Editor's Note: For regulations prohibiting the deposit of snow, ice or brush on public streets, see Section 3-2 Litter, subsection 3-.10, Prohibiting the Deposit of Snow, Ice, Brush in Streets; for regulations requiring sidewalk sweeping, see subsections 3-2.7 and 3-2.8.
[1973 Code § 12-10.1]
As used in this chapter:
ADMINISTRATIVE AUTHORITY
shall mean the Township Manager or his authorized deputy, agent or representative.
EXCAVATION
shall mean any opening in the surface of a public place made in any manner whatsoever.
FACILITY
shall mean pipe, pipeline, tube, main, service, trap, vent, vault, manhole, meter, gauge, regulator, valve, conduit, wire, tower, pole, poleline, anchor, cable, junction box, transformer or any other material structure or object of any kind or character, whether enumerated herein or not which is or may be lawfully constructed, left, placed or maintained in, upon, along, across, over or under any public street.
PUBLIC PLACE
shall mean any public street, way, place, alley, sidewalk, grass plot, park, square, plaza or any other similar public property owned or controlled by the Township and dedicated to public use.
SUBSTRUCTURE
shall mean any pipe, conduit, duct, tunnel, manhole, vault, buried cable or wire, or any other similar structure located below the surface of any public place.
UTILITY
shall mean a private company or corporation or municipal department engaged in providing a particular service to the general public.
[1973 Code § 12-10.2; Ord. No. 12-1986]
It shall be unlawful for any person to dig up, break, excavate, tunnel, undermine or in any manner break up any public place or to make or cause to be made any excavation in or under the surface of any public place for any purpose or to place, deposit or leave upon any public place any earth or other excavated material obstructing or tending to interfere with the free use of the public place, unless such persons shall first have obtained an excavation permit therefor from the Administrative Authority as herein provided.
No road opening permits will be issued from December 1 to March 15, except for emergency repairs, as determined by the Administrative Authority. All trenches must be completed within two (2) weeks of opening roadways. All openings must be closed before December 15. No trenches shall be opened after December 15, even though Administrative Authority issued permit prior to December 15. No roads are to open on Saturday or Sunday, except for emergency repairs, as determined by Administrative Authority.
[1973 Code § 12-10.3; Ord. No. 4-1981]
No excavation permit shall be issued unless a written application on a form provided by the Administrative Authority for the issuance of an excavation permit is submitted to the Administrative Authority. The written application shall state the name and address and principal place of business of the applicant, the authority of the applicant to occupy the public place for which the permit is sought, the location and dimensions of the installation or removal and the approximate size of the excavation to be made, the purpose of the facility and the approximate time which will be required to complete such work, including backfilling such excavation and removing all obstructions, material and debris. The amount of time permitted to complete such work shall not exceed ten (10) days. No excavation shall remain open overnight without the expressed written consent of the Administrative Authority. All excavations conducted during the working day will be backfilled and made passable during the evening hours. An extension of time may be granted by the Administrative Authority for good and sufficient reasons. The application when approved and signed by the Administrative Authority, shall constitute a permit.
An annual blanket permit for the purpose of placing, replacing or repairing any fire hydrant or public utility pole within a public place where the opening does not exceed six (6) square feet in area may be issued by the Administrative Authority.
No excavation permits shall be issued unless evidence is given by the permittee that he has contacted the existing utility companies and requested a markout of the existing utilities in the area. No excavation work shall be permitted to begin until the Administrative Authority has inspected the area of the proposed excavation and has ascertained that all utility markouts have been obtained.
[1973 Code § 12-10.4; Ord. No. 4-1981; Ord. No. 12-1986; Ord. No. 3-1988; Ord. No. 3-2005]
Fees shall be charged by the Administrative Authority for the issuance of an excavation permit. The fee for each application and permit shall be charged at the following rate(s):
a. 
Permit Fee (nonrefundable):
1. 
Excavation up to 500 square feet: $150
2. 
Excavation over 500 square feet: $300
b. 
Cash Bond. To be posted by contractor or homeowner and held by the Township for one (1) year from the date the excavation trench is inspected and approved.
1. 
Excavation up to 500 square feet: $1,000
2. 
Excavation over 500 square feet: $5,000
c. 
Inspection Fees. The Township shall furnish and the permittee shall pay for an inspector for each day from the time any pavement, street, roadway, curb or sidewalk is opened or until the construction has been restored, in the opinion of the superintendent of public works, to the condition is previously existed.
