[Adopted 12-5-1988 as Ord. No. 26-88]
All construction permits issued pursuant to this chapter shall expire 12 months after issuance, unless the construction is actively in progress. If an applicant has received a foundation-or-footing-only permit, but is prevented from obtaining the complete construction permit or from commencing the construction of the required foundations/footings by the imposition of the sewer connection ban pursuant to N.J.A.C. 7:14A-12.21 as issued by the New Jersey Department of Environmental Protection on August 18, 1988, then the original time limitation of said permit shall be tolled from August 18, 1988, to the expiration of the original permit, which time shall be added from the date of termination of the sewer connection ban. It is the intent of this section to provide an applicant with 12 unrestricted months to implement his permit.