A.Â
The Municipal Engineer or his municipal designee shall
inspect all phases of the installation of the permanent BMPs and/or
stormwater management facilities as deemed appropriate by the Municipal
Engineer.
B.Â
During any stage of the work, if the Municipal Engineer
or his municipal designee determines that the permanent BMPs and/or
stormwater management facilities are not being installed in accordance
with the approved stormwater management plan, the municipality shall
revoke any existing permits or other approvals and issue a cease and
desist order until a revised drainage plan is submitted and approved,
as specified in this Part 2, and until the deficiencies are corrected.
C.Â
A final inspection of all BMPs and/or stormwater management
facilities shall be conducted by the Municipal Engineer or his municipal
designee to confirm compliance with the approved drainage plan prior
to the issuance of any occupancy permit.