1. 
Excavation up to 500 square feet: $500
2. 
Excavation over 500 square feet: $1,000 minimum of $1.75 square foot, whichever is higher
Remaining balance to be returned to applicant after inspection of trench opening for release of cash bond.
d. 
Utilities. Public utilities operated under the supervision of the Public Utilities Commission, public utilities holding a franchise from the Township and other governmental agencies which desire to obtain permits under the provisions of this chapter may be relieved of the obligation of submitting permit fees by the administrative authority but shall post a bond, which may be the bond of the public utility solely, in the penal sum of ten thousand ($10,000.00) dollars running in favor of the Township and file it with the Township Clerk. The bond shall be conditioned upon compliance with the applicable provisions of this chapter in respect to each street opening. The utility shall post a construction observation escrow deposit of five thousand ($5,000.00) dollars which deposit will be used by the Township to cover all inspection costs. The escrow shall be replenished as necessary to maintain a five thousand ($5,000.00) dollar balance quarterly.
In lieu of the filing of the certificate of insurance for bodily injury and property damage, the public utility may file with the Township Clerk, at the same time the bond is filed, a letter certifying that it is a self-insurer and exempt from the necessity of obtaining an insurance policy pursuant to the provisions of the Statutes of the State of New Jersey.
[1973 Code § 12-10.6]
A permittee, prior to the commencement of excavation work hereunder, shall furnish the Administrative Authority satisfactory evidence in writing that the permittee has in force and will maintain in force during the performance of the excavation work and the period of the excavation permit public liability insurance of not less than one hundred thousand ($100,000.00) dollars for any one (1) person and three hundred thousand ($300,000.00) dollars for any one (1) accident and property damage insurance of not less than fifty thousand ($50,000.00) dollars duly issued by an insurance company authorized to do business in this State. The policies of insurance shall name the Township of Aberdeen as an additional insured under the policies. Permittee will further submit a surety bond or a completed works insurance policy guaranteeing the restoration of the excavation in a good and safe condition as near as may be to its original condition as determined by the Administrative Authority for a period of twelve (12) months after work has been done, usual wear and tear accepted.
[1973 Code § 12-10.7; Ord. No. 4-1981]
a. 
Guard Lights. It shall be the duty of every person cutting or making an excavation in or upon any public place to place and maintain barriers and warning devices necessary for the safety of the general public as follows:
Barriers and warning lights shall conform to the requirements set forth in the Manual on Uniform Traffic Control Devices (M.U.T.C.D.) Warning lights to indicate a hazard to traffic shall be in use from one-half hour before sunset of each day to one-half hour after sunrise on the next day.
b. 
Traffic Flow. The permittee shall take appropriate measures to assure that during the performance of the excavation work, traffic conditions shall be maintained at all times as near normal as practical so as to cause as little inconvenience as possible to the occupants of the adjacent properties and to the general public.
1. 
When traffic conditions permit, the Administrative Authority may by written approval permit the closing of streets and alleys to all traffic for a period of time prescribed by him, if in his opinion it is necessary. The written approval of the Administrative Authority may require that the permittee give notification to various public agencies and to the general public. In such cases, such written approval shall not be valid until such notice is given. The permittee shall route and control traffic including its own vehicles as directed by the Township Police Department. The following steps must be taken before any street may be closed or restricted to traffic:
(a) 
The permittee must receive the approval of the Township Police Department.
(b) 
The permittee must notify the Chief of the Fire Department and First Aid Squad of any street closed.
(c) 
Upon completion of the construction work, the permittee must notify the Police Department, the Fire and First Aid Departments before traffic is redirected to its normal flow.
(d) 
Where a flagman or flagmen are deemed necessary by the Administrative Authority and/or the Police Department, they shall be furnished by the permittee at his own expense. If, in the opinion of the Administrative Authority or the Police Department, the permittee is not maintaining sufficient traffic operation, a Township Police Officer may be directed to perform such traffic direction by the Administrative Authority and the cost of same will be borne by the permittee.
2. 
Warning signs shall be placed far enough in advance of the construction operation to alert traffic within a public street, and cones or other approved devices shall be placed to channel traffic, in accordance with the instructions of the Administrative Authority.
