[Adopted 3-31-1986 ATM, Art. 37[1]; amended in its entirety 4-24-2017 ATM, Art 29]
 
[1]
Editor's Note: This bylaw also superseded former Art. III, Building Permits, adopted 12-4-1974 STM, Art. 3
An application for a building permit shall comply with the current version of the Massachusetts State Building Code.
The Selectboard shall set all building, wiring, plumbing and heating, ventilation and cooling ("HVAC") permit fees.
The following are inspections requiring notification of the Building Inspector:
A. 
Inspection of footing and foundation walls before backfilling.
B. 
Inspection of framing before drywalling.
C. 
Inspection of occupancy before entry.
Other permits required for construction are as follows:
A. 
Wiring permits.
B. 
Plumbing permits.
C. 
Furnace installation permits.