A. 
The purpose of this chapter is to protect, maintain, and enhance the public health, safety, and general welfare by establishing minimum requirements and procedures that control the adverse impacts associated with increased stormwater runoff. The goal is to manage stormwater by using environmental site design (ESD) to the maximum extent practicable (MEP) to maintain after development, as nearly as possible, the predevelopment runoff characteristics, and to reduce stream channel erosion, pollution, siltation and sedimentation, and local flooding, and use appropriate structural best management practices (BMPs) only when necessary. This will restore, enhance, and maintain the chemical, physical, and biological integrity of streams, minimize damage to public and private property, and reduce the impacts of land development.
B. 
The provisions of this chapter, pursuant to the Environment Article, Title 4, Subtitle 2, Annotated Code of Maryland, 2009 replacement volume, are adopted under the authority of the Town of Bel Air Code and shall apply to all development occurring within the Town of Bel Air. The application of this chapter and provisions expressed herein shall be the minimum stormwater management requirements and shall not be deemed a limitation or repeal of any other powers granted by state statute.
C. 
The Town of Bel Air shall be responsible for the coordination and enforcement of the provisions of this chapter. This chapter applies to all new and redevelopment projects that have not received final approval for erosion and sediment control and stormwater management plans by May 4, 2010.
For the purpose of this chapter, the following documents are incorporated by reference:
A. 
The 2000 Maryland Stormwater Design Manual, Volumes I and II (Maryland Department of the Environment, April 2000), and all subsequent revisions, is incorporated by reference by the Town of Bel Air and shall serve as the official guide for stormwater management principles, methods, and practices.
B. 
USDA Natural Resources Conservation Service Maryland Conservation Practice Standard Pond Code 378 (January 2000).
A. 
In this section, the following terms have the meanings indicated:
ADMINISTRATIVE WAIVER
(1) 
A decision by the Town of Bel Air pursuant to this chapter to allow the construction of a development to be governed by the stormwater management ordinance in effect as of May 4, 2009, in the local jurisdiction where the project will be located.
(2) 
“Administrative waiver” is distinct from a waiver granted pursuant to § 405-6 of this chapter.
APPROVAL
(1) 
A documented action by the Town of Bel Air following a review to determine and acknowledge the sufficiency of submitted material to meet the requirements of a specified stage in a local development review process.
(2) 
"Approval" does not mean an acknowledgment by the Town of Bel Air that submitted material has been received for review.
FINAL PROJECT APPROVAL
(1) 
Approval of the final stormwater management plan and erosion and sediment control plan required to construct a project's stormwater management facilities.
(2) 
"Final project approval" also includes securing bonding or financing for final development plans if either is required as a prerequisite for approval.
PRELIMINARY PROJECT APPROVAL
An approval as part of a local preliminary development or planning review process that includes, at a minimum:
(1) 
The number of planned dwelling units or lots;
(2) 
The proposed project density;
(3) 
The proposed size and location of all land uses for the project;
(4) 
A plan that identifies:
(a) 
The proposed drainage patterns;
(b) 
The location of all points of discharge from the site; and
(c) 
The type, location, and size of all stormwater management measures based on site-specific stormwater management requirement computations; and
(5) 
Any other information required by the Town of Bel Air, including, but not limited to:
(a) 
The proposed alignment, location, and construction type and standard for all roads, accessways, and areas of vehicular traffic;
(b) 
A demonstration that the methods by which the development will be supplied with water and wastewater service are adequate; and
(c) 
The size, type, and general location of all proposed wastewater and water system infrastructure.
B. 
The Town of Bel Air may grant an administrative waiver to a development that received a preliminary project approval prior to May 4, 2010. Administrative waivers expire according to Subsection C of this section and may be extended according to Subsection D of this section.
C. 
Expiration of administrative waivers.
(1) 
Except as provided for in Subsection D(2) of this section, an administrative waiver shall expire on:
(a) 
May 4, 2013, if the development does not receive final project approval prior to that date; or
(b) 
May 4, 2017, if the development receives final project approval prior to May 4, 2013.
(2) 
All construction authorized pursuant to an administrative waiver must be completed by May 4, 2017, or, if the waiver is extended as provided in Subsection D of this section, by the expiration date of the waiver extension.
D. 
Extension of administrative waivers.
(1) 
Except as provided in Subsection D(2) of this section, an administrative waiver shall not be extended.
(2) 
An administrative waiver may only be extended if, by May 4, 2010, the development:
(a) 
Has received a preliminary project approval; and
(b) 
Was subject to a development rights and responsibilities agreement, a tax increment financing approval, or an annexation agreement.
(3) 
Administrative waivers extended according to Subsection D(2) of this section shall expire when the development rights and responsibilities agreement, the tax increment financing approval, or the annexation agreement expires.