[1973 Code § 12-10.8]
The excavation work shall be performed and conducted so as not to interfere with access to fire hydrants, fire stations, fire escapes, water gates, underground vaults, valve housing structures, and all other vital equipment as designated by the Administrative Authority.
[1973 Code § 12-10.9]
The permittee shall maintain safe crossings for two lanes of vehicle traffic at all street intersections where possible, and safe crossings for pedestrians at intervals of not more than three hundred (300) feet. If any excavation is made across any public street, alley or sidewalk, adequate crossings shall be maintained for vehicles and for pedestrians. If the street is not wide enough to hold the excavated material without using part of the adjacent sidewalk, a passageway of at least one-half of the sidewalk width shall be maintained along such sidewalk line.
[1973 Code § 12-10.10]
Whenever the use of a substructure is abandoned, except the abandonment of service lines designated to serve single properties, the person owning, using, controlling or having an interest therein shall, within thirty (30) days after such abandonment, file with the Administrative Authority a statement in writing giving in detail the location of the substructure so abandoned. If the abandoned substructure is in the way, or subsequently becomes in the way, of an installation of the Township or any other public body, which installation is pursuant to a governmental function, the owner shall remove such abandoned substructure or pay the cost of its removal during the course of excavation for construction of the facility by the Township or any other public body.
[1973 Code § 12-10.11]
The permittee shall at all times and at his own expense preserve and protect from injury any adjoining property by providing proper foundations and taking other measures suitable for the purpose; and each permittee shall conduct and carry out excavation work in such manner as to avoid unnecessary inconvenience and annoyance to the general public and occupants of neighboring property. The permittee shall take appropriate measures to reduce to the fullest extent practicable, in the performance of the excavation work, noise, dust and unsightly debris. Between the hours of 10:00 p.m. and 7:00 a.m. he shall not use, except with the express written permission of the Administrative Authority or in case of an emergency as herein otherwise provided, any tool, appliance or equipment producing noise of sufficient volume to disturb the sleep or repose of occupants of the neighboring property.
[1973 Code § 12-10.12]
The following shall apply:
a. 
All material excavated from trenches and piled adjacent to the trench, or in any street, shall be piled and maintained in such manner as not to endanger those working in the trench, pedestrians or users of the streets, and so that as little inconvenience as possible is caused to those using streets and adjoining property. Where the confines of the area being excavated are too narrow to permit the piling of excavated material beside the trench, such as might be the case in a narrow alley, the Administrative Authority shall have the authority to require that the permittee haul the excavated material to a storage site and then rehaul it to the trench site at the time of backfilling. It shall be the permittee's responsibility to secure the necessary permission and make all necessary arrangements for all required storage and disposal sites.
b. 
All trench and tunnel excavations and construction shall conform to the safety requirements for shoring, bracing and ladders in trenches in accordance with State Trench and Tunnel Construction Safety Orders, as they now or may hereafter exist.
c. 
All material excavated shall be laid compactly along the side of the trench and kept trimmed so as to cause as little inconvenience as reasonably possible to vehicular and pedestrian traffic, or as specified by the Administrative Authority. Whenever necessary, in order to expedite the flow of traffic or to abate the dirt nuisance, toe boards or bins may be required by the Administrative Authority to prevent the spreading of dirt into traffic lanes.
[1973 Code § 12-10.13]
As the excavation work progresses, all streets shall be thoroughly cleaned of all rubbish, excess earth, rock or other debris resulting from such work. All clean-up operations at the location of such excavation shall be accomplished at the expense of the permittee and shall be completed to the satisfaction of the Administrative Authority. From time to time, as may be ordered by the Administrative Authority and in any event immediately after completion of such work, the permittee shall, at his own expense, clean up and remove all refuse and unused materials of any kind resulting from such work and, upon failure to do so within twenty-four (24) hours after having been notified to do so by the Administrative Authority, the work may be done by the Administrative Authority and the cost thereof charged to the permittee. The permittee shall also be liable for the cost thereof under the surety bond provided hereunder.
[1973 Code § 12-10.14]
The permittee shall maintain all gutters free and unobstructed for the full depth of the adjacent curb and for at least one (1) foot in width from the face of such curb at the gutter line. Whenever a gutter crosses an intersecting street, an adequate waterway shall be provided and be at all times maintained.
The permittee shall make provisions to take care of all surplus water, muck, silt, slickings, or other runoff pumped from excavations or resulting from slicking or other operations and shall be responsible for any damage resulting from his failure to so provide.
