, in the form of a resolution granting such extension provided the Township Agency has, if necessary, extended the period of protection pursuant to N.J.S.A. 40:55D-52a. As a condition of this extension the guarantee amount may be adjusted to 120% of the estimated cost to construct the improvements at that time and additional appropriate inspection fees shall be paid.
[Amended 4-3-2019 by Ord. No. 19-01]
d.
All performance guarantees shall remain in effect until formally
released by the Township Committee by a resolution and receipt of
an approved maintenance guarantee as required consistent with N.J.S.A.
40:55D-53.
[Amended 4-3-2019 by Ord. No. 19-01]
e.
If the property or any part of same is sold, or otherwise conveyed
to a successor developer prior to the completion and acceptance of
all improvements, an Assignment of Developer's Agreement, and new
performance or maintenance guarantees shall be required from the new
owner or successor developer. Upon the transfer of ownership of property
that is the subject of a construction permit, and prior to beginning
or continuing work authorized by the construction permit, the new
owner or successor developer shall file with the building department
an application for a permit update to notify the building department
of the name and address of the new owner or successor developer and
of all other changes to information previously submitted to the building
department. The building department shall not approve the application
for a permit update until it receives notification from the governing
body or its designee that the new owner or successor developer has
furnished adequate replacement performance or maintenance guarantees
and Assignment of Developer's Agreement.
[Ord. No. 00-04 § XI]
a.
All site improvements shall be inspected during the time of their installation under the supervision of the Township Engineer. Prior to the start of construction of any improvements, the applicant shall deposit by cash or certified check with the Township Clerk the applicable inspection fee required by Subsections g and h hereof. In addition, a preconstruction meeting shall be held with the Township Engineer, the developer, site superintendent, and all prime contractors, as required.
[Amended 4-3-2019 by Ord. No. 19-01]
b.
In no case shall installation of underground facilities or any paving
work be conducted without permission from the Township Engineer.
c.
The Engineer's office shall be notified two working days prior to
commencement of each of the following phases of construction so that
the Engineer or his designated representative may be present to inspect
the work.
1.
Site clearing and grading.
2.
Road subgrade.
3.
Curb and gutter forms.
4.
Curbs and gutters.
5.
Road paving.
6.
Sidewalk forms and driveway apron.
7.
Sidewalks and driveway aprons.
8.
Drainage pipes and other stormwater management construction.
9.
Street name signs.
10.
Survey monuments.
11.
Water distribution systems.
12.
Detention and/or retention basins.
13.
Final grading, topsoil, seeding, planting, shade trees.
14.
Traffic signage and stripping.
d.
Any improvement installed contrary to the plan or plat approval by
the Township or Township design standard shall constitute just cause
to void the Township approval.
e.
Any improvements installed without notice for inspection (as determined
by the Township Engineer) shall constitute just cause for:
f.
Inspection by the Township of the installation of improvements and
utilities shall not operate to subject the Township to liability for
claims, suits or liability of any kind that may at any time arise
because of defects or negligence during construction or at any time
thereafter; it being recognized that the responsibility to maintain
safe conditions at all times during construction and to provide proper
utilities and improvements is upon the owners and his contractor,
if any.
g.
Inspection Fees. The obligor shall reimburse the Township forreasonable inspection fees paid to the Township Engineer for the foregoing inspection of improvements; which fees shall not exceed the sum of the amount set forth in Subsection g1 and 2 of this subsection. The Township may require of the developer a deposit for the inspection fees in an amount: (1) not to exceed, except for extraordinary circumstances, the greater of $500 or 5% of the cost of improvements estimated pursuant to N.J.S.A. 40:55D-53.4 of the Municipal Land Use Law and (2) not to exceed 5% of the cost of private site improvements that are not subject to a performance guarantee under § 35-13-2.1. For those developments for which the reasonably anticipated fees total less than $10,000, fees may, at the option of the developer, be paid in two installments. The initial amount deposited in escrow by a developer shall be 50% of the reasonably anticipated fees. When the balance on deposit drops to 10% of the reasonably anticipated fees because the amount deposited by the developer has been reduced by the amount paid to the Township Engineer for inspections, the developer shall deposit the remaining 50% of the anticipated inspection fees. For those developments for which the reasonably anticipated fees total $10,000 or greater, fees may, at the option of the developer, be paid in four installments. The initial amount deposited in escrow by a developer shall be 25% of the reasonably anticipated fees. When the balance on deposit drops to 10% of the reasonably anticipated fees because the amount deposited by the developer has been reduced by the amount paid to the Township Engineer for inspection, the developer shall make additional deposits of 25% of the reasonably anticipated fees.