The following definitions are provided for the terms used in this chapter:
ADMINISTRATION
The Maryland Department of the Environment (MDE) Water Management Administration (WMA).
ADVERSE IMPACT
Any deleterious effect on waters or wetlands, including their quality, quantity, surface area, species composition, aesthetics or usefulness for human or natural uses which are or may potentially be harmful or injurious to human health, welfare, safety or property, to biological productivity, diversity, or stability, or which unreasonably interfere with the enjoyment of life or property, including outdoor recreation.
AGRICULTURAL LAND MANAGEMENT PRACTICES
Those methods and procedures used in the cultivation of land in order to further crop and livestock production and conservation of related soil and water resources.
APPLICANT
Any person, firm, or governmental agency which executes the necessary forms to procure official approval of a project or a permit to carry out construction of a project.
APPROVING AGENCY
The entity responsible for the review and approval of stormwater management plans.
AQUIFER
A porous water-bearing geologic formation generally restricted to materials capable of yielding an appreciable supply of water.
BEST MANAGEMENT PRACTICE (BMP)
A structural device or nonstructural practice designed to temporarily store or treat stormwater runoff in order to mitigate flooding, reduce pollution, and provide other amenities.
CHANNEL PROTECTION STORAGE VOLUME (CPV)
The volume used to design structural management practices to control stream channel erosion. Methods for calculating the channel protection storage volume are specified in the 2000 Maryland Stormwater Design Manual.
CLEARING
The removal of trees and brush from the land, but shall not include the ordinary mowing of grass.
CONCEPT PLAN
The first of three required plan approvals that includes the information necessary to allow an initial evaluation of a proposed project.
DESIGN MANUAL
The 2000 Maryland Stormwater Design Manual, and all subsequent revisions, that serves as the official guide for stormwater management principles, methods, and practices.
DETENTION STRUCTURE
A permanent structure for the temporary storage of runoff which is designed so as not to create a permanent pool of water.
DEVELOP LAND
To change the runoff characteristics of a parcel of land in conjunction with residential, commercial, industrial, or institutional construction or alteration.
DIRECT DISCHARGE
The concentrated release of stormwater to tidal waters or vegetated tidal wetlands from new development or redevelopment projects in the critical area.
DRAINAGE AREA
That area contributing runoff to a single point measured in a horizontal plane, which is enclosed by a ridgeline.
EASEMENT
A grant or reservation by the owner of land for the use of such land by others for a specific purpose or purposes and which must be included in the conveyance of land affected by such easement.
ENVIRONMENTAL SITE DESIGN (ESD)
Using small-scale stormwater management practices, nonstructural techniques, and better site planning to mimic natural hydrologic runoff characteristics and minimize the impact of land development on water resources. Methods for designing ESD practices are specified in the Design Manual.
EXEMPTION
Those land development activities that are not subject to the stormwater management requirements contained in this chapter.
EXTENDED DETENTION
A stormwater design feature that provides gradual release of a volume of water in order to increase settling of pollutants and protect downstream channels from frequent storm events. Methods for designing extended detention BMPs are specified in the Design Manual.
EXTREME FLOOD VOLUME (Qf)
The storage volume required to control those infrequent but large storm events in which overbank flows reach or exceed the boundaries of the one-hundred-year floodplain.
FINAL STORMWATER MANAGEMENT PLAN
The last of three required plan approvals that includes the information necessary to allow all approvals and permits to be issued by the approving agency.
FLOW ATTENUATION
Prolonging the flow time of runoff to reduce the peak discharge.
GRADING
Any act by which soil is cleared, stripped, stockpiled, excavated, scarified, filled, or any combination thereof.
IMPERVIOUS AREA
Any surface that does not allow stormwater to infiltrate into the ground.
INFILTRATION
The passage or movement of water into the soil surface.
MAXIMUM EXTENT PRACTICABLE (MEP)
Designing stormwater management systems so that all reasonable opportunities for using ESD planning techniques and treatment practices are exhausted and, only where absolutely necessary, a structural BMP is implemented.
OFF-SITE STORMWATER MANAGEMENT
The design and construction of a facility necessary to control stormwater from more than one development.
ON-SITE STORMWATER MANAGEMENT
The design and construction of systems necessary to control stormwater within an immediate development.
OVERBANK FLOOD PROTECTION VOLUME (Qp)
The volume controlled by structural practices to prevent an increase in the frequency of out-of-bank flooding generated by development. Methods for calculating the overbank flood protection volume are specified in the Design Manual.
PERSON
The federal government, the state, any county, municipal corporation, or other political subdivision of the state, or any of their units, or an individual receiver, trustee, guardian, executor, administrator, fiduciary, or representative of any kind, or any partnership, firm, association, public or private corporation, or any other entity.
PLANNING TECHNIQUES
A combination of strategies employed early in project design to reduce the impact from development and to incorporate natural features into a stormwater management plan.