[1973 Code § 12-10.15]
The following rules shall apply:
a. 
Approved cutting of bituminous pavement surface ahead of excavations will be required by the Administrative Authority to confine pavement damage to the limits of the trench.
b. 
Saw cutting of Portland cement concrete may be required by the Administrative Authority when the nature of the work or the condition of the street warrants. When required, the depth of the cut shall not be less than one (1) inch in depth; however, depths greater than (1) one inch may be required by the Administrative Authority when circumstances warrant. Saw cutting may be required by the Administrative Authority outside of the limits of the excavation over cave-outs, overbreaks and small floating sections.
c. 
Heavy duty pavement breakers may be prohibited by the Administrative Authority when the use endangers existing substructures or other property.
d. 
Sections of sidewalks shall be removed to the nearest score line or joint.
e. 
Unstable pavement shall be removed over cave-outs and overbreaks, and the subgrade shall be treated as the main trench.
f. 
Pavement edges shall be trimmed to a vertical face and neatly aligned with the center line of the trench.
g. 
Cutouts outside of the trench lines must be normal or parallel to the trench line.
h. 
Boring or other methods to prevent cutting of new pavement may be required by the Administrative Authority.
i. 
The permittee shall not be required to repair pavement damage existing prior to excavation unless his cut results in small floating sections that may be unstable, in which case the permittee shall remove and pave the area.
[1973 Code § 12-10.16; Ord. No. 12-1986]
a. 
All backfilling shall be done with a clean cohesionless soil, such as sand or gravel, free from lumps and stone, or, if approved by the Administrative Authority, other material of equivalent compacting qualities. Broken pavement, large stones, roots and other debris shall not be used in the backfill. Such backfill shall be done in a manner that will permit the restoration of the surface to a density condition not less than that existing prior to excavation, unless otherwise specified. Backfill is required to be placed in lifts no greater than three (3) feet in depth if a Hydro Hammer or other heavy compactor is to be used; where hand compaction is to be done, the depth of the lift is limited to four (4) inches. In the latter case the number of men backfilling shall not exceed the number engaged in compacting. The Administrative Authority may require soil tests to be furnished by a recognized soil-testing laboratory or registered professional engineer specializing in soil mechanics when, in his opinion, backfill for any excavation is not being adequately compacted. In order for the resurfacing to be permitted, such tests must show that the backfill material meets the minimum requirements as prescribed by the Administrative Authority. All expenses of such tests shall be borne by the permittee.
b. 
Backfilling of a trench above five (5) feet shall be filled with quarry blend stone two (2) inch aggregate. Any backfilling below five (5) feet shall be subject to the approval of the Administrative Authority consistent with paragraph a. above. Prior to the installation of bituminous surfaces, ninety-five (95%) percent compaction of backfill materials must be achieved. Backfilling a trench requires replacement of all removed material with dirty stone, except for six (6) inches of sand around piping. Black topping shall be (6) inches of stabilized base and one and one-half (1 1/2) inches of top. All cuts to be sealed between new and old black top. All trenches shall be cut square and out to width of widest part of trench.
Prior to backfilling a trench, either the Road Foreman or the Construction Official must be notified.
[1973 Code § 12-10.17; Ord. No. 4-1981]
a. 
Permanent resurfacing of the street excavation shall be made by the permittee.
b. 
In special situations allowed by the Administrative Authority the permittee may maintain temporary pavement for a period not to exceed thirty (30) days after all backfilling is completed. Any temporary pavement used shall be kept safe for pedestrian and vehicular traffic as directed by the Administrative Authority. Temporary paving of a quality unacceptable to the Administrative Authority shall be removed and replaced with acceptable material of the type designated by the Administrative Authority.
[1973 Code § 12-10.17.1; Ord. No. 4-1981]
a. 
Prior to the placement of the base course of pavement and the surface course, the subgrade shall be inspected and approved by the Administrative Authority. All excavations shall be restored as follows:
1. 
A minimum of four (4) inches of bituminous stabilized base course, mix no. 5 or other mix design approved by the Administrative Authority shall be installed as a base course, the surface of this course being one and one-half (1/2) inches below the existing finished surface surrounding the excavation.
2. 
Over the aforementioned base course, a minimum of one and one-half (1/2) inch FABC Type I, mix no. 5 pavement shall be used as the finished riding surface.
