A grading or building permit may not be issued for any parcel or lot unless a stormwater management plan has been approved or waived by the Town Engineer as meeting all the requirements of this chapter. Where appropriate, a building permit may not be issued without:
A. 
Recorded easements for the stormwater management facility and easements to provide adequate access for inspection and maintenance from a public right-of-way;
B. 
A recorded stormwater management maintenance agreement; and
C. 
A performance bond.
D. 
Permission from adjacent property owners as necessary.
[Added 7-14-2003 by Ord. No. 247]
A nonrefundable permit fee will be collected at the time the stormwater management plan or application for waiver is submitted. The permit fee will provide for the cost of plan review, administration, and management of the permitting process, and inspection of all projects subject to this chapter. A permit fee schedule shall be established by the Town Engineer based upon the relative complexity of the project and may be amended from time to time.
Any grading or building permit issued by the Town Engineer may be suspended or revoked after written notice is given to the permittee for any of the following reasons:
A. 
Any violation(s) of the conditions of the stormwater management plan approval.
B. 
Changes in site runoff characteristics upon which an approval or waiver was granted.
C. 
Construction is not in accordance with the approved plan.
D. 
Noncompliance with correction notice(s) or stop-work order(s) issued for the construction of the stormwater management facility.
E. 
An immediate danger exists in a downstream area in the opinion of the Town Engineer.
In granting the plan approval, the Town Engineer may impose such conditions that may be deemed necessary to ensure compliance with the provisions of this chapter and the preservation of the public health and safety.