[Ord. 2007-6, 6/5/2007, § 501]
1. 
The Township Engineer or his municipal designee shall inspect all phases of the installation of the permanent BMPs and/or stormwater management facilities as deemed appropriate by the Township Engineer.
2. 
During any stage of the work, if the Township Engineer or his municipal designee determines that the permanent BMPs and/or stormwater management facilities are not being installed in accordance with the approved stormwater management plan, the Township shall revoke any existing permits or other approvals and issue a cease and desist order until a revised drainage plan is submitted and approved, as specified in this Part, and until the deficiencies are corrected.
3. 
A final inspection of all BMPs and/or stormwater management facilities shall be conducted by the Township Engineer or his municipal designee to confirm compliance with the approved drainage plan prior to the issuance of any occupancy permit.