The material shall be placed and compacted in lift thickness directed by the Administrative Authority. No material shall be placed without the proper equipment for placement and compaction being present on the site prior to the beginning of work. The equipment required to restore the roadway surface shall be dictated by the size of the opening and shall be designated by the Administrative Authority.
Any surface restoration, including the pavement surface which is not completed in accordance with the Administrative Authority's direction, shall be removed and replaced acceptable to the Administrative Authority.
[1973 Code § 12-10.18]
The maximum length of open trench permissible at any time shall be in accordance with existing ordinances or regulations or as may be specified by the Administrative Authority. No greater length shall be open for pavement removal, excavation, construction, backfilling, patching and all other operations without the written permission of the Administrative Authority.
[1973 Code § 12-10.19]
Excavations shall be completed as follows:
a. 
Prompt Completion. After an excavation is commenced, the permittee shall prosecute with diligence and expedition all excavation work covered by the excavation permit and shall promptly complete such work so as not to obstruct the public place or travel thereon more than is reasonably necessary.
b. 
Emergency Work Time Limits. When traffic conditions, the safety or convenience of the traveling public or the public interest require that the excavation work be performed as emergency work, the Administrative Authority shall have full power to order, at the time the permit is granted, that a crew of men and adequate facilities be employed by the permittee twenty-four (24) hours a day, to the end that such excavation work may be completed as soon as possible.
[1973 Code § 12-10.20]
Nothing in this section shall be construed to prevent the making of such excavations as may be necessary for the preservation of life or property, or for the location of trouble in conduit or pipe, or for making repairs, provided that the person making such excavation shall apply to the Administrative Authority for such a permit on the first working day after such work is commenced.
[1973 Code § 12-10.21]
The Administrative Authority shall make such inspections as are reasonably necessary to the enforcement of this section. The Administrative Authority shall have the authority to promulgate and cause to be enforced such rules and regulations as may be reasonably necessary to enforce and carry out the intent of this section.
[1973 Code § 12-10.22]
The section shall not be construed as imposing upon the Township or any official or employee any liability or responsibility for damages to any person injured by the performance of any excavation work for which an excavation permit is issued hereunder, nor shall the Township or any official or employee thereof be deemed to have assumed any such liability or responsibility by reason of inspections authorized hereunder, the issuance of any permit or the approval of any excavation work.
[1973 Code § 12-10.23]
The provisions of this section shall not be applicable to any excavation work under the direction of competent Township authorities by employees of the Township or by any contractor of the Township performing work for and in behalf of the Township necessitating openings of excavations in streets.
[1973 Code § 12-10.24; Ord. No. 4-1981]
Following the completion of the excavation and restoration of the roadway surface acceptable to the Township, an inspection will be made by the Administrative Authority to determine whether the roadway surface has been restored in an acceptable manner. Once the Administrative Authority has determined that the restoration is acceptable, he will notify the applicant and return the permit fees posted under subsection 19-1.4 herein. The amount returned shall be less any additional costs incurred by the Township to make the roadway safe, make repairs, perform traffic direction, emergency repairs, erection of barricades, inspection by the Township Engineer or other municipal authorities and any and all other work performed during the excavation or restoration of the roadway for which the Township has incurred an expense. The permit fee will be returned no sooner than thirty (30) days following the acceptance of the roadway restoration by the Township. This time period will be considered sufficient to assure that the roadway restoration and compaction of the subgrade has been sufficient and no setting of the roadway surface occurs.
It shall be the obligation of the permittee to notify the Administrative Authority of his requests for final inspection required for the return of a permit fee and/or surety bond.
[1973 Code § 12-10.25; Ord. No. 12-1986; Ord. No. 3-1988; Ord. No. 16-1995]
Any roads which have been resurfaced or reconstructed shall not be reopened for a period of five (5) years, except in emergency situations, as determined by Administrative Authority.
[1973 Code § 4-5.1]
All persons owning or leasing lands lying within the geographical limits of the Township shall keep all brush, hedges and other plant life growing on the lands within ten (10) feet of any roadway and within twenty-five (25) feet of the intersection of two roadways, cut to a height of not more than two and one-half (2 1/2) feet.
