1.
|
BUILDING SUBCODE FEES
| ||||
a.
|
Minimum fee:
|
$75.00
| |||
b.
|
New Construction: Fees for new construction shall be based upon
the volume of the structure. Volume shall be computed in accordance
with N.J.A.C. 5:23-2.28. Use groups and types of construction are
as classified and defined in N.J.A.C. 5:23-Subchapter 3 Subcodes and
Subchapter 4 Enforcing Agencies; Duties; Powers; Procedures.
| ||||
Minimum fee for new construction shall be:
|
$150.00
| ||||
NEW CONSTRUCTION (except as listed in other use groups, below)
| |||||
Per cubic foot of volume:
|
$.040
| ||||
OTHER USE GROUPS
| |||||
A-1, A-2, A-3, A-4 and A-5, F-1, F-2, S-1 and S-2:
| |||||
Per cubic foot of volume:
|
$.030
| ||||
All Farm Buildings for shelter of livestock and food storage:
| |||||
Per cubic foot of volume:
|
$.0020
| ||||
c.
|
RENOVATIONS, ALTERATIONS, REPAIRS, AND MINOR REPAIRS
| ||||
Fee based on the estimated cost of work. To determine the estimated
cost, the applicant shall submit to the Construction Code Official
such cost data as may be available produced by the architect or engineer
of record, or by a recognized estimating firm, or by bona fide contractor's
bid if available shall be submitted. The Construction Code Official
shall make final decision regarding the estimated cost.
| |||||
i. $1.00-$50,000.00:
|
$40.00 per $1,000.00
| ||||
ii. $50,001.00-$100,000.00:
|
add $35.00 per $1,000.00
| ||||
iii. Over $100,000.00:
|
add $25.00 per $1,000.00
| ||||
ADDITIONS; Fees shall be computed on the same basis as for new
construction for the added portion. Minimum fee is:
|
$150.00
| ||||
d.
|
COMBINATION RENOVATIONS AND ADDITIONS: Fees shall be the sum
of the fees computed separately as renovation, addition.
| ||||
e.
|
DEMOLITION: The fee shall be as follows:
| ||||
i. R-5 buildings or structures:
|
$125.00
| ||||
ii. All other use groups:
|
$200.00
| ||||
f.
|
RELOCATION OF BUILDINGS OR STRUCTURES: For the relocation of
buildings and structures to a new location (including premanufactured
construction, assembly or components transported to a construction
site) the fee shall be based on the following estimated cost:
| ||||
1. Transportation and moving
| |||||
2. New foundation
| |||||
3. Placement of structure in a completed condition at the new
site.
| |||||
4. External utility connections
| |||||
i. $1.00 - $50,000.00:
|
$40.00 per $1,000.00
| ||||
ii. $50,001.00 - $100,000.00:
|
$35.00 per $1,000.00
| ||||
iii. Over $100,000.00:
|
$25.00 per $1,000.00
| ||||
iv. Temporary Construction Trailer:
|
$100.00
| ||||
The applicant shall submit a copy of the Contract Proposal Cost
Data by the architect or engineer of record, a recognized estimating
firm or by contract bid. The Building Sub Code Official shall make
the final decision regarding the estimated cost.
| |||||
g.
|
SWIMMING POOLS: The fee shall be as follows:
| ||||
i. R-5 above ground:
|
$140.00
| ||||
ii. Residential in ground:
|
$200.00
| ||||
iii. All other use groups:
|
$300.00
| ||||
iv. Pool demo:
|
$75.00
| ||||
h.
|
STORAGE SHEDS AND SIMILAR STRUCTURES:
| ||||
i. 1-180 square feet, (Zoning Only) if in a SFHA, same as new
construction
| |||||
ii. 201 square feet or larger, same as new construction (A1a)
| |||||
i.
|
TENTS in excess of 900 sq. ft. or more than 30 feet in any dimension
the fee shall be:
|
$120.00
| |||
j.
|
ROOFING: The fee shall be as follows:
| ||||
i. R5 Use groups:
|
$75.00
| ||||
ii. All other use groups use A1c
| |||||
k.
