The Board of Supervisors, by resolution, shall establish a schedule of fees for all applications submitted and inspections performed under this chapter. The applicant shall also be responsible for reimbursing the municipality for all of the municipality's costs incurred in reviewing the application and accompanying plans and documents, including the Township Engineer and Solicitor fees. The cost of inspections will be billed to the applicant as inspections are completed at a rate as set forth from time to time by resolution of the Board of Supervisors.
A. 
The fees required of the applicant by this chapter shall, at a minimum, cover:
(1) 
Administrative costs;
(2) 
The review of the SWM site plan by the municipality, the Municipal Engineer and other municipal consultants;
(3) 
Coordination and meetings with the applicant;
(4) 
The inspection of erosion and sediment control measures, BMPs, conveyances and other related improvements during construction;
(5) 
Review of project communications, reports, and additional supporting information;
(6) 
Other site inspections;
(7) 
The final inspection upon completion of the BMPs, conveyances, and other stormwater management facilities and related improvements presented in the SWM site plan; and
(8) 
Review of final as-built plan submission and revised calculations, and inspections as needed.
B. 
The applicant shall also reimburse all expenses incurred by the municipality for any additional work or municipal consultant fees required to enforce any permit provisions regulated by this chapter, correct violations, and ensure proper completion of remedial actions.