[1973 Code § 4-5.2]
If any person owning or leasing lands lying within the geographical limits of the Township shall fail, refuse or neglect to cut the brush, hedges and other plant life to a height of not more than two and one-half (2 1/2) feet within ten (10) days of receipt, by registered mail or personal service of notice to that effect from the Manager of the Township, the Township may provide for the cutting of the brush, hedges or other plant life by or under the direction of the proper officer.
[1973 Code § 4-5.3]
The Manager is hereby empowered to administer and enforce the provisions of this section with respect to any and all streets and roads, owned and maintained by the Township.
[1973 Code § 4-5.4]
In all cases where brush, hedges or other plant life is cut from any lands in the Township by or under direction of the Chief of Police of the Township, the Manager shall certify the cost of the cutting to the Township Council which shall examine the certificate and if found correct shall cause the cost to be charged against the lands, or in the event that such cost is excessive, to cause the reasonable cost thereof to be charged against the lands. The amount charged shall become a lien upon the lands and shall be added to and become and form part of the taxes next to be assessed and levied upon such lands, the same to bear interest at the same rate as other taxes and shall be collected and enforced by the same officers and in the same manner as taxes.
Editor's Note: Former Section 19-3, Sight Triangles, previously codified herein and containing portions of Ordinance No. 31-2005, was repealed in its entirety by Ordinance No. 9-2007.
[Ord. No. 8-2013]
a. 
Food service establishment shall mean a facility established primarily for the preparation and service of food and drink on the premises, which shall include restaurants, bakeries, ice cream parlors, taverns, delicatessens, and similar establishments.
b. 
Outside dining shall mean the utilization of sidewalk space beyond the building line to accommodate the serving of food and drink to patrons of a food service establishment, immediately fronting on that sidewalk space, which space is separated from the pedestrian area of the sidewalk by bollards.
c. 
Bollards shall mean short vertical, non-permanent, movable posts designed to separate a portion of the sidewalk area.
[Ord. No. 8-2013]
No outside dining is permitted within the Township unless and until the owner or operator of a food service establishment has fully complied with and continues to comply with all of the criteria set forth in this chapter.
[Ord. No. 8-2013]
Outside dining is permitted within the Township from May 1st through October 1st each year.
[Ord. No. 8-2013]
Outside dining is permitted where the sidewalk space fronting the building of a food service establishment is a minimum of 10 feet wide. Outside dining shall not be permitted to project into a sidewalk more than half the width of said sidewalk or more than eight (8) feet into a sidewalk, whichever is less. The remaining public portion of the sidewalk must remain free for pedestrian and emergency access.
[Ord. No. 8-2013]
a. 
Bollards must be placed on the perimeter of the sidewalk area where outside dining is permitted to separate said area from the public portion of the sidewalk.
b. 
No planters, flower boxes, menu stands, decoration items or the like may protrude into the public portion of the sidewalk.
c. 
All bollards, tables, chairs and any other items associated with outside dining shall be removed from the sidewalk at the close of each business day.
[Ord. No. 8-2013]
a. 
The owner or operator of a food service establishment seeking to have outside dining must apply for a zoning permit. If the operator of a food service establishment is a tenant, the zoning permit application must include a letter from the landlord or property owner stating that the tenant is permitted to operate outside dining on the property.
b. 
The zoning permit application must comply with all rules and regulations regarding zoning permit applications in the Township; it must be detailed and include a copy of the site plan showing the location of the proposed outside dining as well as the dimensions of the tables, chairs and the location of the bollards.
c. 
The zoning permit application must be reviewed and approved by the Township Zoning Officer with the advice of the Police and Fire Departments.
d. 
Once the zoning permit is approved, the approval is for the life of the business.
[Ord. No. 8-2013]
The food service establishment seeking to have outside dining shall file with the Township Building Department, a certificate of liability insurance in the minimum amount of one hundred thousand ($100,000.00) dollars, naming the Township of Aberdeen as an additional insured, which policy shall be kept in full force during the operation of the outside dining.
[Ord. No. 8-2013]
Any person, firm, corporation, or business violating any of the provisions of this section, shall upon conviction thereof, be subject to a fine of not less than fifty ($50.00) dollars nor exceeding one thousand ($1000.00) dollars, and each and every day in which said violation exists shall constitute a separate violation.
[Ord. No. 8-2013]
The Township may require a food service establishment to temporarily suspend its outside dining and remove all tables, chairs and other items associated with its outside dining in the event there is an emergency or if the Township is conducting any work which requires the suspension of the outside dining.