|
SIDING: The fee shall be as follows:
| ||||
i. R-5 Use groups:
|
$75.00
| ||||
ii. All other use groups use A1c
| |||||
l.
|
DECKS: The fees shall be based on the estimated cost as Alb
Renovations, Alterations. The estimated cost shall be calculated as
1 square foot equals $15.00.
| ||||
m.
|
PRE-MANUFACTURED FIREPLACES, free standing stoves, etc.:
|
$75.00
| |||
n
|
. SIGNS: The fee shall be $2.00 per square feet surface area
of the sign computed on one side only on double faced signs. Minimum
fee:
|
$75.00
| |||
o.
|
SUNROOMS AND SCREEN ROOMS:
|
$100.00
| |||
p.
|
SOLAR ATTACHMENTS
| ||||
i. R-5 Use groups use A1c:
|
$100.00
| ||||
ii. All other use groups use A1c:
|
$200.00
| ||||
q.
|
RETAINING WALLS
| ||||
R5
|
$150.00
| ||||
All other use groups use A1c
| |||||
r.
|
Platform for generators or a/c compressors:
|
$75.00
| |||
2.
|
PLUMBING SUBCODE
| ||||
a.
|
MINIMUM FEE:
|
$75.00
| |||
b.
|
FIXTURES AND APPLIANCES: The installation of plumbing per fixture
or stack shall include but not be limited to water closets, bathtubs,
shower stalls, sinks, laundry tubs, floor drains, vtr, drinking fountains,
dishwashers, clothes washers, dryers (new construction), water heaters
(new construction), fireplaces (new construction),, stoves/range (new
construction), generators (new construction), and any gas appliance
not listed in this fee schedule, roof drains, hose bibs, icemakers,
or similar devices or appliances the fee shall be as follows:
| ||||
i. Per fixture device or appliance:
|
$20.00
| ||||
c.
|
MODULAR & PRE-MANUFACTURED STRUCTURES
| ||||
installed on site shall be as follows:
|
$175.00
| ||||
d.
|
SPECIAL DEVICE:
| ||||
i. R5 - the installation of a boiler (hot water or steam)(new
construction), Pool Heaters, Generators, Backflow Preventors, grease
traps, interceptors, sewage pump, sump pumps, furnaces (new construction),
ac units (new construction) or similar devices:
|
$75.00
| ||||
ii. All Other Use Groups:
|
$100.00
| ||||
e.
|
GAS AND/OR OIL PIPING shall be as follows:
| ||||
i. R-5:
|
$75.00
| ||||
ii. All other use groups:
|
$100.00
| ||||
f.
|
LAWN IRRIGATION:
|
$75.00
| |||
g.
|
SEWER CONNECTION
| ||||
i. R-5:
|
$75.00
| ||||
ii. All other use groups:
|
$100.00
| ||||
h.
|
WATER CONNECTION
| ||||
i. R5:
|
$75.00
| ||||
ii. All other use groups:
|
$100.00
| ||||
i.
|
NEW or REPLACEMENT GAS or OIL FIRED EQUIPMENT IN EXISTING R-3,
R-4 AND R-5 HOMES:
|
$75.00
| |||
j.
|
NEW or REPLACEMENT A/C SYSTEMS IN EXISTING R-3, R-4 AND R-5
HOMES
|
$75.00
| |||
k.
|
Testable BFP:
|
$75.00
| |||
l.
|
Pool Drains R-5:
|
$75.00
| |||
Pool Drains/SVRS — All other use groups:
|
$100.00
| ||||
m.
|
Furnace - New or Replacement not subject to 2i:
|
$200.00
| |||
n.
|
A/C system New or Replacement not subject to 2i:
|
$200.00
| |||
o.
|
HVAC system New or Replacement not subject to 2i:
|
$200.00
| |||
p.
|
Rooftop package units (hvac):
|
$100.00
| |||
q.
|
Septic abandonment:
|
$75.00
| |||
r.
|
Water Heater, new or replacement, not subject to 2(i):
|
$200.00
| |||
3.
|
FIRE SUBCODE
| ||||
a.