[Amended 4-3-2019 by Ord. No. 19-01]
h.
If the Township determines that the amount in escrow for the payment of inspection fees, as calculated pursuant to Subsection g1 and 2 of Subsection g, is insufficient to cover the cost of additional required inspections, the municipality may require the developer to deposit additional funds in escrow provided that the Township delivers to the developer a written inspection escrow deposit request, signed by the Township Engineer which: (1) informs the developer of the need for additional inspections, (2) details the items or undertakings that require inspection, (3) estimates the time required for those inspections, and (4) estimates the cost of performing those inspections.
[Added 4-3-2019 by Ord. No. 19-01]
[Amended 4-3-2019 by Ord. No. 19-01]
a.
Prior to the signing and filing of final major subdivision plats,
or the signing and recording of a minor subdivision deed as a condition
of final site plan approval in the case of a site plan, the developer
shall enter into an agreement with the Township Committee. This agreement
shall be of a form that is acceptable to the Township Attorney and
one in which the developer agrees to abide by the terms and conditions
of approval, construct the required improvements in accordance with
the approved plans, agree to maintain the constructed improvements
including but not limited to, payment of streetlighting charges, snow
removal, maintenance of storm drainage, sewer and water facilities.
The developer also shall agree that in the event the improvements
are not maintained, the Township can utilize the cash portions of
the performance guarantees to immediately attend to items presenting
a safety hazard.
[Ord. No. 00-04 § XI; Ord. No. 01-30 § II; amended 4-3-2019 by Ord. No. 19-01]
a.
Upon substantial completion of all required street improvements (except for the top course) and appurtenant utility improvements, and the connection of same to the public system, the obligor may request of the Township Committee in writing, by certified mail addressed in care of the Township Clerk, that the Township Engineer prepare, in accordance with the itemized cost estimate prepared by the Township Engineer and appended to the performance guarantee pursuant to § 35-13-2, a list of all uncompleted or unsatisfactory completed improvements. If such a request is made, the obligor shall send a copy of the request to the Township Engineer. The request shall indicate which improvements have been completed and which improvements remain uncompleted in the judgment of the obligor.
Concurrent with this request, the obligor shall forward a set
of as-built plans for the following:
1.
Roads (plan and profiles).
2.
Surface and stormwater drainage (plans and profiles) for facilities
in roads and easements.
3.
Gas mains and underground electric, telephone and community antenna
television (C.A.T.V.) conduits (plans and profiles) for facilities
in roads and easements.
Upon acceptance of the as-built plan information by the Township
Engineer, four paper copies of the as-built plan shall be submitted
to the Township.
|
Thereupon the Township Engineer shall inspect all of the improvements
covered by the obligor's request and shall file a detailed list and
report, in writing, with the Township Committee, and shall simultaneously
send a copy thereof to the obligor not later than 45 days after receipt
of the obligor's request.
|
The list prepared by the Township Engineer shall state, in detail, with respect to each required improvement determined to be incomplete or unsatisfactory, the nature and extent of the incompleteness of each incomplete improvement or the nature and extent of, and remedy for, the unsatisfactory state of each completed required improvement determined to be unsatisfactory. The report prepared by the Township Engineer shall identify each required improvement determined to be complete and satisfactory together with a recommendation as to the amount of reduction to be made in the performance guarantee relating to the completed and satisfactory improvement, in accordance with the itemized cost estimate prepared by the Township Engineer and appended to the performance guarantee pursuant to § 35-13-2.1.
|
b.
