[Ord. 5/8/1997A, § 501]
A preliminary plan is intended to establish the overall development
scheme to minimize the need for revisions of final plans.
[Ord. 5/8/1997A, § 504]
All certification shall comply with the state professional licensing
laws. All subdivisions of land shall be certified and stamped by a
registered land surveyor.
[Ord. 5/8/1997A, § 505]
Based upon the recommendation of the Township Engineer, the
Planning Commission may require an applicant for a proposed subdivision
or land development that would not be connected to a public water
system to provide a study showing that such withdrawal will not have
significant negative impact upon groundwater quantity. Such study
shall be completed by a qualified professional. See Appendix 22-I
for further requirements.
[Ord. 5/8/1997A, § 506]
Based upon the recommendation of the Township Engineer, the
Planning Commission may require an applicant to provide a study to
determine whether there will be sufficient capacity in transmission
lines and treatment to handle the expected wastewater from a proposed
development. Such study shall be completed by a qualified professional.