[CC 1979 §46.300; Ord. No. 2007 §1, 4-20-1993]
All curb and gutter constructed in the City shall be constructed under the supervision and direction of the City Engineering Department within such time the Board of Aldermen shall direct and provide.
[CC 1979 §46.310; Ord. No. 2007 §1, 4-20-1993]
Prior to the issuance of a curb and gutter building permit for repair or construction of curb and gutter, general plans shall be submitted to the Engineering Department for review and approval.
[CC 1979 §46.320; Ord. No. 2007 §1, 4-20-1993; Ord. No. 2045 §1(46.320(7), 8-17-1993]
A. 
The City of Sullivan does hereby establish a cost-sharing program for placement of curb and gutter on City streets with the following guidelines:
1. 
The City will pay for fifty percent (50%) of the costs of the installed concrete curb and gutter and drive entrances (materials and labor). The City will also be responsible for other costs that are associated with the placement of the curb and gutter such as storm drainage, backfill and street widening.
2. 
Property owners on whose property the curb and gutter and street improvements will front will be responsible for fifty percent (50%) of the cost of the installed concrete curb and gutter and drive entrances (materials and labor).
3. 
The cost of fifty percent (50%) of the installed curb and gutter and drive entrances shall be levied as a special assessment against the lot, tract or parcel of ground along and in front of which said improvement is made. Said assessment shall be levied by ordinance which shall set out separately the number and title of the ordinance under authority of which the work will be done, a separate description of each lot, tract or parcel assessed, the name of the owner thereof, the number of front feet therein and the total amount thereof. Said assessment ordinance shall also authorize the City Clerk to issue said tax bills as identified in Revised Statutes of the State of Missouri.
4. 
Curb and gutters will be installed based on priority of need considering the following factors: width of the existing street, traffic volume, safety to motorists, desire for improvements by property owners and any other factors which could influence the need for improvements. The City Engineering Department shall prioritize curb and gutter projects within the City.
5. 
This program will be limited to available funding as approved in the City's annual budget.
6. 
All curb and gutter and road improvements shall be designed to conform to the present City subdivision code, if possible.
7. 
Property owners desiring to install curb and gutter adjacent to their property, on their own accord, may request the City's assistance to perform grading and street widening if the property owner pays for or furnishes storm piping and curb and guttering. These projects shall only be allowed where the curb and gutter and drainage improvements will fit into the overall street widening and drainage improvements planned for the area.
[CC 1979 §46.330; Ord. No. 2007 §1, 4-20-1993]
A. 
The Board of Aldermen may, when deemed necessary or expedient, declare it necessary to construct curb and gutter on any street within the City and have the curb and gutter constructed by a contractor or built by City crews when necessary. The cost of the improvements shall be assessed to the property owners by a special tax bill in accordance with the Revised Statutes of the State of Missouri.
B. 
The Board of Aldermen shall, by resolution, declare the work or improvement necessary, state the nature thereof and the method of payment, and refer to the plans, specifications and estimates of cost filed in the office of the City Clerk. The Board of Aldermen shall cause the resolution to be published in some weekly newspaper printed in the City for two (2) consecutive issues.
C. 
Prior to award of any construction contract, the City Engineer shall prepare and submit to the Board of Aldermen an estimate of the cost of said curb and gutter, including all labor and materials for the installation of said curb and gutter and drive entrances, which estimate shall be the price for the finished improvement; and no contract shall be let for a price in excess of said estimate.
[CC 1979 §46.340; Ord. No. 2007 §1, 4-20-1993]
A. 
All curb and gutter constructed in the City shall be in accordance with the "Unified Land Use Regulations" if at all possible (see Chapter 400 of this Code).
B. 
Variations from the current subdivision code shall only be allowed by the Board of Aldermen if there is no feasible way to construct the improvements as specified.
[CC 1979 §46.350; Ord. No. 2007 §1, 4-20-1993]
All special tax bills which are paid to the City shall be deposited into the Capital Improvements Fund.