The Township Committee, by resolution, shall either approve the improvements determined to be complete and satisfactory by the Township Engineer, or reject any or all of these improvements upon the establishment in the resolution of cause for rejection, and shall approve and authorize the amount of reduction to be made in the performance guarantee relating to the required improvements accepted, in accordance with the itemized cost estimate prepared by the Township Engineer and appended to the performance guarantee pursuant to § 35-13-2.1. This resolution shall be adopted not later than 45 days after receipt of the list and report prepared by the Township Engineer. Upon adoption of the resolution by the Township Committee, the obligor shall be released from all liability pursuant to its performance guarantee, with respect to those approved improvements, except for that portion adequately sufficient to secure completion or correction of the improvements not yet approved; provided that 30% of the amount of the performance guarantee posted may be retained to ensure completion and acceptability of all required improvements.
[Amended 4-3-2019 by Ord. No. 19-01]
c.
For the purpose of releasing the obligor from liability pursuant to its performance guarantee, the amount of the performance guarantee attributable to each approved improvement shall be reduced by the total amount for each such improvement, in accordance with the itemized cost estimate prepared by the Township Engineer and appended to the performance guarantee pursuant to Subsection a of this section, including any contingency factor applied to the cost of installation. If the sum of the approved improvements would exceed 70% of the total amount of the performance guarantee, then the Township may retain 30% of the amount of the total performance guarantee to ensure completion and acceptability of all required improvements, as provided above.
[Amended 4-3-2019 by Ord. No. 19-01]
d.
If the Township Engineer fails to send or provide the list and report as requested by the obligor pursuant to § 35-13-5a above within 45 days from receipt of the request, the obligor may apply to the court in a summary manner for an order compelling the Township Engineer to provide the list and report within a stated time and the cost of applying to the court, including reasonable attorney's fees, may be awarded to the prevailing party.
If the Township Committee fails to approve or reject the improvements determined by the Township Engineer to be complete and satisfactory or reduce the performance guarantee for the complete and satisfactory improvements within 45 days from the receipt of the Township Engineer's list and report, the obligor may apply to the court in a summary manner for an order compelling, within a stated time, approval of the complete and satisfactory improvements and approval of a reduction in the performance guarantee for the approvable complete and satisfactory improvements in accordance with the itemized cost estimate prepared by the Township Engineer and appended to the performance guarantee pursuant to § 35-13-2.1; and the cost of applying to the court, including reasonable attorney's fees, may be awarded to the prevailing party.
e.
In the event that the obligor has made a cash deposit with the Township
or approving authority as part of the performance guarantee, then
any partial reduction granted in the performance guarantee pursuant
to this subsection shall be applied to the cash deposit in the same
proportion as the original cash deposit bears to the full amount of
the performance guarantee.
f.
If any portion of the required improvements is rejected, the approving
authority may require the obligor to complete or correct such improvements
and, upon completion or correction, the same procedure of notification,
as set forth in this section shall be followed.
g.
Nothing herein, however, shall be construed to limit the right of
the obligor to contest by legal proceedings any determination of the
Township Committee or the Township Engineer.
h.
[1]In the event that final approval is by stages or sections
of development pursuant to N.J.S.A. 40:55D-38, the provisions of this
section shall be applied by stage or section.
i.
Any release of performance guarantees will be conditioned upon the
provision of a maintenance guarantee to be posted with the Township
Committee, for an effective period of two years, in an amount equal
to 15% of the performance guarantee amount. In addition, upon the
inspection and issuance of final approval of the following private
site improvements by the municipal engineer, the developer shall post
with the Township a maintenance guarantee in an amount not to exceed
15% of the cost of the installation of the following private site
improvements: stormwater management basins, in-flow and water quality
structures within the basins, and the out-flow pipes and structures
of the stormwater management system, if any, which cost shall be determined
according to the method of calculation set forth in N.J.S.A. 40:55D-53.4.
[Amended 4-3-2019 by Ord. No. 19-01]
j.
To the extent that any of the improvements have been dedicated to the Township on the subdivision plat or site plan, the Township Committee shall be deemed, upon the release of any performance guarantee required pursuant to Subsection a above, to accept dedication for public use of streets or roads and any other improvements made thereon according to site plans and subdivision plats approved by the Approving Authority, provided that such improvements have been inspected and have received final approval by the Municipal Engineer.