|
Minimum Fee:
|
$75.00
| |||
b.
|
GAS or OIL FIRED APPLIANCES - NEW CONSTRUCTION OR REPLACEMENT
UNITS IN ALL USE GROUPS EXCEPT R-3, R-4 AND R-5
| ||||
1st Unit:
|
$60.00 each
| ||||
2nd and up:
|
$40.00 each
| ||||
R-3, R-4 AND R-5:
|
COVERED IN PLUMBING FEE 2i
| ||||
c.
|
FIRE SUPPRESSION SYSTEMS
| ||||
i. 1-20 heads:
|
$100.00
| ||||
ii. 21-100 heads:
|
$200.00
| ||||
iii. 101-200 heads:
|
$400.00
| ||||
iv. 201-400 heads:
|
$1,000.00
| ||||
v. 401-1,000 heads:
|
$1,400.00
| ||||
vi. Over 1,000 heads:
|
$1,800.00
| ||||
d.
|
FIRE ALARMS, DETECTORS fees to be computed as fire suppression
systems. In computing fees for heads and detectors, the number of
each to be computed separately.
| ||||
e.
|
FIRE PUMPS the fee shall be:
|
$100.00
| |||
f.
|
STANDPIPE SYSTEMS each:
|
$300.00
| |||
g.
|
ENGINEERED SUPPRESSION SYSTEM the fee shall be:
|
$150.00
| |||
h.
|
INDEPENDENT PRE-ENGINEERED SYSTEM the fee shall be:
|
$150.00
| |||
i.
|
INCINERATORS the fee shall be:
|
$500.00
| |||
j.
|
CREMATORIUMS the fee shall be:
|
$500.00
| |||
k.
|
SPRAY BOOTHS AND DIPPING OPERATIONS:
|
$150.00
| |||
l.
|
FUEL DISPENSING UNITS in the case of service stations the fee
shall be per island:
|
$225.00
| |||
m.
|
INSTALLATION AND REMOVAL OF STORAGE TANKS
| ||||
i. R-5:
|
$100.00
| ||||
ii. All other use groups:
|
$200.00
| ||||
n.
|
Generator installation:
|
$75.00
| |||
o.
|
LOW VOLTAGE ALARMS (SUPPLEMENTAL):
|
$75.00
| |||
4.
|
ELECTRIC SUBCODE
| ||||
a.
|
MINIMUM FEE:
|
$75.00
| |||
b.
|
FIXTURES OR RECEPTACLES (receptacles and fixtures shall include
lighting outlets, wall switches, electrical discharge fixtures, convenience
receptacles, light standards 8 ft or less, exit signs/lights or similar
fixtures, motors or devices of less than 20 amps, less than one horsepower
or less than one kilowatt, burglar, fire and communication devices
etc.), the fee shall be as follows:
| ||||
i. 1-25:
|
$60.00
| ||||
ii. each additional 25:
|
$10.00
| ||||
iii Light standards 9 ft or taller (per light standard):
|
$25.00
| ||||
iv. Replacement wiring — 1 branch circuit:
|
$25.00
| ||||
v. Household electrical cooking equipment up to 16 KW:
|
$25.00
| ||||
vi. Receptacles — 20 to 50 amps (each):
|
$25.00
| ||||
vii. Receptacles — 60-100 amps(each):
|
$58.00
| ||||
viii. Utility load management devices (each):
|
$58.00
| ||||
ix. Burglar, security or fire alarm control device - up to 6
devices:
|
$50.00
| ||||
7 or more devices:
|
$75.00
| ||||
x. Motor control center or disconnect means —up to 200
amps:
|
$58.00
| ||||
xi. Motor control center or disconnect means —201 to 1000
amps
|
$125.00
| ||||
xii. Motor control center or disconnect means —1001 amps
or higher:
|
$576.00
| ||||
xiii. Dishwasher:
|
$35.00
| ||||
xiv. Disposal:
|
$40.00
| ||||
xv. Furnaces/air-conditioning systems:
|
$50.00
| ||||
c.
