A. 
The Borough Engineer or his designee shall have full and complete authority to inspect all phases of the regulated activities undertaken at the project site, as deemed appropriate by the Borough Engineer, including the full right of ingress and egress to the property.
B. 
Any and all approved plans, which are authenticated by a registered professional engineer, shall be available on the project site at all times and shall be subject to inspection and inquiry. Engineering design notes shall accompany all plans which involve structural or mechanical measures and shall serve as supporting evidence that structures meet design standards and specifications specified herein.
C. 
During any stage of the work, if the Borough Engineer or his designee determines that the work is not in accordance with the approved plan, the Borough shall have the authority to terminate, stop or suspend activities not in compliance with such approvals and/or permits as may be issued until a revised plan is submitted and approved by the Borough, as specified in this chapter, and until the deficiencies are corrected.
D. 
A final inspection of all work shall be conducted by the Borough Engineer or his municipal designee to confirm compliance with the approved drainage plan prior to the issuance of any occupancy permit.
E. 
Frequency.
(1) 
The landowner or the owner's designee (including the municipality for dedicated and owned facilities) shall inspect SWM BMPs, facilities and/or structures installed under this chapter according to the following frequencies, at a minimum, to ensure the BMPs, facilities and/or structures continue to function as intended:
(a) 
Annually for the first five years.
(b) 
Once every three years thereafter.
(c) 
During or immediately after the cessation of a ten-year or greater storm.
(2) 
Inspections should be conducted during or immediately following precipitation events. A written inspection report shall be created to document each inspection. The inspection report shall contain the date and time of the inspection, the individual(s) who completed the inspection, the location of the BMP, facility or structure inspected, observations on performance, and recommendations for improving performance, if applicable. Inspection reports shall be submitted to the municipality within 30 days following completion of the inspection.