[Ord. No. 2010-1621 §1, 4-20-2010]
The applicant must notify the City before the commencement of construction. In addition, the applicant must notify the City in advance of construction of critical components of the stormwater practices on the approved stormwater management design plan, as determined by the City. The City may, at its discretion, issue verbal or written authorization to proceed with critical construction steps, such as installation of permanent stormwater practices based on stabilization of the drainage area and other factors.
[Ord. No. 2010-1621 §1, 4-20-2010]
The City or its representatives shall conduct periodic inspections of the stormwater practices shown on the approved stormwater management design plan, and especially during critical installation and stabilization steps. All inspections shall be documented in writing. The inspection shall document any variations or discrepancies from the approved plan, and the resolution of such issues. Additional information regarding inspections can be found in the Stormwater Design Manual. A final inspection by the stormwater authority is required before any performance bond or guarantee, or portion thereof, shall be released.
[Ord. No. 2010-1621 §1, 4-20-2010]
If a stormwater BMP is found to be inadequate by virtue of physical evidence of operational failure, even though it was built as called for in the approved stormwater management design plan, it shall be corrected by the applicant before the certificate of completion is issued. If the applicant fails to act, the City may use the performance bond or guarantee to complete the work.
[Ord. No. 2010-1621 §1, 4-20-2010]
Subsequent to final installation and stabilization of all stormwater BMPs shown on the stormwater management design plan, submission of all necessary as-built plans, and final inspection and approval by the City, the City shall issue a stormwater certificate of completion for the project. In issuing such a certificate, the City shall determine that all work has been satisfactorily completed in conformance with this Chapter.