RECHARGE VOLUME (Rev)
That portion of the water quality volume used to maintain groundwater recharge rates at development sites. Methods for calculating the recharge volume are specified in the Design Manual.
REDEVELOPMENT
Any construction, alteration, or improvement performed on sites where existing land use is commercial, industrial, institutional, or multifamily residential and existing site impervious area exceeds 40%.
RETENTION STRUCTURE
A permanent structure that provides for the storage of runoff by means of a permanent pool of water.
RETROFITTING
The implementation of ESD practices, the construction of a structural BMP, or the modification of an existing structural BMP in a previously developed area to improve water quality over current conditions.
SEDIMENT
Soils or other surficial materials transported or deposited by the action of wind, water, ice, or gravity as a product of erosion.
SITE
Any tract, lot, or parcel of land, or combination of tracts, lots, parcels of land, that are in one ownership, or are contiguous and in diverse ownership, where development is to be performed as part of a unit, subdivision, or project.
SITE DEVELOPMENT PLAN
The second of three required plan approvals that includes the information necessary to allow a detailed evaluation of a proposed project.
STABILIZATION
The prevention of soil movement by any of various vegetative and/or structural means.
STORMWATER
Water that originates from a precipitation event.
STORMWATER MANAGEMENT SYSTEM
Natural areas, ESD practices, stormwater management measures, and any other structure through which stormwater flows, infiltrates, or discharges from a site.
STRIPPING
Any activity that removes the vegetative surface cover, including tree removal, clearing, grubbing, and storage or removal of topsoil.
VARIANCE
The modification of the minimum stormwater management requirements for specific circumstances such that strict adherence to the requirements would result in unnecessary hardship and not fulfill the intent of this chapter.
WAIVER
The reduction of stormwater management requirements by the Town of Bel Air for a specific development on a case-by-case review basis.
WATERCOURSE
Any natural or artificial stream, river, creek, ditch, channel, canal, conduit, culvert, drain, waterway, gully, ravine or wash, in and including any adjacent area that is subject to inundation from overflow or floodwater.
WATER QUALITY VOLUME (WQv)
The volume needed to capture and treat 90% of the average annual rainfall events at a development site. Methods for calculating the water quality volume are specified in the Design Manual.
WATERSHED
The total drainage area contributing runoff to a single point.
A. 
Scope. No person shall develop any land for residential, commercial, industrial, or institutional uses without providing stormwater management measures that control or manage runoff from such developments, except as provided within this section. Stormwater management measures must be designed consistent with the Design Manual and constructed according to an approved plan for new development or the policies stated in § 405-7 of this chapter for redevelopment.
B. 
Exemptions. The following development activities are exempt from the provisions of this chapter and the requirements of providing stormwater management:
(1) 
Agricultural land management practices;
(2) 
Additions or modifications to existing single-family detached residential structures if they comply with Subsection B(3) of this section;
(3) 
Any developments that do not disturb over 5,000 square feet of land area; and
(4) 
Land development activities that the administration determines will be regulated under specific state laws, which provide for managing stormwater runoff.
A. 
Except as provided in Subsections B and D of this section, the Town of Bel Air shall grant stormwater management quantitative control waivers only to those projects within areas where watershed management plans have been developed consistent with Subsection G of this section. Written requests for quantitative stormwater management waivers shall be submitted that contain sufficient descriptions, drawings, and any other information that is necessary to demonstrate that ESD has been implemented to the MEP. A separate written waiver request shall be required in accordance with the provisions of this section if there are subsequent additions, extensions, or modifications to a development receiving a waiver.
B. 
Except as provided in Subsection D of this section, if watershed management plans consistent with Subsection G of this section have not been developed, stormwater management quantitative control waivers may be granted to the following projects, provided that it has been demonstrated that ESD has been implemented to the MEP:
(1) 
That have direct discharges to tidally influenced receiving waters;
(2) 
That are infill development located in a priority funding area where the economic feasibility of the project is tied to the planned density and where implementation of the 2009 regulatory requirements would result in a loss of the planned development density, provided that:
(a) 
Public water and sewer and stormwater conveyance exist;
(b) 
The quantitative waiver is applied to the project for the impervious cover that previously existed on the site only;
(c) 
ESD to the MEP is used to meet the full water quality treatment requirements for the entire development; and
(d) 
ESD to the MEP is used to provide full quantity control for all new impervious surfaces; or
(3) 
When the approving agency determines that circumstances exist that prevent the reasonable implementation of quantity control practices.
C. 
Except as provided in Subsection D of this section, stormwater management qualitative control waivers apply only to:
(1) 
Infill development projects where ESD has been implemented to the MEP and it has been demonstrated that other BMPs are not feasible;
(2) 
Redevelopment projects if the requirements of § 405-7 of this chapter are satisfied; or
(3) 
Sites where the approving agency determines that circumstances exist that prevent the reasonable implementation of ESD to the MEP.
