A. 
Sketch plan submission for preapplication approval.
(1) 
For sketch plan submission for a minor subdivision, an application fee of $25 shall be paid at the time the required maps are submitted, prior to the meeting with the Planning Board.
(2) 
For sketch plan submission for a major subdivision, an application fee of $100 shall be paid at the time the required maps are submitted, prior to the meeting with the Planning Board.
B. 
Preliminary plat submission, major subdivision. For major subdivisions, preliminary plat submission fee shall be paid at the time of filing of the preliminary layout. The fee shall be a minimum of $50 for each subdivision plat, plus $25 per lot or dwelling unit.
C. 
Final plat submission, minor subdivision. For minor subdivisions, a final plat submission of $75 shall be paid at the time the required maps are submitted, prior to the meeting with the Planning Board.
D. 
Final plat submission, major subdivision. For major subdivisions, a final plat submission fee shall be paid at the time of filing of the final layout. The fee shall be a minimum of $25 per lot or dwelling unit.
E. 
Inspection fee. The Planning Board shall provide for the inspection of required improvements, during and after construction, to ensure their satisfactory completion and shall require the subdivider to pay an inspection fee to the municipality. Five percent of the amount of the estimated cost of required improvements and the subdivision plat shall not be signed by the Chairmen of the Planning Board unless such fee has been paid at the time of final approval.
F. 
Payee. All of the above fees shall be payable by certified, bank or cashier's check to the Village stating the specific purpose of each fee. All fees are nonrefundable.