|
MOTORS OR ELECTRICAL DEVICES (each)
| ||||
1-9 horsepower:
|
$40.00
| ||||
10-50 horsepower:
|
$60.00
| ||||
51-100 horsepower:
|
$125.00
| ||||
OVER 100 horsepower:
|
$500.00
| ||||
d.
|
TRANSFORMERS AND GENERATORS Kilowatt or Kilovolt (each):
| ||||
1-10:
|
$35.00
| ||||
11-50:
|
$60.00
| ||||
51-112.5:
|
$125.00
| ||||
OVER 112.5:
|
$500.00
| ||||
e.
|
SERVICE ENTRANCE with 1 PANEL & GROUNDING ELECTRODE SYSTEM
| ||||
0-200 amps:
|
$60.00
| ||||
201-800 amps:
|
$175.00
| ||||
OVER 800 amps:
|
$500.00
| ||||
EACH ADDITIONAL PANEL:
|
$50.00
| ||||
Below does not include cost of service panel
| |||||
(1)
|
Service cable/feeder replacement (up to 200 amps):
|
$50.00
| |||
(2)
|
Service cable/feeder replacement (201—800 amps):
|
$125.00
| |||
(3)
|
Service cable/feeder replacement over 800 amp:
|
$250.00
| |||
(4)
|
Underground service lateral .1-200 amp:
|
$50.00
| |||
(5)
|
Underground service lateral 201-800 amp:
|
$125.00
| |||
(6)
|
Underground service lateral over 800 amp:
|
$250.00
| |||
f.
|
For the purpose of computing fees above, all motors and plug-in
appliances shall be counted including control equipment, generators,
transformers and heating, cooking or other devices consuming or generating
electrical current.
| ||||
g.
|
SOLAR — INCLUDES SOLAR PANES, RACKING, MICRO INVERTERS,
COMBINERS AND GROUNDING
| ||||
1-5 kilowatts:
|
$75.00
| ||||
6-10 kilowatt:
|
$125.00
| ||||
10-20 kilowatts:
|
$200.00
| ||||
21-50 kilowatts:
|
$300.00
| ||||
51-100:
|
$575.00
| ||||
h.
|
IRRIGATION SYSTEM (includes pump and controller):
|
$60.00
| |||
i.
|
POOLS/Hot Tub/Hydro massage tubs/Spas
| ||||
A)
|
ABOVE-GROUND R-5:
|
$75.00
| |||
B)
|
INGROUND R-5:
|
$100.00
| |||
C)
|
All other use groups:
|
$250.00
| |||
D)
|
E/Q Bond inspection: R-5:
|
$60.00
| |||
E)
|
E/Q bond inspection All other uses:
|
$150.00
| |||
F)
|
Pool heater - electric with bond:
|
$40.00
| |||
G)
|
Pool Heater - gas with bond:
|
$25.00
| |||
*Note-Pool includes 1 light, (light niche, ladder cups, diving
board, etc. 1 receptacle, 1 (up to 1hp) filter, motor and required
bonding (Not E/Q Bond).
| |||||
Additional pool lights:
|
$15.00
| ||||
i.1.
|
Pool demo:
|
$60.00
| |||
j.
|
Generator hookup/transfer switch up to 12 kw:
|
$100.00
| |||
13 to 22 kw:
|
$200.00
| ||||
23 and over kw:
|
$500.00
| ||||
k.
|
SATELLITE DISH / COMMERCIAL ANTENNAS
| ||||
Residential:
|
$50.00
| ||||
Commercial (ON BUILDINGS/TOWERS):
|
$100.00
| ||||
l.
|
SIGNS
| ||||
1-5 Kilowatts
|
$35.00
| ||||
6-10 Kilowatts
|
$60.00
| ||||
m.
|
CSST Bond:
|
$60.00
| |||
n.
|
Meter reset/inspection of electrical system, panel and grounding:
|
$100.00
| |||
5.
|
ELEVATOR SUBCODE FEES - shall be in accordance
with N.J.A.C. 5:23-12.6.
| ||||
6.
|
CERTIFICATE OF OCCUPANCY FEES AND OTHER PERMITS
| ||||
a.
