[Ord. No. 22-08, 12/1/2022]
1. The Municipal Engineer or the Engineer's designee shall inspect all
phases of the installation of the permanent BMPs and/or stormwater
management facilities as deemed appropriate by the Municipal Engineer.
2. During any stage of the work, if the Municipal Engineer or the Engineer's
designee determines that the permanent BMPs and/or stormwater management
facilities are not being installed in accordance with the approved
stormwater management plan, New Hanover Township shall revoke any
existing permits or other approvals and issue a cease-and-desist order
until a revised PCSM plan is submitted and approved, as specified
in this chapter, and until the deficiencies are corrected.
3. A final inspection of all BMPs and/or stormwater management facilities
shall be conducted by the Municipal Engineer or the Engineer's designee
to confirm compliance with the approved PCSM plan prior to the issuance
of any occupancy permit.
4. The applicant and/or developer shall be responsible for providing
as-built plans of all SWM BMPs included in the approved PCSM plan.
The as-built plans and an explanation of any discrepancies, which
were reviewed and received approval by the municipality, shall be
submitted to the municipality.
5. The as-built submission shall include a certification of completion
signed by a qualified professional verifying that all SWM BMPs have
been constructed according to the approved plans and specifications.
If any qualified professionals contributed to the construction plans,
they must sign and seal the completion certificate.