D. 
Stormwater management quantitative and qualitative control waivers may be granted for phased development projects if a system designed to meet the 2000 regulatory requirements and the Town of Bel Air ordinance for multiple phases has been constructed by May 4, 2010. If the 2009 regulatory requirements cannot be met for future phases constructed after May 4, 2010, all reasonable efforts to incorporate ESD in future phases must be demonstrated.
E. 
Waivers shall only be granted when it has been demonstrated that ESD has been implemented to the MEP and must:
(1) 
Be on a case-by-case basis;
(2) 
Consider the cumulative effects of the Town of Bel Air waiver policy; and
(3) 
Reasonably ensure the development will not adversely impact stream quality.
F. 
If the Town of Bel Air has established an overall watershed management plan for a specific watershed, then the Town of Bel Air may develop quantitative waiver and redevelopment provisions that differ from §§ 405-6B and 405-7 of this chapter.
G. 
A watershed management plan developed for the purpose of implementing different stormwater management policies for waivers and redevelopment shall:
(1) 
Include detailed hydrologic and hydraulic analyses to determine hydrograph timing;
(2) 
Evaluate both quantity and quality management and opportunities for ESD implementation;
(3) 
Include a cumulative impact assessment of current and proposed watershed development;
(4) 
Identify existing flooding and receiving stream channel conditions;
(5) 
Be conducted at a reasonable scale;
(6) 
Specify where on-site or off-site quantitative and qualitative stormwater management practices are to be implemented;
(7) 
Be consistent with the General Performance Standards for Stormwater Management in Maryland found in the Design Manual; and
(8) 
Be approved by the Administration.
A. 
Stormwater management plans are required by the Town of Bel Air for all redevelopment, unless otherwise specified by watershed management plans developed according to Subsection G of this section. Stormwater management measures must be consistent with the Design Manual.
B. 
All redevelopment designs shall:
(1) 
Reduce impervious area within the limit of disturbance (LOD) by at least 50% according to the Design Manual;
(2) 
Implement ESD to the MEP to provide water quality treatment for at least 50% of the existing impervious area within the LOD; or
(3) 
Use a combination of Subsection B(1) and (2) of this section for at least 50% of the existing site impervious area.
C. 
Alternative stormwater management measures may be used to meet the requirements in Subsection B of this section if the owner/developer satisfactorily demonstrates to the Town of Bel Air that impervious area reduction has been maximized and ESD has been implemented to the MEP. Alternative stormwater management measures include but are not limited to:
(1) 
An on-site structural BMP;
(2) 
An off-site structural BMP to provide water quality treatment for an area equal to or greater than 50% of the existing impervious area; or
(3) 
A combination of impervious area reduction, ESD implementation, and an on-site or off-site structural BMP for an area equal to or greater than 50% of the existing site impervious area within the LOD.
D. 
The Town of Bel Air may develop separate policies for providing water quality treatment for redevelopment projects if the requirements of Subsections B and C of this section cannot be met. Any separate redevelopment policy shall be reviewed and approved by the Administration and may include but not be limited to:
(1) 
A combination of ESD and an on-site or off-site structural BMP;
(2) 
Retrofitting, including existing BMP upgrades, filtering practices, and off-site ESD implementation;
(3) 
Participation in a stream restoration project;
(4) 
Pollution trading with another entity;
(5) 
Payment of a fee-in-lieu; or
(6) 
A partial waiver of the treatment requirements if ESD is not practicable.
E. 
The determination of what alternatives will be available may be made by the Town of Bel Air at the appropriate point in the development review process. The Town of Bel Air shall consider the prioritization of alternatives in Subsection D of this section after it has been determined that it is not practicable to meet the 2009 regulatory requirements using ESD. In deciding what alternatives may be required, the Town of Bel Air may consider factors including but not limited to:
(1) 
Whether the project is in an area targeted for development incentives such as a priority funding area, a designated transit-oriented development area, or a designated Base Realignment and Closure Revitalization and Incentive Zone;
(2) 
Whether the project is necessary to accommodate growth consistent with comprehensive plans; or
(3) 
Whether bonding and financing have already been secured based on an approved development plan.
F. 
Stormwater management shall be addressed according to the new development requirements in the Design Manual for any net increase in impervious area.
The Town of Bel Air may grant a written variance from any requirement of Article II, Stormwater Management Criteria, if there are exceptional circumstances applicable to the site such that strict adherence will result in unnecessary hardship and not fulfill the intent of this chapter. A written request for variance shall be provided to the Town of Bel Air and shall state the specific variances sought and reasons for their granting. The Town of Bel Air shall not grant a variance unless and until sufficient justification is provided by the person developing land that the implementation of ESD to the MEP has been investigated thoroughly.