|
CERTIFICATE OF OCCUPANCY 10% of new construction fee or minimum:
|
$100.00
| |||
b.
|
CERTIFICATE OF OCCUPANCY for CHANGE OF USE:
|
$150.00
| |||
c.
|
CERTIFICATE OF CONTINUED OCCUPANCY:
|
$150.00
| |||
(1)
|
Tenant Fit out:
|
$150.00
| |||
d.
|
TEMPORARY CERTIFICATE OF OCCUPANCY EXTENSION:
|
$50.00
| |||
e.
|
CERTIFICATE OF APPROVAL for equipment having been determined
a hazard by N.J.A.C. 5:23-2.23.(i):
|
$50.00
| |||
f.
|
CERTIFICATE OF COMPLETION FOR ASBESTOS ABATEMENT:
|
$100.00
| |||
g.
|
CERTIFICATE OF LEAD ABATEMENT:
|
$100.00
| |||
h.
|
ANNUAL ELECTRICAL and PLUMBING CERTIFICATE OF COMPLIANCE (pools
/ backflow preventers, etc):
|
$100.00
| |||
i.
|
REINSTATE A LAPSED CONSTRUCTION PERMIT for each subcode:
|
$60.00
| |||
j.
|
FEES MISCELLANEOUS for an item for which a fee has not been
established:
|
$75.00
| |||
k.
|
PLAN REVIEW: the fee shall be 20% of the new construction fee.
| ||||
l.
|
VARIATIONS APPLICATIONS
| ||||
i. Class I buildings:
|
$600.00
| ||||
ii. Class II & III buildings:
|
$75.00
| ||||
m.
|
RESUBMITTED VARIATION FEE
| ||||
i. Class I buildings:
|
$250.00
| ||||
ii. Class II & III buildings:
|
$40.00
| ||||
n.
|
ANNUAL PERMITS issued for all Subcodes based on the number of
maintenance workers
| ||||
i. 1-15 workers:
|
$800.00
| ||||
ii. Over 25 workers, each additional worker:
|
$250.00
| ||||
o.
|
TRAINING REGISTRATION fee per subcode for annual permits paid
to State of NJ:
|
$175.00
| |||
p.
|
TRAINING CERTIFICATION AND TECHNICAL support shall be a surcharge
paid to the State of NJ
| ||||
i. New construction cubic feet times:
|
$.00371
| ||||
ii. Alterations except demolitions, $1,000.00 per estimated
cost:
|
$1.90
| ||||
iii. Minimum surcharge:
|
$1.00
| ||||
q.
|
Change of Contractor:
|
$25.00
| |||
7.
|
WAIVER OF CONSTRUCTION PERMIT FEE
| ||||
a.
|
As per N.J.A.C. 52:27D-126e, no person shall be charged a construction
permit fee for the construction, reconstruction, alteration or improvement
designed or under taken solely to promote accessibility such as a
ramp or entrance doorway only, for a disabled persons to an existing
residential private structure. A disabled person, or a parent or sibling
of a disabled person, shall not be required to pay a fee in order
to secure a construction permit for a ramp or entrance doorway.
| ||||
b.
|
For the purpose of this section, "disabled person" means a person
who has the total and permanent inability to engage in any substantial
gainful activity by reason of any medically determinable physical
or mental impairment, including blindness, and shall include, but
not be limited to, any resident of this State who is disabled pursuant
to the Federal Social Security Act of 1974 (42 U.S.C. 231 et seq.),
or is rated as having 60% disability or highest pursuant to any Federal
law administered by the United States Veterans' Act. For purposes
of this paragraph "blindness" means central visual acuity of 20/20
or less in the better eye with the use of a correcting lens. An eye
which is accompanied by a limitation in the field vision such that
the widest diameter of the visual field subtends an angle no greater
than 20 degrees shall be considered as having a central visual acuity
of 20/20 or less.
|
Section 101.1:
|
Insert: Barnegat.
|
Section 303.14:
|
Insert: May 1— October 1.
|
Section 602.3:
|
Insert: October 1 — May 1.
|
Section 602.4:
|
Insert: October 1 — May 1.
|