The developer shall construct streets and other improvements subject to the provisions of Article VI of this chapter. The work shall be performed in strict accordance with approved plans and Township standards and specifications.
All water, gas, electric and other pipes and conduits and all service connections or laterals shall be laid to the legal street side line, where the need therefor can be reasonably anticipated, before paving.
A. 
Notice. The Township shall be notified 48 hours in advance of the commencement of any improvement construction in order that provision may be made for inspection by the Township.
B. 
Samples of materials. Samples of materials shall be furnished to the Township in the same manner as is required of contractors under the State Highway and Sanitary Drainage Specifications.
C. 
Work subject to Township inspection. All construction shown on the plans, whether within the ultimate right-of-way lines or beyond them and whether or not guaranteed by escrow fund or bond, shall be inspected by the Township to assure conformance with the plans and agreements. Inspection costs shall be borne by the developer in accordance with § 129-65G.